27 DCMR 5030
5030. TIME AND MATERIALS CONTRACTS AND LABOR HOURS CONTRACTS
Cite as D.C. Mun. Regs. tit. 27, ยง 5030
5030 TIME AND MATERIALS CONTRACTS AND LABOR HOURS CONTRACTS
5030.1 Time-and-materials contracts provide for acquiring supplies or services on the basis of:
(a) Direct labor hours charged at loaded fixed hourly rates, which include overhead, general and administrative expenses, and profit; and
(b) Materials (which may be charged either at their actual cost or at fixed unit prices, as specified in the contract).
5030.2 A labor hours contract is a time-and-materials contract that does not involve materials.
5030.3 Both time-and-materials contracts and labor hours contracts must specify a ceiling (not-to-exceed) amount.
SOURCE: Final Rulemaking published at 65 DCR 4406 (April 20, 2018); as amended by Final Rulemaking published at 68 DCR 011740 (November 5, 2021).
District of Columbia Municipal Regulations
Contracts and Procurement
27 DCMR ยง 5030