R2-7-503. Procurement of Construction Using Alternate Project Delivery Method
Cite as Ariz. Admin. Code § R2-7-503
The agency chief procurement officer may use an alternate project delivery method if it is in the best interest of the state pursuant to A.R.S. §§ 41-2578 and 41-2579, based on the following factors: 1. Cost and cost control method, 2. Value engineering, 3. Market conditions, 4. Schedule, 5. Required specialized expertise, 6. Technical complexity of the project, or 7. Project management.