R.C.S.A. § 25-68h-2
Floodplain management standards
Cite as Conn. Agencies Regs. § 25-68h-2
(a) All state activities shall conform to the Federal Emergency Management Agency National
Flood Insurance Program requirements, specifically Part 60 -Criteria For Land Management
and Use, Subpart A Sections 60.3, 60.4 and 60.5.
(b) The following restrictions shall pertain to all new and substantially improved structures
located within the floodplain.
(1) Structures shall not be designed for human habitation unless elevated with the lowest
floor one foot above the level of the base flood.
(2) Structures and all stored materials which may result in damage to other structures,
restriction of bridge openings or other narrow sections of the stream or river shall
be anchored or restrained to prevent them from floating away.
(3) Service facilities such as electrical and heating equipment shall be constructed at
or above the elevation of the base flood or floodproofed with a passive system.
(4) Structures located within a "coastal high hazard area" as defined in 44 CFR Part 59
shall be elevated on adequately anchored pilings or columns and securely anchored
to such piles or columns such that the lowest portion of the structural members of
the lowest floor (excluding the pilings or columns) is elevated to one foot above
the base flood and certified by a registered professional engineer or architect that
the structure is securely anchored to piling or columns in order to withstand velocity
waters and hurricane wave wash.
(5) No new structures shall be permitted on undeveloped coastal barrier beaches as designated
by the Federal Emergency Management Agency (FEMA).
(6) All water supply equipment shall be designed to prevent flood waters from entering
and contaminating the system.
(7) All sanitary sewer collection systems located in the floodplain must have watertight
manhole covers and if equipped with vents, shall extend above the elevation of the
base flood.
(c) The following restrictions shall pertain to all filling, dumping, construction, excavating,
and other activities which change the topography within the floodplain.
(1) No filling, dumping or construction or other activity shall be allowed which would
increase the elevation of the base flood by more than one foot or adversely affect
the hydraulic characteristics of the floodplain unless the proposed filling is fully
compensated for by excavation in or contiguous to the filled area.
(2) No filling, dumping, construction or excavation will be allowed if these changes will
result in a concentration of the natural flow of water such as to cause or increase
drainage, erosion or sediment problems.
(3) Any fill placed in the floodplain shall not be greater than that which is necessary
to achieve the intended purpose as demonstrated by a plan showing the uses to which
the filled land will be put and the final dimensions of the proposed fill or other
materials.
(4) Such fill or other material shall be protected against erosion as discussed in the
Connecticut Guidelines for Soil Erosion and Sediment Control (1985), as may be amended.
(5) Any activity within a floodway designated by FEMA which would result in an increase
of the elevation of the base flood or ten year flood profile is prohibited.
(6) The placement of fill in areas of high velocity flow or at the outside edge of a migrating
river bend is discouraged.
(d) The following restrictions shall pertain to the storage of materials and equipment
within the floodplain.
(1) The storage of materials that are buoyant, hazardous, flammable, explosive, soluble,
expansive radioactive or which could be injurious to human, animal or plant life is
prohibited below the elevation of the base flood for a critical activity.
(2) Other material or equipment may be stored below the elevation of the base flood for
a critical activity provided that such material or equipment is not subject to major
damage by floods, and provided that such material or equipment is firmly anchored,
restrained or enclosed to prevent it from floating away.