R14-2-2624

R14-2-2624. Disconnect Switch Requirements

Last amended: 2020Length: 61 wordsOfficial source

Cite as Ariz. Admin. Code § R14-2-2624

A. If required by a Utility, a Customer shall install and maintain a visual-open, manually operated, load break Disconnect Switch that completely opens and isolates all ungrounded conductors of the Generating Facility from the Distribution System. For multi-phase systems, the Disconnect Switch shall be gang- operated. B. A Utility may impose additional requirements for a Disconnect Switch in its Interconnection Manual.