Utah Code § 11-13-320

§ 11-13-320. Air quality permitting transition process.

Year: 2026Length: 125 wordsOfficial source
(1) As used in this section: (a) "Alternative permit" means the same as that term is defined in Section 19-2-109.4. (b) "Division" means the Division of Air Quality created in Section 19-1-105. (c) "Pre-existing permit" means the air quality permit held by the operator of an existing electrical generation facility prior to any amendments associated with transitioning to a new facility. (d) "Transition permit" means the same as that term is defined in Section 19-2-109.4. (2) A project entity that holds a pre-existing permit for an existing electrical generation facility with multiple generating units, and has been issued a transition permit for a new electrical generation facility, may submit an application to the division in accordance with Section 19-2-109.4 for issuance of an alternative permit.
Utah Code § 11-13-320: § 11-13-320. Air quality permitting transition process. | Justis AI