1979-0189
Alabama Attorney General Opinion 1979-0189
Cite as Ala. A.G. Opinion No. 1979-0189
WALTER S. TURNER
CHIEF ASSISTANT ATTORNEY GENERAL
LEE L. HALE
DEPUTY ATTORNEY GENERAL
WILLIAM M. SEHURS. JR .
EXECUTIVE ASSISTANT
-OFFICE OF THE ATTORNEY GENERAL
79- 00119
L41:1?-1
CHARLES A. GRADDICK
ATTORNEY GENERAL
STATE OF ALABAMA
MAY 3 1979
•
JANIE NOBLES
ADMINISTRATIVE ASSISTANT
ADMINISTRATIVE BUILDING
64 NORTH UNION STREET
MONTGOMERY, ALABAMA 36130
AREA (205(. 836-51 SO
Honorable Harry M. Philpott
President
Auburn University
Auburn, Alabama 36830
Public Works - Contracts - Auburn
University
Contract for significant additional work
arising during performance of renovation
contract must be awarded pursuant to
sealed competitive bids.
Dear Sir:
part
This letter is in response to your letter of recent date, the pertinent
of which is as follows:
"Your opinion is requested with respect to the following
question:
Under the specific facts and circumstances herein
described, may Auburn University accomplish the
renovation and repair of a fire-damaged building
located on its campus by Change order to existing
contract or by negotiated supplemental contract?
After advertisement and receipt of sealed bids, Auburn
University entered into a contract with the low bidder,
Giddens and Huff Construction Company of Auburn, Alabama,
for the renovation and restoration of Hargis Hall, located
on the Auburn University campus, for the amount of
$501,669. Work under the contract was commenced by the
contractor. However, after approximately one-third of
the work was completed, a fire of now undetermined origin
destroyed the work done by the contractor andolso sub-
stantially damaged the existing structure.
c
Honorable Harry M. Philpott
- 2
"sit tiara, Alabama
•
Funds remaining on hand under the construction contract
and proceeds from the builder's risk insurance policy
carried by the contractor are sufficient to restore and
complete work under the renovation contract. However,
this work cannot be done until fire damage to the
existing structure in the approximate amount of $180,000
is repaired. Funds for this purpose are available from
fire insurance proceeds and from fees contained in the
institution's building fund.
Auburn University desires to repair the damage to Hargis
Hall and to proceed with its renovation and restoration
in accordance with its original contract by change order
or by negotiated supplemental agreement with Giddens and
Huff Construction Company. The existing condition of
the building creates a risk of further substantial damage
to the property and of injury in the event of collapse,
and it is felt that this situation is one of emergency
affecting public health and safety. Moreover, repairing
damage to the existing structure through the normal
procedure of advertisement and receipt of sealed bids would
require termination of the original contract, when the
contractor is ready, willing land able to continue. This
contractor has a unique knowledge of the building based
on his work on the premises under the existing contract.
Termination and proceeding through a new contract would
involve substantial additional expense, including the
expense of re-enforcing and protecting the building during
the period required for solicitation of new bids, new wage
rates and increased building costs. Further, there is
now paid for and stored by Auburn University construction
material ordered for the project which was ordered prior
to, but delivered subsequent to, the fire of an approximate
value of $50,000."
Obviously, Auburn University could not anticipate that Hargis Hall would
suffer fire damage that would have to be repaired during the performance of the
renovation contract which had been awarded to the low bidder. However, it is my
opinion that the fire damage repair work is a separate and distinct item from the
renovation contract. I do not believe that it constitutes an emergency affecting
public health or safety which would permit the award of a contract without
competitive bids.
In an opinion of the Attorney General dated August 13, 1968 to Honorable
Dennis Porter, City Attorney; Town of Chatom, the following conments were made
concerning a.ditional work:
. . In general, but subject to certain limitations and
exceptions, statutes requiring the letting of public contracts
to the lowest bidder are regarded as rendering invalid and
unenforceable subsequent agreements to pay on to whom a
Honorable Harry M. Philpott
- 3
Auliarn, Alabama
public contract has been duly awarded additional compen-
sation for extras or additional labor and materials not
included in the original contract, at least where the
additional compensation exceeds the amount for which
public contracts may be made without competitive bidding.
See annotations contained in 135 AIR 1266, et seq. It
has also been said that public authorities cannot enter
into a contract with the lowest bidder containing
substantial provisions beneficial to him not included
in or contemplated in the terms and specifications upon
whieh bids were invited; the contract which they execute
must be the contract offered to the lowest responsible
bidder by advertisement and any contract entered into
containing substantial provisions beneficial to the bidder
which were not included in the specifications is void.
Any other course would prevent real competition, lead to
9 favoritism and fraud and defeat the purpose of the law
in requiring contracts to be let upon bids made upon
advertised specifications. See Section 46 of Public Works
and Contracts contained in 43 Am. Juris. 789. Some
examples noted are such as the holding of the court in
Ely v. Grand Rapids, 84 Mich:-336, 47 NW 447, providing
that paving contracts could not be expanded by supplemental
agreement to include gutter paving, this being a distinct
matter wholly outside the original contract. Also, it was
held in Sadler v. Eureka Co., 15 Nev. 39, that changes
could not be considered as separate and distinct it®s
within a dollar amount for competitive bid when the aggregate
total of all changes to the contract exceeds the amount
required for competitive bids. In a ruling by this office,
reported in Quarterly Report of the Attorney General, Volume
53, page 37, it has been held on request by the Highway
Director for an opinion regarding addition by supplemental
agreement of 1.8 miles to a construction contract that such
entering into a supplemental agreement on an entirely new
project would be in the very teeth of Title 50, Section 1,
Code of Alabama 1940, requiring competitive bids on public
improvements."
Although it may be uore convenient to Auburn University to award the fire
damage repair contract to the firm which was low bidder for the renovation and
restoration contract, I know of no legal authority whereby this could be done.
Since the fire damage repair contract greatly exceeds $500.00, it is my opinion
that it rust be awarded by sealed competitive bids as required by the public works
statute, Code of Alabama 1975, Section 39-2-2.
If I may be of any further assistance to you in this matter, please let
me know.
Very truly yours,
CHARLES A. GRADDICK
Attorney General
By -
MN E. LAWLEY
Assistant Attorney General
DEL/dc