R.C.S.A. § 16-271-21
Certification (Repealed)
Cite as Conn. Agencies Regs. § 16-271-21
Within thirty days subsequent to the construction or major reconstruction of any of
its pipe line facilities, every company shall certify to the commission that the pipe
line has been tested and meets the requirements of the standard code and regulations
prescribed by the commission for the stated maximum service pressure at which it will
be operated. The certification shall also state (1) pressure at which the lines were
tested, (2) computations of maximum allowable working pressure in accordance with
the provisions of the standard code and (3), in the event of air or inert gas tests,
measurements of leakage obtained by the testing.