26 CAR § 212-302
26 CAR § 212-302. Minimum expected production levels for in-house reappraisals
Length: 63 wordsOfficial source
(a) Manpower needs necessary for any reappraisal are calculated based on:
(1) Known parcel numbers;
(2) Working days available; and
(3) Anticipated production levels per worker.
(b) Production levels shown in 26 CAR §§ 212-303 – 212-306 are minimum production levels, per worker, per day, to be used for the preparation of appraisal budgets for those counties which choose to perform in-house reappraisals.