156 NLRB 634
Union Carbide Corp.
634
DECISIONS OF NATIONAL LABOR RELATIONS BOARD
DETERMINATION OF DISPUTE
Pursuant to Section 10(k) of the National Labor Relations Act,
as amended, and upon the basis of the foregoing findings and the
entire record in this proceeding, the National Labor Relations Board
hereby makes the following Determination of Dispute.
1. Maintenance electricians employed by Vickers Incorporated,
Division of Sperry Rand Corporation, who are represented by Inter-
national Union of Electrical, Radio and Machine Workers, AFL-CIO,
Local No. 792, are entitled to perform the installation of test stands
and other related production equipment in the new addition to the
Employer's plant at Jackson, Mississippi.
2. International Brotherhood of Electrical Workers, Local 480, is
not entitled to force or require Vickers Incorporated, Division of
Sperry Rand Corporation, its successors or assigns, to assign any of
the above work to employees it represents.
3. Within 10 days from the date of this Decision and Determination
of Dispute, International Brotherhood of Electrical Workers, Local
480, shall notify the Regional Director for Region 15, in writing,
whether it will or will not refrain from forcing or requiring Vickers
Incorporated, Division of Sperry Rand Corporation, its successors or
assigns, by means proscribed by Section 8(b) (4) (D) of the Act, to
assign the above-described work to employees of such Company
represented by such Union.
Union Carbide Corporation Chemicals Division and International
Association of Machinists, AFL-CIO, Petitioner and Local
Union 625, United Association of Journeymen and Apprentices
of the Plumbing and Pipefitting Industry of the United States
and Canada, AFL-CIO, Petitioner.'
Cases Nos. 9-RC-6285,
9-RC-6295, and 9-RC-6296.
January 5,1966
DECISION AND DIRECTION OF ELECTION
Upon separate petitions duly filed under Section 9 (c) of the National
Labor Relations Act, as amended, a consolidated hearing was held
before Hearing Officer Mark Fox. The Hearing Officer's rulings made
at the hearing are free from prejudicial error and are hereby affirmed.
Following the hearing and pursuant to Section 102.67 of the National
Labor Relations Board Rules and Regulations, Series 8, as amended,
by direction of the Regional Director for Region 9 these cases were
transferred to the Board for decision.
Briefs have been filed by the
Employer and the Plumbers 2
1 The petitioning unions are hereinafter referred to as Machinists and Plumbers.
2 The Employer's request for oral argument is hereby denied as the record and briefs
adequately present the issues and positions of the parties.
156 NLRB No. 61.
UNION CARBIDE CORPORATION CHEMICALS DIVISION
635
Upon the entire record in these cases, the Board finds :
1. The Employer is engaged in commerce within the meaning of
the Act.
2. The labor organizations involved claim to represent certain
employees of the Employer.
3. Questions affecting commerce exist concerning the representation
of employees of the Employer within the meaning of Section 9 (c) (1)
and Section 2 (6) and (7) of the Act.
4. There is no history of bargaining at the Employer's Institute
plant at Institute, West Virginia, where it is engaged in the production
of synthetic organic chemicals.
The Units Sought
In Case No. 9-RC-6285 the Machinists seeks a production and main-
tenance unit of approximately 1,400 employees. In Case No. 9-RC-
6296 the Plumbers seek a unit composed of all plumbing-pipefitter
employees, including instrument repairmen, welders, and helpers
and/or apprentices, approximating 170 employees 3
At the hearing, the Plumbers contended that the three classifica-
tions petitioned for constitute a homogeneous group of skilled
craftsmen appropriate for representation in a unit by themselves.
Alternatively, it contended that separate units of each of the three
classifications or any combinations thereof are appropriate for pur-
poses of collective bargaining.
Additionally, the Plumbers sought to
intervene in the Machinists' petition and seek inclusion on the ballot in
the
production and maintenance election.
This intervention is
opposed by both the Machinists and the Employer on the ground of
inconsistency with the petition for craft units.
The Employer and
the Machinists also oppose the establishment of any craft units, con-
tending that only a single production and maintenance unit is
appropriate.
The Employer's Operations
At its Institute plant, the Employer produces more than 200 syn-
thetic organic chemicals, most of which are toxic, flammable, or explo-
sive.
Of these 81, are intermediates, indispensable to the manufacture
of certain other end-product chemicals, but which themselves may also
be utilized for sale.
There are approximately 1,406 hourly rated employees at the plant
who would normally comprise a production and maintenance unit.
3In Case No . 9-RC-6295 the Plumbers also petitioned for a unit of about 35 insulator
employees , which petition , in their brief, they ask to have "dismissed."
We treat this
as a request to withdraw the petition and grant it
636
DECISIONS OF NATIONAL LABOR RELATIONS BOARD
Of these, 564 are attached to the maintenance department.
The
remainder are found in operations, equipment, testing and inspection,
and shipping. It is only from among maintenance department person-
nel that the Plumbers wish to extract a craft unit.
The Employer's operations are comprised of 30 independent operat-
ing units, each supervised by a department head, spread over 415
acres, and divided into 5 field maintenance areas. There are, in addi-
tion, two maintenance shop areas, not immediately involved in the
operational process.
The field areas are again subdivided into one or
more zones.
Each field area has its own complement of maintenance
personnel permanently assigned, which includes pipefitters, electri-
cians, boilermakers, machinists, laborers, or whatever other classifica-
tions are essential to the operation of the particular field area involved.
Each field area is headed by a maintenance general foreman who has
mainly administrative responsibility.
Operationally, maintenance is
broken down into zones, each headed by a maintenance foremen who is
directly responsible to the department head (or heads, if there is more
than one operating unit in the zone) having operational unit responsi-
bility.
Department heads deal directly with maintenance foremen and
must maintain close persona] contact because of the unit operation.
The department head also exercises supervisory authority over the
operating foreman, and must integrate the production and mainte-
nance functions in order to satisfy the operational needs of the plant.
The operating foreman oversees the work of operators, shift utility
mechanics, and shift instrument repairmen.
The maintenance fore-
man has under his control a multicraft group operating on a zone basis.
The maintenance foreman himself is most likely proficient in only
one of the craft classifications, yet the various craft classifications
report to him and not to a foreman expert in their own crafts.
Basic raw materials in the plant are natural gas, napthalene, and
chloroform.
The natural gas is further reduced to three major com-
ponents : ethylene, propylene, and butadiene.
Production of the 81
chemicals above noted is accomplished only through a complex pro-
cedure utilizing almost entirely each of the 30 operating units, among
which there is an interdependency and integration vital to the com-
plete operation.
The production process so described is denoted by
the Employer as a "unit operation," a term of art of industrial engi-
neering applied to a methodology in the operation of an industrial
plant.
The operations of the plant are continuous and, by their nature,
permit no interruption once begun. Storage of intermediates or end
products is restricted because of chemical instability and toxicity.
Many of the products are subject to rapid decomposition, which can
result in autoreactive explosions.
Because of these factors, the entire
UNION CARBIDE CORPORATION CHEMICALS DIVISION
637
process advances in closed pipe systems.
Moreover, the continuous
operation of each operating unit is coordinated with and dependent
upon the flow of one or more of the 200 in-process chemicals con-
stantly being produced.
Each operating unit is also dependent upon a steady supply of
electricity, water, steam, and nitrogen.
Maintenance personnel, who
are assigned to specific areas, and, as needed, to zones within the area,
are responsible for the maintenance and repair of the two electrical
power plants and the substations located in many areas and zones.
Water, used for cooling, is constantly pumped through all areas of the
plant.
Each minute, 280,000 gallons of water are used by the plant.
The responsibility for maintaining and repairing this system lies with
the maintenance department on area and zone bases. The steam and
nitrogen systems too are absolutely essential for the continuous opera-
tion of the plant, the servicing of which systems falls to maintenance
personnel in the zones where they are assigned.
Case No. 9-RC-6296
Seeking to represent separate craft classifications in either a single
unit, in separate units , or in combinations thereof, the Plumbers con-
tend that the right of craftsmen to separate representation should
not be denied merely because of the Employer's highly integrated
production process.
The 89 pipefitters, 33 welders, and 50 instrument
repairmen sought by the Plumbers comprise a total of 172 out of 564
in the maintenance department.
Typically, the performance of maintenance work at the Employer's
plant arises in the following manner:
A written work request origi-
nates with a department head or his technical staff and is forwarded
to a maintenance analyst operating in a zone.
He in turn confers
with the maintenance foreman in the zone where the work is to be per-
formed, discussing any special requirements of the job or hazards
that might arise.
The maintenance analyst then details the procedure
to be followed and the number and type of maintenance people to be
used, also apprising the maintenance coordinator of his requirements,
so that a proper balance of maintenance manpower can be maintained
at all times .
While this is going on, the operating foreman makes
preparations for the eventuality of the maintenance work by shutting
down, bypassing, or substituting for the equipment that is to be serv-
iced.
After checking with the operating foreman, the maintenance
foreman then approves the commencement of the repair or mainte-
nance.
On completion, the operator will check the equipment in the
presence of the maintenance employees , at which time additional
repairs, if necessary, will be made .
Because of the highly integrated
nature of the operation , each department head assigns priorities to
638
DECISIONS OF NATIONAL LABOR RELATIONS BOARD
the maintenance work. "A" priority is of a highly urgent nature and
must be completed within a prescribed time; "B" priority permits
delay for a limited period only; and "E" requires immediate attention.
About 25 to 30 percent of the maintenance work is of the last variety.
The journeymen employees in the classifications sought by the
Plumbers are known as group A mechanics, with a top rate of $3.57.
Apprentices, known in the plant as trainees, start at $3.44.
Operators,
on the other hand, receive a $3.50 top rate, but are also entitled to a
rotating shift differential of 111/3 cents.
All employees begin as trainees at a base rate and progress to top
rate within varying periods up to 48 months.
Rate increases are
granted at 3-month intervals during the first year, and at 6-month
intervals thereafter until the top rate is achieved.
All employees are
paid weekly by the same paymaster, although maintenance personnel
punch an area clock while operating personnel punch different clocks.
Fringe benefits and employee services are provided uniformly to all
hourly employees.
The same seniority provisions are applicable to
all hourly employees.
The plant has three rotating shifts for produc-
tion employees : 7 a.m. and 2 and 11 p.m. The great majority of main-
tenance employees work a 7:30 a.m. to 4 p.m. shift, although some
maintenance personnel are assigned to the night shift from 4 p.m. to
midnight; and occasionally, maintenance men are assigned, though not
in large numbers, to rotating shifts.
Generally, new hires at the plant begin in the laborers' group, a
classification in the maintenance department.
From this classification,
however, the employee may move to any other classification in the
plant, depending on job vacancies.
Although, based on company
policy, it is theoretically possible for a group A mechanic in one of
the craft classifications to move into a top rated operator's job, and
vice versa, such occurrences would be highly unlikely. In point of
fact, the incidence of transfer from maintenance to operational func-
tion is rare, although there are transfers from one maintenance classi-
fication to another, and there is some overlap of job functions among
maintenance classifications.
Newly hired employees who will ulti-
mately work on one of the craft classifications are not required, at the
time of hire, to have any craft experience or apprenticeship training.
There is a general training program conducted for all maintenance
department employees however. Thus maintenance trainees must take
60-hour classroom courses in basic mathematics, basic blueprint read-
ing, basic science, and basic freehand sketching over an 18-month
period.
Operators, on the other hand, receive no formal classroom
training, but are provided a manual of operations, and are given on-
the-job training.
UNION CARBIDE CORPORATION CHEMICALS DIVISION
639
Although maintenance work, and specifically the work performed
by the three classifications sought by the Plumbers, requires close con-
tact with production personnel, the actual performance of the main-
tenance work is wholly within the competence and responsibility of
the pipefitter, welder, or instrument repairmen and subject to the
supervision of a foreman in the maintenance department,
Thus, pipefitters are required to read blueprints, sketch pipe fabrica-
tion, fabricate, install, remove, and repair pipe, and install instru-
ments.
They must belt and unbelt pipe, insulate tubing, do steam
tracing and instrument tubing, blank line, perform valve removal and
repair valves, steams traps, and steam vacuum systems.
All of these
we find to be the usual and recognized duties assigned to pipefitters
requiring the utilization of normal skills of craft pipefitters.
Although some of the less skilled of these functions are performed by
other classifications of employees at the Institute plant, notably by the
48 shift utility mechanics in the production department, none exercise
all the skills or functions of pipefitters.
Nor do they perform any
part thereof with the same frequency as the pipefitters.
Moreover,
shift utility mechanics have other job functions which are wholly
unrelated to pipefitting and occupy a sustantial part of their time.
From time to time shift utility mechanics may transfer from that
classification into the classification of pipefitter trainee, in which event,
they, like other apprentice pipefitters, become trainees subject to the
trainee's wage rates.
Accordingly, we reject the Employer's con-
tention that shift utility mechanics must be included in a unit of
pipefitters.
We find further that the pipefitters are trained to be
craftsmen pipefitters and that performance of their work tasks nor-
mally requires the use of skills of a craftsman pipefitter.
However,
since the Plumbers have asked the addition of welders to the eraft
unit petitioned for, we will consider such request.
The welders, together with their trainees, perform the overwhelm-
ing portion of their work in the central shops, where they are per-
manently assigned.
There is no overlap of duties between welders
and any other classification in the plant, the journeyman welder being
required to be proficient in the three basic types of welding : acetylene,
heliarc, and electric.
It is true that welders, who are responsible for
doing all the welding in the plant, at times perform welding for other
classifications.
But more than 90 percent of their work is performed
in conjunction with work being done by pipefitters.
Most often, the
pipefitter sketches the work to be done and sends it to the welding
shop where it is fabricated and welded by welders under the super-
vision of a welder foreman.
Accordingly, we find that between the
640
DECISIONS OF NATIONAL LABOR RELATIONS BOARD
pipefitters and the welders there is a close community of interests and
that together they constitute a homogeneous group of skilled craftsmen,
appropriate for representation in a unit by themselves .4
Regarding the additional inclusion of instrument repairmen with
pipefitters and welders in the craft unit petitioned for, the Plumbers
has offered no support, and we find none, for such a unit grouping.
We do find, however, that by themselves the instrument repairmen
constitute an identifiable craft and are entitled to separate representa-
tion if they so choose .-5
Thus, instrument repairmen are required to
calibrate, maintain, and adjust over 7,000 highly sensitive pneumatic
and electronic control instruments. In investigating malfunctions, the
instrument repairman is called upon to exercise a high degree of
judgment, and to utilize electronic instruments in arriving at a diag-
nostic decision.
Because of the highly complex nature of his job, the
instrument repairman receives more specialized training than any
other classification in the plant and is considered the most highly
skilled of all bargaining unit employees.
Thus, the instrument repair-
man must, in addition to the basic courses given to all maintenance
department employees, take courses in basic electricity and electronics
as well as electronic and pneumatic instrumentation. The special craft
skill of instrument repairmen is even further emphasized by the fact
that, unlike other craftsmen who work under a maintenance foreman
not necessarily proficient in their particular craft, the instrument
repairman is supervised solely by an instrument repairman foreman.
On this basis, we find that instrument repairmen and their trainees
constitute a homogeneous group of skilled craftsmen, appropriate for
representation in a unit by themselves.6
In determining in this case the character and scope of the unit or
units that will assure employees the fullest freedom in exercising their
Section 7 rights, we have considered the functional and operational
integration which exists at the Employer's plant, together with all
other relevant factors.?
Upon our appraisal of all the circumstances,
including the absence of a bargaining history on a more comprehensive
4 Bethlehem Steel Company, Shipbuilding Division, Beaumont Yard, 108 NLRB 241 ; of
Koppers Company, Inc., Chemical Division , Williams Plant, 117 NLRB 422, 426-427
5 Marinette Paper Company, 127 NLRB 1319 ; The General Tire and Rubber Company,
106 NLRB 246, 249
U There are, among the 50 instrument repairmen , 4 who do precisely the same work
but who are attached to the production department and who work under a production
foreman
We do not, under all the circumstances , find this separate line of supervision
sufficient to exclude the shift instrument repairmen from the craft unit found appropriate.
7 Our decision herein is not to be taken as foreclosing the possibility that, in other cir-
cumstances, the integration of operations and functions may be such as to warrant a find-
ing that only an overall unit is appropriate
Nor do we express an opinion as to how
we would rule in a case similar to this one, but where, however , there is a history of
bargaining on a production and maintenance basis and severance of craft units is sought.
UNION CARBIDE CORPORATION CHEMICALS DIVISION
641
basis, we find the craft units above described to be appropriate for
purposes of collective bargaining if the craft employees desire sepa-
rate representation.'
Case No. 9-RC-6285
All parties agree and it is clear that a production and maintenance
unit such as is sought by the Machinists is appropriate.
However, as
we have found that the craft units sought by the Plumbers may also
be appropriate, our final determination of the scope of the production
and maintenance unit must wait upon an expression of the desires
of the employees involved in the elections hereinafter directed.
A disagreement exists as to the placement of six field inspectors,
who, the Machinists contends, without specifying a reason therefor,
should be excluded from the unit. These six employees are attached
to the equipment testing and inspection department composed of 21
employees.
None of the six, however, is included in the vacation
schedule of the ETI department, although wage scales are the same.
Field inspectors are not assigned overtime as are other inspectors and
are not included in the overtime roster from which assignments are
made.
They work in air-conditioned offices which may be locked,
whereas ordinary inspectors work on the plant floor which is not
air-conditioned.
Field inspectors do not carry toolboxes, which are
required of inspectors; they are engaged principally in paperwork
and make only sight inspections, without recourse to tools. In the
Employer's telephone directory, field inspectors, unlike ordinary
inspectors, are officially listed individually as inspector coordinators.
There is no evidence that would point to supervisory status for these
employees.
Nor is there evidence that they fall within some other
classification normally excluded from a production and maintenance
unit.
However, as the record is not entirely clear as to their precise
status, we are unable to conclude at this time whether or not the field
inspectors share a sufficient community of interest with other bar-
gaining unit employees as to require their inclusion in the unit.
We
do not, therefore, make final disposition as to their status but shall
permit them to vote subject to challenge.
The Plumbers' intervention and participation in an election in the
overall production and maintenance unit is opposed by the Machinists
on the ground of inconsistency with its petition for the craft units.
8In so finding , we do not ignore the Employer's argument that an unplanned opera-
tional breakdown or functional disorder may create a serious hazard to the welfare of the
plant and its personnel
we do not, however, view the grouping of employees in more
than one bargaining unit as either enlarging the already existing possibility of hazard,
or of preventing the Employer and its employees from taking the necessary steps to deal
with such potential hazards.
642
DECISIONS OF NATIONAL LABOR RELATIONS BOARD
For the reasons set forth in Schrick, Incorporated 9 and F. N. Burt
Company, Inc.,10 we will require the Plumbers to elect between appear-
ing on the ballot for the production and maintenance unit or on the
ballot for the craft units."
On the basis of the entire record, we find that all group A mechanics
employed as plumber-pipefitters and welders are craftsmen, and
together with pipefitters and welder trainees may constitute a separate
appropriate unit if they so desire.
We further find that all group A
mechanics employed as instrument repairmen and all shift instrument
repairmen are craftsmen, and together with instrument repairmen
trainees may constitute a separate appropriate unit if they so desire.
In view of the foregoing we shall make no final unit determinations
at this time but shall direct that the questions concerning representa-
tion that have arisen be resolved by separate elections by secret ballot
among the employees in the following voting groups, excluding from
groups (a) and (b) all other employees and supervisors as defined in
the Act :
(a) All group A mechanics employed as plumber-pipefitters and
welders, and pipefitters and welder trainees.
(b) All group A mechanics employed as instrument repairmen,
including shift instrument repairmen, and instrument repairmen
trainees.
(c) All production and maintenance employees, excluding the
employees in voting groups (a) and (b) and all professional employ-
ees, guards, and supervisors as defined in the Act.
If the majority of the employees in either voting group (a) or (b)
select the Plumbers, the employees in that group will be taken to have
indicated their desire to constitute a separate bargaining unit, and the
Regional Director conducting the elections is hereby instructed to issue
a certification of representation to the Plumbers for such voting group,
which the Board under the circumstances finds to be an appropriate
unit for purposes of collective bargaining.
However, if a majority of
the employees in either voting group (a) or (b) does not vote for the
Plumbers, that group will appropriately be included in the production
and maintenance unit and their ballots shall be pooled with those for
group (c) .12 If a majority in voting group (c), including any pooled
group, vote for the Machinists, that Union shall be certified as the
9130 NLRB 1501.
10130 NLRB 1115.
n For the reasons set forth in his dissenting opinion in F. N. Burt Co , Inc, supra,
Member Fanning does not agree with our disposition requiring the Plumbers to make
an election.
12 If the votes are pooled , they are to be tallied in the following manner The votes
for the labor organizations seeking separate units in groups (a) and
( b) shall be counted
as valid votes but neither for nor against the labor organizations seeking to represent
the production and maintenance unit.
All other votes are to be accorded their face value.
JEM MFG., INC.
643
representative of employees in such group, which, under these circum-
stances the Board finds to be a single appropriate unit for purposes
of collective bargaining.
[Text of Direction of Election omitted from publication.]
CHAIRMAN MCCULLOCH and MEMBER JENKINS took no part in the
consideration of the above Decision and Direction of Election.
Jem Mfg., Inc. and Sheet Metal Workers' International Associa-
tion, Local 270, AFL-CIO.
Case No. 16-CA-3306. January 6,
1966
DECISION AND ORDER
On September 14, 1965, Trial Examiner Sidney D. Goldberg issued
his Decision in the above-entitled proceeding, finding that Respond-
ent had engaged in and was engaging in certain unfair labor practices
and recommending that it cease and desist therefrom and take certain
affirmative action, as set forth in the attached Trial Examiner's Deci-
sion.
Thereafter Respondent filed exceptions to the Trial Examiner's
Decision and a supporting brief.
The National Labor Relations Board has reviewed the rulings of
the Trial Examiner made at the hearing and finds that no prejudicial
error was committed.
The rulings are hereby affirmed.
The Board
has considered the Trial Examiner's Decision, the exceptions, the brief,
and the entire record in the case, and hereby adopts. the findings and
recommendations of the Trial Examiner, as modified herein.
Although we agree with' the Trial Examiner's findings that
Respondent violated Section 8 (a) (5) and (1) of the .National Labor
Relations Act, as amended, by refusing to recognize and ba.rgain'with
the Union, we do not adopt all of his reasoning in support of such
findings.
As more fully detailed in the Trial Examiner's Decision, on
March 2, 1965, the Union met with Respondent coowners, stated that
it represented a majority of Respondent's employees, and presented
authorization cards to the Respondent to prove its majority.
Although
John Wheatley, one of the coowners, said that he did not think the
employees should be represented, Wheatley examined the authoriza-
-tion cards and copied down the names. The Union then presented the
Respondent with a written request for recognition and a proposed
agreement recognizing the Union and requested that Respondent sign
156 NLRB No. 62.
317-919-66-vol. 15 0- 4 2