22 CAR § 111-1706. Project schedule

Length: 214 wordsOfficial source
(a) Refer to 22 CAR § 111-410 for basic schedule requirements. (b)(1) For projects utilizing a fast track methodology, the design professional shall assist the agency in developing a request for proposals package to be utilized in the selection process for the contractor or construction manager. (2) The RFP shall be submitted to the Design Review Section and Construction Section for review and approval prior to issuing to potential contractors. (3) The requirements of the RFP shall closely match the requirements of a schematic design plan review submittal. (4) Include appropriate specifications for the desired building materials and equipment. (c)(1) The department shall submit a schedule of activities listing the proposed milestone submittal dates to the Building Authority Division including but not limited to the following: (A) Submittal of request to begin selection of the design professional; (B) Submittal of request to select commissioning agent, if applicable; (C) Submittal of contractor selection RFQ document for review and approval; (D) Submittal of design professional services contract for approval; (E) Submittal of commissioning agent services contract, if applicable; (F) Submittal of contractor contract; (G) Submittal of first plan review; and (H) Beginning date of construction phase and expected duration of construction. (2) Refer to 22 CAR § 111-1707(e) for submittal schedule requirements using fast track construction.
22 CAR § 111-1706: 22 CAR § 111-1706. Project schedule | Justis AI