3045. REDESIGN RESPONSIBILITY FOR DESIGN ERRORS OR DEFICIENCIES
Cite as D.C. Mun. Regs. tit. 8-B, ยง 3045
3045 REDESIGN RESPONSIBILITY FOR DESIGN ERRORS OR DEFICIENCIES
3045.1 The architect-engineer firm shall make necessary corrections at no cost to the University if the designs, drawings, specifications, or other items or services furnished by the firm contain any errors, deficiencies, or inadequacies.
3045.2 If the CCO does not require a firm to correct errors, the CCO shall include a written statement of the reasons for that decision in the contract file.
SOURCE: Final Rulemaking published at 57 DCR 2630 (Mar. 2010).