1991-075
Procurement of modular furniture
Cite as Alaska Op. Att'y Gen. No. 1991-075
Bob Link, Director
December 17, 1991
Division of General Services
and Supply
663-92-0277
Department of Administration
465-3600
Procurement of modular
furniture (Bid #13214)
Marjorie L. Odland
Assistant Attorney General
Governmental Affairs - Juneau
You have requested our review of the bidding process
and the resulting bids submitted in response to Invitation to Bid
(ITB) #13214.
ITB #13214 is a procurement of systems modular
furniture. In particular, you seek our opinion as to whether the
procurement should be resolicited by Department of Administration
(DOA) under AS 36.30 and 2 AAC 12.
In brief, it is our opinion that certain portions of
the ITB, even after several amendments were issued thereto, were
capable of more than one interpretation and, ultimately, resulted
in bidders providing bid prices based upon misinterpretations of
the ITB instructions. Therefore, this office recommends that ITB
#13214 be cancelled and the procurement be resolicited as
provided for under AS 36.30.160(b), 2 AAC 12.190, and 2 AAC
12.860.
FACTS
The facts as we know them are as follows: On July 26,
1991, the division of general services and supply (GS&S) sent out
ITB #13214 for bids on systems modular furniture to be installed
in four different state office locations in Juneau.
Several
amendments with respect to the solicitation were sent out to
prospective bidders after questions were raised by bidders. 1/
1/ Amendment #1, dated August 20, 1991, suspended the opening of
ITB #13214 until further notice.
Amendment #2, dated September
9, 1991, set a new bid opening date and made numerous amendments
to the original ITB in response to questions from bidders.
Of
particular note are the amendments to bid price calculations and
air quality testing compliance and the bid schedule.
Amendment
#3, dated September 19, 1991, suspended the September 20 bid
opening date.
Amendment #4, dated September 23, 1991, was a
complete reissuance of the ITB, containing amendments based upon
questions
from
bidders
including
air
quality
testing
requirements. Finally, Amendment #5, dated October 7, 1991, set
a new opening bid date of October 24, 1991, and amended the air
Bob Link, Director
December 17, 1991
File #: 663-92-0277
Page 2
Bids were received from four businesses:
(1) Don's
Business Supplies; (2) Bower's Office Products, Inc.; (3) The
Office Place; and (4) Capital Office Supply.
Each of these
bidders responded to the original ITB #13214 and had received the
five amendments to the ITB noted above.
The bids were opened on October 24, 1991. The original
bid prices submitted were as follows:
$ 24,513.63
Don's Business Supplies
40,370.52
Bowers Office Products
70,988.52
The Office Place
l44,882.50
Capital Office Supply
There is an obvious, large price discrepancy in the
bids. During the review and evaluation process, the contracting
officer, Joe Ver, contacted the bidders with respect to this
discrepancy and discovered that there was confusion amongst the
bidders as to what was expected to be included in the bid price.
For example, Don's Business Supplies bid the same brand and
model of systems furniture as The Office Place; however, the bid
prices differed by nearly $30,000. Don's explained that, page 2
of Amendment #5 requested that components be included in the
calculation for each group specification to be priced on page 5
of the amendment.
However, Don's pointed out that there was no
place for a price or reference to the component listing on page
5.
Don's Business Supply then interpreted this section as
allowing an omission of the components in the overall bid price.
2/
Upon further review and evaluation of the bids, it
became apparent to Mr. Ver that three of the four bidders were
confused by the instructions for compiling the bid price as set
out in ITB #13214 and its amendments:
1) Capital Office
Supplies' bid was nearly four times greater than necessary due to
an misinterpreta
tion of Amendment #5's bid schedule, page 2; 2) Bower's Office
Products also left off several components from its bid price due
to an apparent misreading of the ITB's instructions; it also
(..continued)
quality compliance list of furniture previously tested and
approved.
2/
Don's Business Supplies' amended bid price, after the bids
were opened and clarification requested by the division, was
$45,886.
Bob Link, Director
December 17, 1991
File #: 663-92-0277
Page 3
misinterpreted the indoor air quality compliance section of
Amendment #4 as to when DOA must be notified that a previously
untested brand of furniture was "undergoing" air quality testing;
and 3) Don's Business Supplies omitted components, as noted in
the preceding paragraph.
The Office Place was the only bidder that apparently
did not need further interpretation of the bid specifications
after all amendments were made to ITB # 13214. The Office Place
submitted the highest bid price (with the exception of Capital
Office, which mistakenly quadrupled certain portions of its bid).
After review of the bids, your office asked for our
assistance in determining whether the bid should be cancelled and
resolicited.
LEGAL ANALYSIS
AS 36.30.160(b) provides:
Correction or withdrawal of inadvertently
erroneous bids before or after bid opening,
or cancellation of awards or contracts based
on
bid
mistakes
may
be
permitted
in
accordance with regulations adopted by the
commissioner. After bid opening, changes in
bid prices or other provisions of bids
prejudicial to the interest of the state or
fair competition may not be permitted.
When only one responsive bid to an ITB is received, the state may
award the bid to that bidder if the bidder is deemed responsible
and
if the procurement officer finds that the
price submitted is fair and reasonable and
that either other prospective bidders had
reasonable opportunity to respond or there is
not
adequate
time
for
resolicitation.
Otherwise the bid may be rejected and (1) new
bids or offers may be solicited.
2 AAC 12.190 (emphasis added).
Under 2 AAC 12.860, all bids may be rejected in whole
or in part if "(7) the award is not in the best interests of the
state."
Bob Link, Director
December 17, 1991
File #: 663-92-0277
Page 4
Finally, the determination by a public agency of the
responsiveness of a bid is within the agency's discretion. State
v. Bowers Office Products, 621 P.2d 11, 13 (Alaska 1980).
In the present case, it became apparent to the
contracting officer that three of the four bidders, all of whom
are experienced bidders under the state procurement process, were
confused as to the ITB's specifications. Not only did one bidder
bid too low, another bidder nearly quadrupled its bid. 3/
The
third bidder who failed to include all components in his price
bid also misunderstood the instructions with respect to the
deadline for testing of furniture for indoor air quality.
According to Amendment 4 of ITB #13214, page 7:
Contractors who supply [furniture] brands other
than
those
mentioned
above
must
provide
a
certified letter, with the bid or within ten (10)
days after a request by the Division of General
Services, from Air Quality Sciences, Inc., in
Atlanta, Georgia, which states that their systems
furniture is now undergoing the testing and that
the test results will be forwarded to the Division
of General Services as soon as the test is
completed.
If the lowest responsive and
responsible bidder is a contractor that is having
their systems tested, final award will not be made
pending receipt of testing results from Air
Quality Services, Inc.
(Emphasis added.)
Bowers Office Products (Bowers) is the only
bidder that offered a brand of furniture that was untested for
air quality.
Bowers did not submit a letter with its bid that
the furniture was undergoing testing. However, in response to a
request from the contracting officer on November 13, 1991, for
such verification, Bowers submitted a copy of a letter from Air
Quality Services, Inc. that stated that the furniture was
accepted for testing, with the tests to begin December 9, 1991.
The division received this letter on November 19, 1991, well
within the 10-day requirement of the ITB. The division, however,
3/ While bidding low is certainly the purpose behind competitive
bidding, the low bid in this case was low by nearly $30,000. As
for the high bid of Capitol Office, it certainly is not the norm
to overbid the price to a degree that the bidder loses all
competitive advantage. Bidding a price that is nearly four times
higher than necessary adds credence to our belief that the ITB
specifications were confusing.
Bob Link, Director
December 17, 1991
File #: 663-92-0277
Page 5
believed
that
Bowers'
letter
of
November
19,
1991,
was
nonresponsive to the request because the furniture was not
"undergoing" testing at the time but had merely been "accepted"
for testing. We disagree that this made the bid nonresponsive as
to this factor.
We believe that it is a reasonable
interpretation of the provision on page 7 of Amendment 4 to ITB
#13214 that the furniture was accepted for testing with a date
certain for tests to be completed.
The ITB speaks only to the
division being notified of the test results when the tests are
completed; no deadline is mentioned in the ITB as to when the
testing must be completed.
CONCLUSION
Based
upon
AS 36.30.160(b),
2
AAC 12.190(1),
and
2 AAC 12.860(7), it is our opinion that the Department of
Administration has the authority to reject all the bids,
including the one responsive bid from The Office Place, and
solicit new bids. We believe that to award the contract to The
Office Place would be competitively unfair to the other three
bidders whose bids were based upon reasonable but erroneous
readings of the specifications intended in ITB #13214 that
ultimately affected bid prices to their detriment.
It would also be competitively unfair to The Office
Place to recalculate the other three bidders' prices by either
adding or subtracting various components from their bid prices
based upon the manufacturer's current published suggested retail
list price, because it is unknown whether a bidder would have
chosen a certain-priced item out of a field of many. Given that
Don's Business Supplies and The Office Place bid the same brand
of systems furniture, the process could be tainted because the
contracting officer may select certain priced components that
could ultimately put one bidder at an obvious competitive
advantage or disadvantage over the other.
If this case concerned a minor technical defect or
irregularity or a minor recalculation that would not affect the
substance of a bid or give one bidder a competitive advantage
over another, then it may be appropriate for the division to
correct an inadvertent error. See Chris Berg, Inc. v. State, 680
P.2d 93, 94 (Alaska 1984). However, that is clearly not the case
here. The division would have to completely reconstruct three of
the four bids, which undoubtedly involves more than minor
recalculations and, in our opinion, goes beyond the Alaska
Supreme Court's ruling in Chris Berg, Inc..
Please contact us if you need further assistance.
Bob Link, Director
December 17, 1991
File #: 663-92-0277
Page 6
MLO:ck
cc: Joe Ver, Contracting Officer
Department of Administration