R2-7-704. Refusal to Submit Cost or Pricing Data

Last amended: 2006Length: 84 wordsOfficial source

Cite as Ariz. Admin. Code § R2-7-704

A. If an offeror fails to submit cost or pricing data in the required form and within the time-frames required, the agency chief procurement officer may reject the offer. B. If a contractor fails to submit data to support a contract modification in the form required and within the time-frames required, the agency chief procurement officer may: 1. Reject the contract modification; or 2. Set the amount of the contract modification subject to the contractor’s rights under Article 9 of the Arizona Procurement Code.