R.C.S.A. § 16-271-17
Final pressure tests (Repealed)
Cite as Conn. Agencies Regs. § 16-271-17
The commission shall be notified at least twelve hours prior to the commencement of
any pressure test of a gas pipe line. Such pressure tests shall be of at least twelve
hours' duration except when the test is hydrostatic, in which case it shall not be
less than four hours. Prior to the test of pipe lines, appropriate town officials
shall be notified where and when such tests are to be made in order that adequate
and proper police protection may be provided. A section of pipe line shall be tested
hydrostatically or with air or an inert gas in accordance with the testing requirements
and procedures set forth in the standard code prior to placing such section of pipe
line into service.