8 CAR § 41-1405
8 CAR § 41-1405. Best available retrofit technology requirements
Length: 139 wordsOfficial source
(a) SWEPCO Flint Creek Power Plant (AFIN 04-00107) shall comply with best available retrofit technology requirements for particulate matter at SN-01 by meeting the existing permitted particulate matter emission limit as of October 15, 2007.
(b) [Reserved].
(c) [Reserved].
(d) [Reserved].
(e) Entergy Arkansas, Inc. White Bluff (AFIN 35-00110) shall comply with best available retrofit technology requirements for particulate matter at Unit 1 (SN-01) and Unit 2 (SN-02) by meeting existing permitted particulate matter emission limits for the respective units as of October 15, 2007.
(f) [Reserved].
(g) [Reserved].
(h) [Reserved].
(i) [Reserved].
(j) [Reserved].
(k) [Reserved].
(l) Entergy Arkansas, Inc. Lake Catherine (AFIN 30-00011) shall comply with best available retrofit technology requirements for particulate matter when burning natural gas at Unit 4 Boiler (SN-03) by meeting the existing permitted particulate matter emission limit as of October 15, 2007.