R.C.S.A. § 16-1-67
Special components (Repealed)
Cite as Conn. Agencies Regs. § 16-1-67
In addition to the requirements hereinabove set forth in part 1 of this article each
application for the approval of the commissioners under chapters 278, 279 and 280
of the general statutes shall contain the following data, either in the statement
of application or as exhibits annexed thereto and accompanying the application:
(a) If such application is for an approval for any purpose connected with the temporary
or permanent layout, construction, completion, extension, alteration, improvement
or removal of any railroad, depot, or any other structure, fixture, or facility of
any description whatsoever that is accessory to any operation conducted by the railroad
company, then there shall be annexed to the application:
(1) All agreements and other instruments permitting or otherwise authorizing the implementation
of the purpose for which said approval is sought.
(2) Plan of the proposed work hereinabove described, which plan shall have been prepared
in accordance with the standards and specifications of the American Railway Engineering
Association.
(3) Statement setting forth evidence of applicant's compliance with the insurance requirements
established by the railroad company for said work.
(b) If such petition or application is for any purpose set forth in general statutes sections
16-103, 16-104, 16-109, 16-113, 16-114, 16-117, 16-134, 16-135, 16-136, 16-137, 16-138,
or 16-139, then the petitioner or applicant shall annex to the application:
(1) Statement describing in detail the location of the site that is the subject of the
petition or application.
(2) Where applicable, any plan, engineer's drawing, or plot plan necessary to describe
the proposal that is the subject of the petition or application. Any plan for work
on any portion of the railroad or any facility connected with the operation thereof
shall conform to the standards and specifications of the American Railway Engineering
Association.
(3) Where applicable, an itemized statement of the cost of implementing the proposal in
the event that approval is granted by the commissioners.