R.C.S.A. § 16-19cc-2
Quarterly review of nuclear generating capacity (Repealed)
Cite as Conn. Agencies Regs. § 16-19cc-2
(a) The Department, in its quarterly fossil fuel adjustment hearing under the provisions
of section 16-19b of the general statutes for electric public service companies, shall
review the nuclear generating capacity of each company, and, where fifty per cent
or more of a company's nuclear generating capacity has been out of service for the
calendar quarter being reviewed, shall make a determination as to whether or not the
company has fulfilled its public service responsibilities under titles 16 and 16a
of the General Statutes. This determination shall be in addition to any other reviews
and determinations the Authority may make regarding nuclear outages.
(b) Upon a determination that the electric public service company has not fulfilled its
public service responsibilities as a result of outages of its nuclear generating capacity
and the cause of such outages was not beyond the control of the plant operator of
the unit for which replacement power costs are sought, the Department may prohibit
the electric public service company from recovering through its rates or charges,
directly or indirectly, all or any portion of its additional replacement power costs
associated with the purchase of electricity from other sources through its rates or
charges. The Department shall utilize adjustments to base rates, and/or the fossil
fuel adjustment clause and/or the generation utilization adjustment clause to adjust
for the replacement power costs of outage(s).