R.C.S.A. § 29-232-50
New power boiler installations
Cite as Conn. Agencies Regs. § 29-232-50
(a) No power boiler, except reinstalled boilers and those exempted by statute, shall be
installed in this state after November 15, 1957, unless it has been designed, constructed,
inspected by a National Board commissioned inspector and stamped in conformity with
the provisions of Section I of the latest edition of the American Society of Mechanical
Engineers Boiler and Pressure Vessel Code, entitled "Power Boilers" and with addenda
and amendments thereto, approved by the society and adopted by the commissioner as
safe requirements for the construction, installation and inspection of boilers in
the interest of public safety, as such rules, addenda or amendments thereto shall
appear on file with the secretary of state.
(b) When a stationary power boiler is moved and reinstalled, the attached fitting and
appliances shall comply with these rules and regulations for new installations.