Cite as Conn. Agencies Regs. § 8-119jj-28

(a) A developers' fee may be established at up to 10% of the total development cost, less the cost of land, or $100,000, whichever is less. (b) The fee schedule shall be determined as follows: Percent of Fee Key Event 10% Preliminary Application 15% Final Application 25% Construction Start 50% Construction Completion (c) Developer's fees are earned based on the schedule established for completing key events in the development process, as approved by the Commissioner. (d) Developers shall only earn a fee for those key events that are completed according to the established schedule. Developers may not be entitled to earn a fee for key events completed after the established schedule. Developers shall earn, but not receive, any fee, until completion of the housing development.