255 NLRB 632
Zurn Industries, Inc.
632
DECISIONS OF NATIONAL LABOR RELATIONS BOARD
Zurn Industries, Inc. and Robert Pendergrass. Case
19-CA- 11731
April 6, 1981
DECISION AND ORDER
On July 16, 1980, Administrative Law Judge
James M. Kennedy issued the attached Decision
dismissing the complaint in this proceeding. There-
after, the General Counsel filed exceptions and a
supporting brief, requesting review of the record de
novo. Respondent filed no cross-exceptions.
The Board has considered the record and the at-
tached Decision in light of the exceptions and brief
and has decided to affirm the rulings, findings, and
conclusions of the Administrative Law Judge only
to the extent consistent herewith.
The complaint alleges that Respondent threat-
ened its employees with discharge, and discharged
six employees-Robert Pendergrass (the Charging
Party), Everette Kissler (the union steward), Tony
Wells, Steven Stedham, David Alexander, and
Larry Jones, herein "the concrete crew-for their
complaint about unsafe working conditions, in vio-
lation of Section 8(a)(l) of the National Labor Re-
lations Act, as amended. The Administrative Law
Judge recommended that the complaint be dis-
missed, finding first that Respondent made no
threats, and second, that the concrete crew was
dismissed for unsatisfactory work, not because of
their complaints. We disagree.
Respondent is a construction contractor which,
during the time in question, was building a cooling
tower for a nuclear power plant in Satsop, Wash-
ington. The employees in question were laborers
assigned at all relevant times to the concrete or
"mud" crew, meaning that they poured concrete
from a concrete truck into forms. There were a
number of discrete tasks involved in this: Concrete
was loaded from the truck into buckets, which
were then emptied onto a chute directed to the
forms and, as the concrete was poured into the
forms, it was vibrated with machines called vibra-
tors to prevent air pockets from forming and to
prevent the concrete from separating.
Respondent, as required by Federal regulations
and its contract with the site owner, held weekly
safety meetings for employees on the site, usually
conducted
by
its
safety
"supervisor,"
James
Seaman. During the months of June, July, and
August, Respondent's employees persistently de-
manded that Respondent furnish a "safety skip": a
4- by 4- by 8-foot box that could be attached to a
crane and used to rescue injured workers from
heights or excavations. Respondent initially fur-
nished a wooden skip, which did not satisfy the
employees because they thought it too weak. Re-
255 NLRB No. 88
spondent then furnished a steel skip, but the em-
ployees were still dissatisfied because the skip had
no door, no litter, and no first aid kit. After the
second skip arrived, it was discussed at an August
15 safety meeting of all Respondent's employees at
the site. When this discussion became heated, Re-
spondent's site superintendent, Kester Buffington,
interrupted the meeting and said that he was "tired
of hearing about safety and especially about the
safety skip," that anyone with any complaint
should talk to the steward about it, and that if
anyone did not like that procedure there would be
two checks waiting for him in the office, meaning
they
were
discharged.
When Buffington
had
spoken, the meeting broke up.
Immediately
after this meeting, the concrete
crew went to the site of that day's "pour," where
they found that the forms were not yet complete.
Specifically, ladders and handrails were not in
place and at least one metal bar called a rebar was
not capped. The crew concluded that the job was
not safe, and called this to the attention of Seaman.
Seaman, who did not have authority to stop work,
went to find the safety supervisor for Ebasco, a
construction management
contractor overseeing
the entire project. While Seaman was gone, the
concrete crew decided among themselves that they
would not work on the pour until they were sure it
was safe. While waiting, they were observed by
Superintendent Buffington and Ray Lewis, a qual-
ity control
supervisor for Ebasco.
Lewis ap-
proached them and told them that Buffington
wanted them to begin work; they responded that
they were not going to work until they heard from
the Ebasco safety man. The Ebasco safety supervi-
sor agreed that the forms were unsafe, and the
pour was delayed several hours.
Two days later, on August 17, the forms were
removed from the August 15 pour, revealing nu-
merous serious defects. That afternoon, the six
members of the August 15 concrete crew were dis-
charged. When they learned of their discharge,
they confronted Buffington in his office. Buffington
told them that they were being fired because of the
poor results of the August 15 pour, which Buffing-
ton said were due to poor vibration. Two of the
six, Stedham and Wells, objected, saying that they
had not been engaged in work related to vibration
on the August 15 pour.
In dismissing the complaint, the Administrative
Law Judge concluded that "the only probable sce-
nario" was that the six-man concrete crew was dis-
charged because of the poor results of the August
15 pour. He also concluded that Buffington did not
threaten discharge for complaining about safety
when he spoke to the safety meeting on the morn-
ZURN INDUSTRIES, INC.
633
ing of August 15. We disagree with these conclu-
sions.
During the August 15 safety meeting Buffington
came out of his office adjacent to the meeting
place and spoke in an "annoyed" tone. In pertinent
part, Buffington said:
We are tired of hearing all this commotion
about safety and . . . about this safety skip.
We have a skip now and if anybody doesn't
like it we have checks for them.
The Administrative Law Judge termed these re-
marks "totally understandable"
in the circum-
stances.'
He noted that Respondent had already
"complied" with employee requests for a skip, and
that one employee at the safety meeting had said,
"To hell with the way management wants that
skip, we need it for safety, it's the way we want it,
not the way they want it." This remark the Admin-
istrative Law Judge termed an "insubordinate seiz-
ure of safety authority." However, an employee is
not insubordinate to express an opinion on occupa-
tional safety-one of the most imporfant conditions
of employment. Nor does this expression lose its
Section 7 protection because it may have been in-
temperate. See Fall River Savings Bank, 247 NLRB
631, fn. 3 (1980); American Telephone & Telegraph
Co., 211 NLRB 782, 783 (1974); Houston Shell and
Concrete Co., A Division of McDonough Co., 193
NLRB 1123, 1129 (1971).
The Administrative Law Judge further found
that Buffington was, in any case, merely telling em-
ployees to direct their complaints through proper
channels. But weekly safety meetings were proper
channels, and the crew's action later that day re-
garding the unsafe forms was also directed through
proper channels: Steward Kissler, Seaman, and the
Ebasco safety supervisor. We conclude that Buff-
ington, by his remarks at the safety meeting, threat-
ened employees with discharge for engaging in
concerted activity for their mutual aid or protec-
tion, a right guaranteed by Section 7, and thus vio-
lated Section 8(a)(1) of the Act.
Concerning the discharge of the concrete crew,
the Administrative Law Judge concluded that it
was not motivated by the safety concern voiced by
the crew at the August 15 pour site, hence there
was no violation of the employees' Section 7 rights.
I The Administrative Law Judge found that Buffington's remarks that
morning were addressed only to complaints about the safety skip, not to
safety generally, and that the contrary recollections of several witnesses
were "exaggerations." The record testimony does not support that con-
clusion. In addition, either version would establish Buffington's hostility
to employee complaints at that time. Buffington testified only as an ad-
verse witness for the General Counsel. He was not recalled to deny any
of the subsequent testimony. Unlike the Administrative Law Judge, we
draw an adverse inference from the lack of a specific denial. See Maortin
Luther King. Sr. Nursing Center. 231 NLRB 15. fn I (1977).
The Board has recently stated in Wright Line, a Di-
vision of Wright Line, Inc., 251 NLRB 1083 (1980),
that where the motivation for discharge is at issue,
the General Counsel must make a prima facie
showing sufficient to support an inference that pro-
tected activity by employees was a motivating
factor in an employer's decision to discharge. The
employer then has the burden of showing that the
employees would have been discharged absent that
protected activity.
Contrary to the Administrative Law Judge, we
find that the General Counsel has made a prima
facie showing. The Administrative Law Judge
found improbable the fact that Buffington, at the
August 17 discharge confrontation, said that there
had been too much "commotion" about safety from
the concrete crew, because the only "commotion"
about safety occurred at the recent weekly safety
meeting. The Administrative Law Judge further
found that, in any case, the impact of the crew's re-
fusal to work until the site was approved safe to
work was "submerged" by the fact that concrete
could not have been placed until the forms were
finished. We find the Administrative Law Judge's
treatment of the testimony on these matters specu-
lative and do not adopt it.
Respondent's exhibits show the "15 Aug '79"
pour was originally scheduled for "8:30," Stedham
testified that it was "rescheduled at 10 the first
time" and Pendergrass testified that the pour was
actually started that afternoon about I o'clock.
Buffington, though knowing the forms were unfin-
ished, ordered the concrete crew to proceed. The
crew contacted Seaman to protest the unsafe con-
ditions
created
by the incomplete
form,
and
Seaman in turn contacted the Ebasco representa-
tive. As a result, the crew was sent to an early
lunch while handrails were being provided. 2
We further find that Buffington was clearly
aware of these developments 3 and, contrary to the
2 The Administrative Law Judge concluded that, while the crew-
members were prepared to refuse to work, they were not "forced to
refuse" to work on the forms and therefore did not refuse to do so Be
that as it may. what is important is that the crew initiated the delay of
work.
3 Buffington was aware that the concrete crew had refused to do the
pour, and he testified that the refusal occurred "awfully close to noon I
would imagine. I know it was a good 45 minutes or getting close to an
hour from what the scheduled pour was to have been made .. ."
Later, the Administrative Law Judge asked Buffington the sequence of
events on August 15 with respect to the forms for the pour. to which
Buffington answered:
The first that it was brought to my attention, and somebody came to
me, I don't know who. hut possibly one of the foremen, possibly Jim
Seaman, and said the pour crew isn't going to get on there without a
handrail . ... I immediately went to Vernon Lee, the carpenter
foreman. and explained we were going to have to have handrails on
there . ..
The first time I was aware there was ally controversy
on handrails was now I guess there was more I didn't get involved
Continued
ZURN
INDUSTRIES,
INC.
633
634
DECISIONS OF NATIONAL LABOR RELATIONS BOARD
Administrative Law Judge, find nothing improb-
able in the employees' testimony that Buffington, at
the time of discharge, mentioned "commotion"
about safety as the cause of the crew's discharge.
In reaching this result we note that the Administra-
tive Law Judge referred to employee Wells' testi-
mony, which he considered "closest" to the truth,
as "not describ[ing] anything like Buffington's sup-
posed admission" as reported by Stedham, Pender-
grass, and Jones. However, Wells' testimony on
this point clearly indicates that Buffington referred
to the crew's complaints as a basis for the dis-
charge and in fact is quite similar to that of Sted-
ham, Pendergrass, and Jones, all of whom were se-
questered at the hearing. 4 Thus, Wells, in response
to the General Counsel's question whether he had
heard anyting regarding complaints during the dis-
cussion between Stedham and Buffington:
Mr. Buffington had stated to Steve Stedham
that the higher up offices have been hearing
complaints from the concrete crew and that he
was told to fire the whole crew.
Stedham, protesting his discharge to Buffington
because he did not run a vibrator, was told by
Buffington:
He said it came from above . . . he had been
hearing too much commotion about safety
from the crew and that he and Stamp thought
they could do better with a whole new crew.
And I said that it wasn't the crew it was the
way Mr. Buffington scheduled pours way
ahead of time, and the equipment they had,
which was lousy, they'd need more than a
whole new crew.
Pendergrass, who heard Buffington respond to
Stedham when he protested that he did not even
run a vibrator:
And Kester [Buffington] said, "Well, we have
been hearing a lot of commotion from the con-
crete crew about safety and it came down
from George [Stamp] to get rid of all of you
and so I did."
Jones, concerning what Buffington said to him
and Steve Stedham when they protested that they
weren't using the vibrators:
Well, you've got me, the reason you were
fired is because you were complaining about
in, and then they came to me and said they weren't going to get on
there . .
.
4 By contrast, the site superintendent, Buffington, had been in the
courtroom during the testimony of Project Manager Stamp. These two
were the first witnesses called by the General Counsel as adverse wit-
nesses. See Fed. R. Evid. 615: Unga Painting Corporation,
237 NLRB
1306.13
11 (1978).
safety, and people above my head found out
about it. And I had to let you go.
The Administrative Law Judge, in countering
the obvious problem of Buffington's lack of denial
of the testimony quoted above, 5 made a passing
reference
to "considerations
of demeanor and
fervor" and then concluded that Pendergrass and
Stedham-whom he was not discrediting on the
basis of "deliberate prevarication"-appeared
to
him as "excessively sensitive to the safety skip
matter," as "aware of the agreement not to work
on August 15 and . . . ready to ascribe an evil
motive to nearly anything negative which oc-
curred." He added that Jones was "even worse" in
this regard,6 and concluded: "That Buffington ever
uttered such an admission is most doubtful."
The Administrative Law Judge seems to have
confused demeanor with fervor for safe working
conditions and, based on his own speculation in
that regard, has excused the failure of Respondent
to question Buffington. On this record we are not
prepared to conclude that the employees' concern
about safety-either as to the skip or the hand-
rails-was excessive, or that their undenied testi-
mony was not credible. The credibility findings we
make comport with the record evidence and with
the inferences fairly drawn therefrom. See El
Rancho Market, 235 NLRB 468, 470 (1978). We
therefore find that Buffington indicated, during his
August 17 discussion with the discharged employ-
ees, that they were discharged because of their
complaints about safety.
Having concluded that General Counsel has
made a prima facie showing that the motive of Re-
spondent in discharging the crew was its activity in
complaining about safety with respect to the hand-
rails, we turn to Respondent's burden of showing
that it would have discharged the crew absent the
crew's protected request to provide safety.
Although each crewmember received an identi-
cal termination slip, stating, "Does not do work to
our satisfaction," Respondent advanced conflicting
explanations of the discharges, before and during
the hearing. Stamp testified that he ordered Buff-
ington to fire the crew; while Buffington agreed
with that account at the hearing," he had said in a
pretrial affidavit that he decided to discharge the
crew without even consulting Stamp. At different
times Buffington and Stamp cited different pours as
the cause of the discharges, including those of
See fn. 1, above.
6 We cannot agree that Jones' testimony showed "bias on its face."
Rather it suggests that Jones wanted to hear Buffington admit that he
was discharging the crew for their complaints, as Jones knew his rights
and was prepared to enforce them. (See ALJD, sec. IlI.C.)
' See fn. 4, above.
ZURN INDUSTRIES, INC.
635
August 3, 12, 15, 16, and 17. In his affidavit, Buff-
ington said the discharges were based "solely" on
the August 16 pour. Some of these pours included
employees who were not discharged, and the re-
sults of the last two were not yet known on August
17, the date of discharge. Though Stamp claims to
have observed improper work by the crew, he
admits they were not warned. Respondent's incon-
sistency leads us to draw an unfavorable inference
against it for inability to settle upon an explanation
for the discharge of the crew. See A. J. Krajewski
Manufacturing Co., Inc. v. N.L.R.B., 413 F.2d 673,
675 (Ist Cir. 1969), where the court noted "espe-
cially the Company's inability to adhere with con-
sistency to any explanation of its action"; also
N.L.R.B. v. Teknor-Apex Company, 468 F.2d 692,
694 (Ist Cir. 1972).
As earlier noted, the Administrative Law Judge
concluded that the only "probable scenario" was
that the crew was discharged on August 17 be-
cause of the results of the August 15 pour. Howev-
er, the Administrative Law Judge also found-and
the record clearly supports the facts-that although
vibration of concrete is necessary to a satisfactory
pour, two of the three vibrators used by the crew
were not functioning on August 15, and Respond-
ent thereafter was forced to purchase replace-
ments.8 Respondent knew that the vibrators were
not functioning properly, but nevertheless contin-
ued the pour. In addition, the entire crew of six
was discharged, though only two of them operated
vibrating equipment on that pour, and the foreman
who supervised and worked with the crew was not
discharged or even reprimanded.9 We further note
that the record contains evidence that the concrete
crew's work was generally satisfactory.
Under
these circumstances, we find that Respondent's as-
serted reason for the discharges was a pretext.
On this record, the discharge of the entire crew
flowed from the crew's specific safety complaints
of August 15 and the accompanying protest and
delay of work, concerted activity protected by
Section 7 of the Act, which we find were the true
causes of the discharges. Accordingly, we find and
conclude that Respondent has violated Section
8(a)(1) of the Act.
s Ebasco's report on the August 15 pour (Pour 8XB) notes that the de-
fects were typical of pours where the concrete falls too far, which it did
on August 15 because the tremie chute was broken.
9 The Administrative Law Judge concludes his Decision by noting a
grievance settlement several weeks later: One crewmember was rehired
and the rest were judged suitable for rehire; he finds that the employees'
union thereby admitted some "fault" on the employees' part, and that Re-
spondent admitted some "unfairness" on its part. The Administrative
Law Judge thus implies that this settlement is evidence that Respondent
did not violate the Act. We cannot agree.
CONCLUSIONS OF LAW
1. Zurn Industries, Inc., is an employer within
the meaning of Section 2(2) of the Act, engaged in
commerce
and operations
affecting commerce
within the meaning of Section 2(6) and (7) of the
Act.
2. Laborers Local No. 374, affiliated with the
Washington and Northern Idaho District Council
of Laborers, AFL-CIO, is a labor organization
within the meaning of Section 2(5) of the Act.
3. By threatening to discharge employees for
voicing their opinions concerning job safety issues,
Zurn Industries, Inc., violated Section 8(a)(1) of
the Act.
4. By discharging employees Robert Pender-
grass, Everett
Kissler, Steven
Stedham, Tony
Wells, Larry Jones, and David Alexander on
August 17, 1979, Zurn Industries, Inc., violated
Section 8(a)(1) of the Act.
5. The aforesaid unfair labor practices affect
commerce within the meaning of Section 2(6) and
(7) of the Act.
THE REMEDY
Having found that Respondent Zurn Industries,
Inc., engaged in certain unfair labor practices in
violation of Section 8(a)(l) of the Act, we shall
order Respondent to cease and desist therefrom
and from engaging in like or related conduct, and
to take certain affirmative action to effectuate the
policies of the Act.
Respondent shall be ordered to offer Robert
Pendergrass,
Everett
Kissler, Steven
Stedham,
Tony Wells, Larry Jones, and David Alexander
immediate reinstatement to their former positions
of employment or, if those positions no longer
exist, to substantially equivalent positions, without
prejudice to their seniority or other rights and
privileges, and to make them whole for any loss of
earnings or other benefits they may have suffered
by reason of their unlawful discharges. Backpay
and interest thereon shall be computed in the
manner prescribed in F: W Woolworth Company, 90
NLRB 289 (1950), and Florida Steel Corporation,
231 NLRB 651 (1977).' °
ORDER
Pursuant to Section 10(c) of the National Labor
Relations Act, as amended, the National Labor Re-
lations Board hereby orders that the Respondent,
'0 See, generally. Isis Plumbing d Heating Ca., 138 NLRB 716 (1962).
Member Jenkins would compute interest on the backpay in accordance
with his partial dissent in Olympic Medical Corporation, 250 NLRB 146
(1980).
ZURN NDUSTRIES,
INC.
635
.
636
DECISIONS OF NATIONAL LABOR RELATIONS BOARD
Zurn Industries, Inc., Elma, Washington, its offi-
cers, agents, successors, and assigns, shall:
1. Cease and desist from:
(a) Discharging employees for engaging in con-
certed activity for their mutual aid or protection,
by expressing their concerns for safe working con-
ditions, either in weekly safety meetings, or at
other reasonable times and places.
(b) Threatening its employees with discharge for
engaging in concerted activity for mutual aid or
protection by expressing concern for safe working
conditions.
(c) In any like or related manner interfering
with, restraining, or coercing employees in the ex-
ercise of the rights guaranteed them by Section 7
of the Act.
2. Take the following affirmative action to effec-
tuate the policies of the Act:
(a) Offer Robert Pendergrass, Everett Kissler,
Steven Stedham, Tony Wells, Larry Jones, and
David Alexander immediate and full reinstatement
to their former positions or, if those positions no
longer exist, to substantially equivalent positions,
without prejudice to their seniority or other rights
or privileges previously enjoyed, and make them
whole for any loss of earnings or other benefits
they may have suffered as a result by paying them
a sum equal to what they would have earned
absent the unfair labor practice, less any net interim
earnings, plus interest.
(b) Preserve and, upon request, make available to
the Board or its agents, for examination and copy-
ing, all payroll records, social security payment re-
cords, timecards, personnel records and reports,
and all other records necessary to analyze the
amount of backpay due under the terms of this
Order.
(c) Post at the Satsop, Washington, site of Zurn
Industries, Inc., copies of the attached notice
marked "Appendix."
Copies of said notice, on
forms provided by the Regional Director for
Region 19, after being duly signed by an author-
ized representative, shall be posted by Respondent
immediately upon receipt thereof, and be main-
tained by it for 60 consecutive days thereafter, in
conspicuous places, including all places where no-
tices to employees are customarily posted. Reason-
able steps shall be taken by Respondent to insure
that said notices are not altered, defaced, or cov-
ered by any other material.
(d) Notify the Regional Director for Region 19,
in writing, within 20 days from the date of this
"' In the event that this Order is enforced by a Judgment of a United
States Court of Appeals, the words in the notice reading "Posted by
Order of the National Labor Realtions Board" shall read "Posted Pursu-
ant to a Judgment of the United States Court of Appeals Enforcing an
Order of the National Labor Relations Board."
Order, what steps Respondent has taken to comply
herewith.
APPENDIX
NOTICE To EMPLOYEES
POSTED BY ORDER OF THE
NATIONAL LABOR RELATIONS BOARD
An Agency of the United States Government
YOu HAVE THE RIGHT, under the National Labor
Relations Act, as amended, to act together on your
concern for safe working conditions, and in other
respects for your mutual aid or protection.
The National Labor Relations Board has found,
after a hearing, that we violated the National
Labor Relations Act by threatening our employees
with discharge for complaining about safety condi-
tions at their worksite, and by discharging Robert
Pendergrass,
Everett
Kissler,
Steven
Stedham,
Tony Wells, Larry Jones, and David Alexander on
August 17, 1980.
We hereby notify our employees that:
WE WILL NOT discharge employees for ex-
pressing their concerns for safe working condi-
tions in weekly safety meetings or at reason-
able times and places.
WE WILL NOT threaten any employee with
discharge for expressing concern about safe
working conditions.
WE WILL NOT in any like or related manner
interfere with, restrain, or coerce our employ-
ees in the exercise of the rights guaranteed
them by Section 7 of the Act.
WE WILL offer immediate and full reinstate-
ment to Robert Pendergrass, Everett Kissler,
Steven Stedham, Tony Wells, Larry Jones,
and David Alexander to their former jobs or,
if those positions no longer exist, to substan-
tially equivalent positions, without prejudice to
their seniority or other rights or privileges pre-
viously enjoyed.
WE WILL make whole Pendergrass, Kissler,
Stedham, Wells, Jones, and Alexander for any
loss of earnings or other benefits each may
have suffered from the time of discharge to
the time of reinstatement, less net earnings
during that period, plus interest.
ZURN INDUSTRIES, INC.
DECISION
STATEMENT OF THE CASE
JAMES M. KENNEDY, Administrative Law Judge: This
case was heard before me at Seattle, Washington, on
ZURN INDUSTRIES, INC.
637
February 14 and 15, 1980, pursuant to a complaint issued
by the Regional Director for the National Labor Rela-
tions Board for Region 19 on October 25, 1979,1 and
which is based on a charge filed by Robert Pendergrass,
an individual, on September 4. The complaint alleges
that Zurn Industries, Inc. (herein called Respondent), has
engaged in certain violations of Section 8(a)(l) of the
National Labor Relations Act, as amended (herein called
the Act).
Issues
Whether or not Respondent on August 17 discharged
its entire concrete placement crew because some of its
members had engaged in or had threatened to engage in
a work stoppage over safety matters and whether the
discharge had been preceded by a threat to discharge
employees over safety complaints.
All parties were given full opportunity to participate,
to introduce relevant evidence, to examine and cross-ex-
amine witnesses, to argue orally, and to file briefs. Briefs,
which have been carefully considered, were filed on
behalf of the General Counsel and Respondent.
Upon the entire record of the case, and from my ob-
servation of the witnesses and their demeanor, I make
the following:
FINDINGS OF FACT
1. RESPONDENT'S BUSINESS
Respondent admits it is a Pennsylvania corporation en-
gaged in the engineering and construction business and
having an office located in Elma, Washington, and a job-
site in nearby Satsop. It further admits that during the
past year, in the course and conduct of its business it has
purchased and received goods and materials valued in
excess of $50,000 from suppliers outside Washington
State. Accordingly, it admits, and I find, it is an employ-
er engaged in commerce and in a business affecting com-
merce within the meaning of Section 2(2), (6), and (7) of
the Act.
II. THE LABOR ORGANIZATION INVOLVED
The parties stipulated, and I find, that Laborers Local
No. 374, affiliated with the Washington and Northern
Idaho District Council of Laborers, AFL-CIO (herein
called the Union), is a labor organization within the
meaning of Section 2(5) of the Act.
III. THE ALLEGED UNFAIR LABOR PRACTICES
A. Background and Participants
Respondent
has contracted
with the Washington
Public Power Supply System (WPPSS) to design and
construct the cooling towers for a nuclear power plant
located near Satsop, Washington. Other portions of the
plant are being constructed by other firms and all of the
construction
companies
are under the direction
of
Ebasco Services,
Inc.,
which has a contract
with
WPPSS to oversee all construction. Ebasco is the con-
' All dates herein refer to 1979. unless otherwise indicated.
struction manager and performs the site's necessary ad-
ministrative functions.
Respondent has recognized the Union as the repre-
sentative of its laborers and has recognized other craft
unions as well, including a local of the Ironworkers
Union. At the time in question, Respondent employed
between 80 and 100 employees, including approximately
20 to 25 laborers. Of these approximately 6 were as-
signed to the concrete placement crew, commonly called
the "mud crew."
Respondent's hierarchy from the bottom up is: Don
Scott, mud crew foreman; Henry Chavie, laborer fore-
man; Kester Buffington, field superintendent; and George
Stamp, project manager. Stamp was the highest official
present at the site and reported to Respondent's Tampa,
Florida, headquarters. Others who reported directly to
Stamp were
Respondent's
safety supervisor, James
Seaman, and members of Respondent's quality control
department.
The mud crew regularly consisted of Pendergrass, Ev-
erett Kissler, the union steward, David Alexander, Tony
Wells, Larry Jones, and Steven Stedham.
At the time of the transactions to be described herein,
August 1979, Respondent was in the process of placing
concrete for the water inlet trench and the foundation of
the cooling tower, which will eventually rise to the
height of 495 feet. The foundation ring is approximately
420 feet in diameter. The water inlet joins the tower at a
"header," which is a large concrete platform containing
a tunnel for the hot water. In addition to serving as the
header for the inlet, the platform was also to serve as the
base for the tower crane to be used during construction.
It is fair to say, and no party disagrees, that the quality
of the concrete work to be performed at this stage of
construction must meet the design specifications: if not,
the structural integrity of the crane base and surrounding
foundations would be jeopardized.
During the course of construction, and pursuant to its
agreement
with WPPSS, Respondent
holds weekly
safety meetings with its crews. All meetings occur on
Wednesdays before beginning work: during a month
three meetings are limited to each individual craft, while
one is an all-craft meeting.
One of the topics which had heen regularly discussed
at the safety meetings was the need for a "safety skip." 2
The witnesses are all in agreement that Respondent was
not obligated by safety rules or regulations-whether
promulgated by state or Federal safety agencies-to pro-
vide such a device. Nonetheless, it appears that on large
construction
projects such as this safety skips are
common. Indeed, Ebasco Services had a standard design
for one. As a result of safety meeting requests which had
begun in May, Respondent built a wooden skip. Howev-
er, because it was not constructed of steel, like Ebasco's
design, many employees did not trust it, believing it not
strong enough. It was approximately 4 by 4 by 8 feet,
2 Some of the Witnesses referred to it as a
afety 'skiff"
as do the
Getneral Counsel and Ihe transcript. Iowevcr. t is clear that the proper
name of the instrumcnt is "skip"-a baskel or a bucket for carr)ing men.
here injured nen. See
WItehotr'rs
Third N.e
I,,t rnll iotll Dltilonaurv
( 1963}
ZURN
INDUSTRIES.
INC.
637
638
DECISIONS OF NATIONAL LABOR RELATIONS BOARD
and contained an entry door. As a result of the addition-
al complaints, Respondent ordered a steel skip to be con-
structed in Centralia, Washington. It arrived in mid-
August, shortly before the safety meeting of August 15.
Although it was approximately the same size as the
wooden skip, it did not contain a door, and there was
testimony that some employees thought its use would not
be limited to rescue purposes.
B. The Safety Meeting of August 15
At 8 a.m. on August 15, an all-craft safety meeting was
begun under the leadership of Safety Supervisor Jim
Seaman. He testified that the meeting was not specifical-
ly aimed at the safety skip, and that it started out with a
discussion of some minor complaints, such as a lack of
band-aids and torn gloves. At some point, he said that he
had heard the new skip was on the way and it would not
be very long before it arrived. Pendergrass remembers
an ironworker asked for details about the safety skip, and
Seaman replied it had arrived but he had not seen it yet.
Another ironworker said it was only a metal box and did
not qualify as a safety skip. Tony Wells remembered
Seaman discussing the skip with an ironworker and their
discussion dealt with whether or not it met OSHA stand-
ards. Steve Stedham testified that during the meeting
Seaman announced that Respondent had a safety skip,
saying, "I know that you men don't like it, but that's the
way the Company wants it." At this point, according to
Stedham, an ironworker "spouted out" saying, "To hell
with the way management wants that skip, we need it
for safety, it's the way we want it, not the way they
want it."
Everyone is in agreement that, during the discussion
regarding the skip, Field Superintendent Kester Buffing-
ton came out of his office, which was adjacent to the
meeting place, and spoke to the group in an annoyed
tone.
Pendergrass testified that Buffington stepped out in
front of Seaman and said, "We are tired of hearing all
this commotion about safety and especially about this
safety skip. We have a skip now and if anybody doesn't
like it we have checks for them. We have a procedure
around [here]. You talk to your steward, your steward
talks to your business agent, and your business agent
talks to me. If you don't like that we have checks for
you, too." Despite this alleged statement, Pendergrass
and others conceded that at company safety meetings
Respondent encouraged employees to make suggestions
and comments. Pendergrass found Seaman "responsive
and very amiable" whenever employees made safety sug-
gestions to him.
About this incident, Kissler testified that Buffington
"commented on he'd heard enough about the safety skip
and that what they had was what the Company was
going to provide for us. [Buffington] said if we didn't
like the procedure the Company was taking, that anyone
that didn't like it could pick up their check and head
down the road." Wells testified that Buffington interrupt-
ed Seaman. Wells recalled, "[Buffington said] he had
heard enough about the safety skip, that he's been hear-
ing complaints about it for the last month, and that he
was sick and tired of hearing it, that there was proce-
dures, proper channels, that you were to go through
when you had a safety complaint, and that if he heard
any more from anybody else about the safety skip, that if
they didn't like the way the project was run, they could
go pick up their checks at the window." Stedham testi-
fied that, after hearing the ironworker speak angrily of
the skip, Buffington pointed his finger at the man and
said, "I'm damn tired of hearing about safety, especially
the safety skip. I don't want to hear no more about it: if
you guys don't like the way things are run around here,
I'll get you both your checks and you can go down the
damn road."
Seaman recalled Buffington saying he was tired of
hearing so much about the safety skip and, if the employ-
ees did not agree with the way things were going, there
were two checks waiting for them in the office. He
denies Buffington saying anything about safety com-
plaints generally. He remembers that during the meeting
there was a "lot of rhetoric"-a conclusionary statement
which I believe to be accurate if it is taken to mean that
angry tones were used by those employees who wanted
a different style skip.
The General Counsel did not ask Jones for his recol-
lection, although he was no doubt present, being sched-
uled to work shortly as a vibrator man. Neither did the
General Counsel ask Buffington for his version when he
was called as an adverse witness.
After listening to the versions of the mud crew mem-
bers as they testified about Buffington's remarks at the
safety meeting, I found myself totally unimpressed with
the likelihood that Buffington made an unlawful state-
ment. It is apparent, particularly from Stedham, that
some members of the ironworker crew were quite angry
and at least one of them told Seaman that safety matters
were solely the concern of employees, not the concern
of the employer and that it was the workmen's right to
dictate safety terms to Respondent. Clearly, that attitude
was insubordinate and an attempt to undermine manage-
rial authority. Moreover, the safety skip matter had been
before Buffington since May and had been resolved, not
once, but twice. Respondent had first built the wooden
skip which had been on the job since June. When em-
ployees complained it was not strong enough, Buffington
caused another to be built and its imminent arrival had
just been announced by Seaman. Thus, from Buffington's
standpoint he had complied with two employee requests
for a skip and believed the problem to be over. In that
context his response that he was "sick and tired of hear-
ing about the safety skip" is totally understandable, par-
ticularly where it was being exacerbated by an employ-
ee's insubordinate seizure of safety authority. In essence,
Buffington stated that he was no longer going to enter-
tain direct employee complaints about the skip, but
would entertain them if they were brought to him
through the proper channels, the various union grievance
procedures. And, his remark, that people could quit if
they did not like the way the Company operated, was
simply a response to the ironworker's insubordination. In
no way was it a threat to discharge employees for
making safety related complaints. Thus, I conclude, from
analyzing the testimony of the General Counsel's own
ZURN INDUSTRIES, INC.
639
witnesses, that the General Counsel did not make out a
prima facie case with respect to Buffington's alleged
threat to discharge employees for engaging in the pro-
tected activity of making safety complaints or speaking
of safety matters. Supporting this conclusion is the em-
ployees' own testimony that Respondent encouraged
safety discussions and responded favorably to legitimate
concerns. Their recollection that Buffington's remarks
encompassed safety matters beyond the skip are exagger-
ations and are not credited.
C. The Discharge of the Mud Crew
Immediately after the safety meeting ended on August
15, the mud crew headed down to begin work on pour
number 8-B, the inlet header crane base. When they ar-
rived, they observed that the form was not finished and
the carpenter and ironworker crews were still working
on it. From the drawings, it appears that the concrete for
that day was to begin at ground level and rise to ap-
proximately 15 feet, the height of the form when fin-
ished. Because it had not yet been finished, the form
lacked handrails, some of the ladders had not been
placed and vertical rebar had not been capped. The
crew, particularly Steward Kissler, decided it was not a
safe workplace. A cement truck had already arrived and
the pour was scheduled to begin at 9 a.m. Nonetheless,
the crew decided to check with Safety Supervisor Jim
Seaman, regarding whether or not work should begin.
Both Steward Kissler and Larry Jones saw Seaman
nearby and spoke to him about it. Seaman looked the
pour over, apparently concluded that the unfinished
forms raised a safety question, and told them he would
discuss it with Ebasco's safety personnel. He left to do
that. In the meantime, the crew decided among them-
selves that they would not work until the handrails were
up. While they awaited Seaman's return, they observed
Buffington on the ring wall with Ray Lewis, a quality
control man. While they waited Lewis came down and
told them Buffington wanted them to begin the pour.
Wells told him that he was not going to begin because it
was not safe, and Lewis told him "go ahead and swing
the bucket out anyway .... " According to Pendergrass
and Stedham, Wells refused to do so. Wells himself said
that he simply told Mud Crew Foreman Don Scott "that
we could not start the pour until we heard word from
the safety man on whether or not it was safe." At ap-
proximately 11:30, according to Stedham,3 Seaman told
them the pour was not to begin until the rails were up.
As a result the crew took an early lunch. When they re-
turned at approximately I p.m., the guard rails had been
installed in at least one section of the form and they
began to pour.
At this point it should be observed that Project Man-
ager Stamp and Buffington both testified without contra-
diction that this particular pour was delayed for three
reasons: (I) the forms were not ready, (2) the reinforcing
iron was not ready, and (3) the iron inserts (anchors)
were not installed. Stamp testified that the pour was de-
It seems unlikely that it would have taken Seaman from 9 to 11:30
a.m. to tell them the pour was to be delayed. I believe Stedham's testimo-
ny to be an exaggeration. The delay was probably no more than 15 min-
utes. for the Ebasco safety people were nearby.
layed pursuant to a joint decision of Ebasco Services,
Buffington, and Seaman. He admits he understood that it
was the Laborer steward who had raised the handrail
issue. He also concedes that the first load of concrete
was lost and that a certain amount of overtime was re-
quired later that day to make up for the delay. He mini-
mized the latter observation by saying that even without
the delay some overtime would have been required
anyway. Stamp also testified that he did not blame the
mud crew for the lost concrete, but on the fact that the
forms were not ready.4
The General Counsel argues from this scenario that I
should conclude that the mud crew had engaged in a
protected work stoppage to await the correction of cer-
tain safety matters and that the discharge which followed
2 days later was principally motivated by it. I have no
difficulty in concluding that the mud crew members con-
cluded among themselves that they would not work on
this particular pour until the handrails were installed, the
rebar capped, and the ladders in place. Nonetheless, it
appears to me that nothing out of the ordinary occurred.
Steward Kissler, following the proper procedure, pointed
out the safety question to the safety supervisor, who
went to the project overseer, Ebasco. At the same time,
it is also clear that the forms were not complete. All wit-
nesses are in agreement that the ironworkers and carpen-
ters were still constructing the forms, and commonsense
can only lead to the conclusion that if the forms were
not ready for concrete, concrete could not be poured.
The reason the rails and ladders were not set was be-
cause the forms were not finished. The rails are the last
thing to be installed and the form would not be complet-
ed until they were. But aside from that, the absence of
finished reinforcing iron and inserts further dictated that
the pour not begin.
Thus, even though the mud crew did not want to
work on those forms, it does not appear that they were
ever forced to refuse. They were prepared to do so, but
did not have to, and therefore did not. After Ebasco's
and Respondent's management consulted with one an-
other, the crew was sent to an early lunch to await com-
pletion of the forms. Finally, I observe that even though
the crew made a decision not to go to work until the
safety matters were corrected, there is no credible evi-
dence that Respondent was aware of that decision. It is
true that Pendergrass and Stedham thought that Jones
had refused Lewis' request to go to work, but it does not
even appear that Jones spoke to Lewis. Instead he spoke
to Scott, and no one has shown Scott to have done any-
thing but remain silent while Seaman spoke with Ebasco.
Accordingly, I am unimpressed with the General Coun-
sel's evidence that either Buffington or Stamp was aware
of the crew's decision. Even if they were, there is no
evidence that they believed the crew's concern caused
the delay. The delay was solely attributable to the fact
that the forms were not ready for concrete. In addition,
they knew that the union steward's safety concern was
legitimate.
4 On a project this size one load of lost concrete is no doubt a ery
minor expense.
Z U R N I N D U S T R I E S , I N C ~ ~~
~~~~~~.
3
640
DECISIONS OF NATIONAL LABOR RELATIONS BOARD
The pour of August 15, having started on an inauspi-
cious note, continued to sour. During the pour, two of
the three vibrators broke and the tremie chute (a chute
attached to the crane-borne bucket which keeps the
mixed concrete from separating while falling) all broke,
leaving vibrator man Wells to do the work of two men
and permitting the aggregate to separate on impact. The
job was also hampered to some extent by the fact that
portions of the form were still being worked on by the
ironworkers and carpenters, though, frankly, I doubt the
testimony to the effect that the other crafts interfered
significantly. It appears that those crafts were working at
some distance from the pour on other sections of the
form.
On August 16 another pour was made, which required
concrete to be placed against a 45-degree hillside. A cer-
tain amount of difficulty was encountered with that
pour, and there is conflicting testimony with respect to
whether or not the vibrators were working properly. I
do not deem it necessary to resolve that conflict, though
the work is said to have had some bearing on the crew's
discharge the following day. Nonetheless, vibratormen
were seen on that occasion attempting to move concrete
laterally with the vibrator, an unacceptable practice as it
tends to break up the aggregate and causes it to be
uneven, thereby affecting its strength.
On the morning of Friday, August 17, the forms for
the August 15 pour were removed, revealing for the first
time serious deficiencies in the quality of the pour. The
north face of the header on that pour was most deficient,
containing numerous rock pockets and voids. (See Resp.
Exh. 4, pp. 2 and 4, diagrams for the repair order.) One
void was so bad it actually created a hole through the
entire wall. (See Resp. Exh. 7, bottom photo, where to
demonstrate the void a reinforcing bar was inserted
through the entire foundation.) Needless to say, both Re-
spondent's quality control people as well as those of
WPPSS were quite alarmed by the poor quality of work.
Respondent's quality control office informed Stamp im-
mediately. On that day, WPPSS wrote a complaint letter
to Respondent, though it was not received for several
days.
Respondent's project manager, Stamp, testified that on
learning of the workmanship he decided to discharge the
entire mud crew. He had had doubts about the quality of
work being performed by the crew since an August 3
pour and had had a number of conversations with Buff-
ington about its members.5 Both Stamp and Buffington
agree that they had discussed certain instances involving
some members of the mud crew who had expressed re-
luctance to do other work when pours were not sched-
uled. While the evidence supporting their conclusions is
not totally clear, Stedham admitted conduct quite similar
while explaining the difficulties the mud crew encoun-
tered on the August 15 pour. Stedham is an experienced
concrete worker and considered to be a good vibrator
man. Before becoming the leadman and operating the
truck chute, as he did on August 15, he had been a vi-
brator man. When an operable vibrator was obtained to
I Resp. Exh. 5 contains three photographs (two of the same error)
with respect to the August 3 pour.
replace one of the broken ones on August 15, Laborer
Foreman Chavie asked Stedham to run it. Chavie's re-
quest was no doubt reasonable, considering the fact that
the other vibrator man, Alexander, was inexperienced
and was doing noticeably poor work. Nonetheless, Sted-
ham admittedly refused. That refusal lends credence to
Stamp's and Buffington's testimony that mud crew mem-
bers were reluctant to perform jobs other than their
own.
Both Stamp and Buffington testified that the decision
to discharge the mud crew was solely made by Stamp on
August 17. In addition, at the confrontation which oc-
curred that afternoon, Buffington told the crew that the
decision had been made by his superior, which could
only mean Stamp.6
At approximately 3:30 p.m., the concrete crew mem-
bers received termination notices. Each slip contained a
checkmark in the box marked "does not work to our sat-
isfaction. " ?7
Pendergrass asked Chavie, who had deliv-
ered his slip, what the underlying reason for the dis-
charge was. Chavie replied that he had been told "poor
vibration." Pendergrass and those other members of the
crew who had not worked as vibratormen were in-
censed. While they agreed that the poor vibration work
had occurred on August 15, they did not believe they
should be blamed for it, principally because they had not
operated the vibrators; second, because they believed
that the poor vibration was in large part due to Respond-
ent's failure to supply the vibratormen with operable
equipment; and third, because they knew Respondent
was aware of Alexander's inexperience.
Although the crew did not descend on Buffington in
his office en masse, nonetheless within a matter of min-
utes the entire crew was either in Buffington's office or
in the doorway. All, with the possible exception of Alex-
ander, were in earshot. The first to arrive, and the most
vocal, was Stedham. Stedham admits yelling at Buffing-
ton and demanding to know why the entire crew was
being fired. Buffington responded that the crew had not
worked to his satisfaction and had engaged in "poor vi-
bration." Stedham shouted he had not run a vibrator and
Buffington said, "It came from above, that we've been
hearing too much commotion about safety and the poor
vibration was not the only reason, but he had been hear-
ing too much commotion about safety from the crew and
that he and Stamp thought they could do better with a
whole new crew." Stedham responded it was not the
crew's fault; that it was the way Buffington scheduled
pours and the lousy equipment. Stedham offered "to kick
his ass" because he thought Buffington was a slob.
Kissler intervened saying to Stedham that he was wast-
ing his time. Stedham, however, continued shouting and
` It is true that in his second affidavit Buffington says he was the sole
person to make the decision and did not consult Stamp. Nonetheless, in
view of statements attributed to him at the conlfrontation. which are con-
sistent with his testimolly before me, I conclude his testimonly is the more
accurate.
' All six were also listed as "ineligible for rehire," A stipulation of the
parties shows that at a grievance settlement meeting o
August 31
Kissler was reinstated as of September 4 without backpay, and the re-
maining termination slips were modified to show the others were eligible
for rehire.
ZURN INDUSTRIES, INC.
641
admits calling Buffington a "chickenshit," an "asshole," a
"mother fucker," and an "unfit supervisor." Stedham
says Buffington used similar language in return.
Pendergrass testified that he could hear Stedham yell-
ing before he even arrived and heard Stedham complain-
ing that he did not run a vibrator, but "busted buckets"
to which Buffington replied, "Well, we've been hearing
a lot of commotion from the concrete crew about safety
and it came down from George [Stamp] to get rid of you
all and so I did."
Tony Wells testified that he heard Stedham ask Buff-
ington why he was fired. Buffington replied he was fired
for "unsatisfactory work." When Stedham asked what
was unsatisfactory, Buffington said that "there was poor
vibration on the concrete crew and that he had received
word from higher up in the office to fire the whole
crew." After the General Counsel suggested the topic of
safety and some byplay among counsel and myself, the
General Counsel asked Wells the following:
Q. (By Mr. Brennan) Would you please tell us
what was said and by whom, regarding complaints?
A. Mr. Buffington had stated to Steve Stedham
that the higher up offices had been hearing com-
plaints from the concrete crew and that he was told
to fire the whole crew.
Q. Do you recall if he said what those complaints
were about?
A. About the project site, about the safety skip
that was-that they said was right for the job site
and just general complaints.
Larry Jones testified that he heard Stedham ask Buff-
ington, "Kester, what the hell is this? You can't fire me
for this." Buffington replied, "Well, that's one of the rea-
sons why I fired you, is your attitude." Jones interrupted
saying, "No, you can't tell us its our attitude, now why
did you fire us?" Jones says Buffington looked at him
and then at Stedham and said, "Well, you don't expect
me to keep you on the job with a pour like that. Look at
that pour," referring to the August 15 job. Both ex-
plained that the vibrators were broken and Stedham said,
"Goddamn it Kester, I wasn't even on that pour, I was
running the chute." Jones chimed in saying, "Damn it,
Kester, I wasn't even on that pour either, I was tearing
apart your broken vibrators that you already knew were
broken." Then Jones says Buffington looked at both and
"kind of hee-hawed around" and said, "Well, you've got
me, the reason you were fired is because you were com-
plaining about safety, and people above my head found
out about it. And I had to let you go." Jones went on to
say that he had heard "what I wanted to hear and I kind
of turned and walked out." Immediately on cross-exami-
nation, Jones explained his last remark by saying "[Buff-
ington] said that he fired us because we were complain-
ing about safety and that's against the law and I planned
on hanging his ass right here in court."
As noted previously, Buffington was called as an ad-
verse witness by the General Counsel, who did not ask
him about his version of the August 17 confrontation.
Respondent did not choose to recall him during its case.8
The General Counsel argues that Buffington made ad-
missions against interest to the above employees, which
are undenied. Indeed, on a cold record it would appear
that Respondent abandoned its obligation to defend.
However, that would ignore considerations of demeanor
and fervor which were apparent to me as I listened to
the testimony. Certainly the testimony of Jones shows
bias in its face, and it rang untrue. Likewise the testimo-
ny of Stedham and Pendergrass did not appear convinc-
ing with respect to its veracity on the question of wheth-
er or not Buffington referred to safety. Only Wells' ini-
tial testimony seemed to have an objective view of what
occurred in that office. And, even after being cued Wells
did not describe anything like Buffington's supposed ad-
mission as reported by the other three.9
His testimony
appears to me to be the closest to the truth. This is not
to say that I am discrediting either Pendergrass or Sted-
ham on the basis of deliberate prevarication, though that
may have been the case: rather, it seems to me that they
were excessively sensitive to the safety skip matter, were
aware of the agreement not to work on August 15, and
were ready to ascribe an evil motive to nearly anything
negative which occurred. Jones is even worse than those
two in this regard. He said that he "wanted to hear" an
admission from Buffington; accordingly, he did. That
Buffington ever uttered such an admission is most doubt-
ful.
In analyzing both Stedham's and Pendergrass' testimo-
ny here, I note that both said Buffington remarked that
there had been too much "commotion" about safety
from the concrete crew. In themselves, the statements
smack of improbability. The only "commotion" about
safety was by the ironworkers over the safety skip on
August 15.10 The mud crew's August 15 decision not to
work until the site was approved as safe raised no com-
motion either, and Buffington could not have been refer-
ring to that incident. In any case it was submerged by
the fact that concrete could not have been placed until
the forms were finished. Thus, I do not credit Stedham's
and Pendergrass' testimony here.
Frankly, the only probable scenario is that the mud
crew employees were discharged because of the results
achieved on the August 15 pour, discovered on August
17. No one disagrees with Respondent's conclusion that
the work was unacceptable. And, as it involved the
structural integrity of a nuclear reactor cooling tower as
well as the integrity of the base for the construction
crane, the discharge of those who performed the work is
not surprising. That is particularly so where Respondent
' The General Counsel did not question Alexander about this incident
either; there is some testimony that Alexander was not present. but the
record is not clear on the point. The General Counsel did not ask Ste-
ward Kissler about what occurred either. It may be that he did not hear
the admission or he may have left before Stedham induced it. It may also
he that it did not occur and he could not have honestly testified that it
did.
9 Wells' reference to the skip in his cued testimony is unlikely since
that was an ironworker-raised matter. which Buffington was not likely to
have placed at the feetl of the mud crew.
"' Steward Kissler's mild involvement in that issue had occurred
weeks earlier and can only be considered remote.
ZURN
INDUSTRIES,
INC.
641
642
DECISIONS OF NATIONAL LABOR RELATIONS BOARD
is agreed to be generally responsive to safety issues, and
the integrity of the plant and its principal construction
tool-the crane-are put in question. In that context, I
therefore discredit those versions based on both internal
improbability as well as circumstantial improbability. It
follows that the General Counsel's witnesses were inher-
ently unreliable with respect to that issue and that there-
fore the General Counsel did not make out a prima facie
case. In that circumstance, it was unnecessary for Re-
spondent to have recalled Buffington for the purpose of
making a specific denial.
I recognize that to some extent the poor concrete
work was not the direct fault of the crew. Certainly the
defective equipment contributed to the poor workman-
ship. Nonetheless, that deficiency on the part of manage-
ment does not add anything to the General Counsel's al-
legation that they were fired for having expressed con-
cern regarding safety practices. No doubt Respondent
accepts its ultimate responsibility for the poor workman-
ship; in fact, Respondent took several steps to correct it.
One of those steps, however, included discharging the
entire crew. In view of the awful results achieved by the
crew a blanket solution-i.e., getting rid of all in-
volved-would not be an unlikely response. It is also
true that the response was unfair to those who had not
engaged in the vibrator work or to those who had used
faulty equipment. Nonetheless, no law was violated with
respect to it; indeed the unfairness was recognized a few
weeks later when cooler heads prevailed during the
Union's handling of the grievance. There the Union ap-
pears to have acknowledged that the crew had per-
formed poorly and a certain amount of discipline was
reasonable. Likewise, Respondent acknowledged that its
discipline was too drastic and compromised by reinstat-
ing Kissler and permitting the Union to again refer the
remainder of the crew for reemployment.
In conclusion I find that the General Counsel has
failed to prove by credible evidence that Respondent dis-
charged its concrete crew on August 17 because it be-
lieved the crew members had a propensity for engaging
in safety matters.
Based on the foregoing findings of fact and the record
as a whole, I hereby make the following:
CONCLUSIONS OF LAW
1. Respondent is an employer within the meaning of
Section 2(2) of the Act, engaged in commerce and in an
industry affecting commerce within the meaning of Sec-
tion 2(6) and (7) of the Act.
2. The Union is a labor organization within the mean-
ing of Section 2(5) of the Act.
3. Respondent has not engaged in the unfair labor
practices as alleged in the complaint.
[Recommended Order for dismissal omitted from pub-
lication.]