22 CAR § 101-108
22 CAR § 101-108. Timelines
Length: 149 wordsOfficial source
(a) The following timelines shall be followed for the development of qualified projects.
(b) If an RPE has requested and been approved for an accelerated timeline, the expedited timeline shall be followed for the selection of a qualified project.
(c) The days listed are calendar days.
Event
Standard Timeframe
Expedited Timeframe
Affected local jurisdiction and other public entity notification
prior to RFP issuance
60 days
30 days
Submittal of RFP to TSS prior
to publication
60 days
30 days
Duration of RFP publication
from advertisement to response deadline
45-120 days*
45-90 days*
Execution of Comprehensive Agreement
180 days** after RFP response deadline
120 days**
*May be extended by the RPE up to an additional one hundred twenty (120) days with the consent of the Department of Shared Administrative Services.
**This deadline may be extended up to three hundred sixty-five (365) calendar days by mutual written agreement of both parties.