327 NLRB 449
Teamsters Local 166 (Shank/Balfour Beatty)
TEAMSTERS LOCAL 166 (SHANK/BALFOUR BEATTY)
427
Teamsters Local Union No. 166 (Shank/Balfour
Beatty) and California Dump Truck Owners As-
sociation. Case 31–CE–212
January 26, 1999
DECISION AND ORDER
BY MEMBERS FOX, LIEBMAN, AND BRAME
On October 1, 1998, Administrative Law Judge Mi-
chael D. Stevenson issued the attached decision. The
General Counsel and the Charging Party filed exceptions
and supporting briefs, the Respondent filed an answering
brief, and the Charging Party filed a reply brief.1
The National Labor Relations Board has delegated its
authority in this proceeding to a three-member panel.
The Board has considered the decision and the record
in light of the exceptions and briefs and has decided to
affirm the judge’s rulings, findings, and conclusions and
to adopt the recommended Order as modified.
The General Counsel and the Charging Party have ex-
cepted to the judge’s recommended Order.2 They assert
that the Order is overly narrow in that it applies only to
deliveries to the City Creek Portal of the Inland Feeder
Project jobsite. We find merit to these exceptions and
grant the remedy sought by the General Counsel.
The record shows that the Inland Feeder Pipeline Pro-
ject (the Project) is a single construction project involv-
ing the construction of an underground water distribution
pipeline and tunnel. There are at least two entrances to
the site: the City Creek Portal and the Strawberry Creek
Portal. Shank/Balfour Beatty, the Employer, was en-
gaged to perform certain excavation work for the Project,
which required it to, inter alia, furnish and deliver to the
Project jobsite cement water tunnel-support segments
(segments) which the Employer would use to shore up
the tunnel as the excavation progressed. The segments
were cast at a facility owned by Robertson’s Ready Mix
(Robertson’s), located about 4 miles from the Project’s
City Creek Portal and several miles further away from
the Strawberry Creek Portal.3
The judge determined that the Employer and the Re-
spondent entered into an unlawful agreement, in viola-
tion of Section 8(e), to refrain from using owner-
operators to deliver the segments at the Project’s City
Creek Portal.4 To remedy the Respondent’s unlawful
actions, the judge’s recommended Order requires the
Respondent to cease and desist from entering into, main-
taining, reaffirming, giving effect to, invoking, or enforc-
ing such agreements with respect to the delivery of seg-
ments from Robertson’s to the Project’s City Creek Por-
tal. The judge rejected the General Counsel’s contention
that the order should apply to all segment deliveries to
the Project from Robertson’s, regardless of which Project
entrance was used, because the judge viewed the General
Counsel’s position as equivalent to a request for a broad
cease-and-desist order.
1 The Respondent’s motion to strike the Charging Party’s exceptions
is denied as lacking in merit.
2 The judge’s recommended Order requires the Respondent to cease
and desist from “entering into, maintaining, reaffirming, giving effect
to, invoking, or enforcing the terms of the Inland Feeder Project Labor
Agreement or any other agreement in which Shank/Balfour Beatty
agrees, or has agreed, to cease or refrain from doing business with any
other person, including the owner-operators of any vehicle, with respect
to the transportation of cement water tunnel-support segments from the
Robertson’s Ready Mix storage site to the City Creek Portal location
and surrounding areas on the Inland Feeder Pipeline Project.”
3 The record does not disclose the exact distance from Robertson’s to
the Strawberry Creek Portal.
4 The Respondent has not excepted to that determination.
Contrary to the judge, we find that it will effectuate the
policies of the Act to prohibit the Respondent from enter-
ing into, maintaining, reaffirming, giving effect to, in-
voking, or enforcing any agreement to refrain from using
owner-operators for the delivery of segments from
Robertson’s to any entrance to the Project.5 It is true that
the agreement found unlawful herein was entered into to
resolve a dispute over the manning of the delivery of
segments through the City Creek Portal, and that deliver-
ies through the Strawberry Creek Portal were not in-
volved. However, it is clear from the record as a whole
that the Respondent’s position with respect to the deliv-
ery of segments from Robertson’s was that the Employer
could not use owner-operators to make such deliveries to
any location on the Project. Moreover, the logic behind
the judge’s finding that the agreement not to use owner-
operators for segment deliveries from Robertson’s to the
City Creek Portal violated Section 8(e) would apply with
equal force to an agreement not to use owner-operators
for deliveries through the Strawberry Creek Portal, as in
either case the transportation and delivery of the seg-
ments is not jobsite work.
ORDER
The National Labor Relations Board adopts the rec-
ommended Order of the administrative law judge and
orders that the Respondent, Teamsters Local Union No.
166, International Brotherhood of Teamsters, Chauffeurs,
Warehousemen and Helpers of America, its officers,
agents, and representatives, shall take the action set forth
in the Order as modified.
1. Substitute the following for paragraph 1(a).
“(a) Entering into, maintaining, reaffirming, giving ef-
fect to, invoking, or enforcing the terms of the Inland
Feeder Project Labor Agreement or any other agreement
in which Shank/Balfour Beatty agrees, or has agreed, to
5 This limited expansion of the judge’s order is not, as the judge
stated, equivalent to the issuance of a broad cease-and-desist order.
Such orders prohibit a respondent from engaging in unlawful conduct
involving any person engaged in commerce. Cf. Sheet Metal Workers
Local 27 (Cahill Monmouth Contracting), 292 NLRB 1046 (1989)
(broad order inappropriate unless respondent shown to have a proclivity
to violate the Act). The order herein only applies to agreements be-
tween the Respondent and the Employer, and is further limited in its
application to agreements involving the delivery of segments from
Robertson’s to the Project.
327 NLRB No. 84
DECISIONS OF THE NATIONAL LABOR RELATIONS BOARD
428
cease or refrain from doing business with any other per-
son, including the owner-operator of any vehicle, with
respect to the transportation of cement water tunnel-
support segments from the Robertson’s Ready Mix stor-
age site to any location on the Inland Feeder Pipeline
Project.”
2. Substitute the following for paragraph 2(a).
“(b) Rescind and render null and void and of no effect
any agreement in which Shank/Balfour Beatty agrees or
has agreed, to cease or refrain from doing business with
any other person, including the owner-operator of any
vehicle, with respect to the transportation of cement wa-
ter tunnel-support segments from the Robertson’s Ready
Mix storage site to any location on the Inland Feeder
Pipeline Project.”
3. Substitute the attached notice for that of the admin-
istrative law judge.6
APPENDIX
NOTICE TO MEMBERS
POSTED BY ORDER OF THE
NATIONAL LABOR RELATIONS BOARD
An Agency of the United States Government
The National Labor Relations Board has found that we vio-
lated the National Labor Relations Act and has ordered us to
post and abide by this notice.
WE WILL NOT enter into, maintain, reaffirm, give ef-
fect to, invoke, or enforce the terms of the Inland Feeder
Project Labor Agreement or any other agreement in
which Shank/Balfour Beatty agrees, or has agreed, to
cease or refrain from doing business with any other per-
son, including the owner-operator of any vehicle, with
respect to the transportation of cement water tunnel-
support segments from the Robertson’s Ready Mix stor-
age site to any location on the Inland Feeder Pipeline
Project.
WE WILL rescind and render null and void and of no
effect any agreement in which Shank/Balfour Beatty
agrees or has agreed, to cease or refrain from doing busi-
ness with any other person, including the owner-operator
of any vehicle, with respect to the transportation of ce-
ment water tunnel-support segments from the Robert-
son’s Ready Mix storage site to any location on the In-
land Feeder Pipeline Project.
TEAMSTERS LOCAL UNION NO. 166
Ann Cronin-Oizumi, for the General Counsel.
Robert V. Kuenzel, of San Rafael, California, for the Charging
Party Employer.
6 If this Order is enforced by a judgment of a United States court of
appeals, the words in the notice reading “Posted By Order Of The Na-
tional Labor Relations Board” shall read “Posted Pursuant To A Judg-
ment Of The United States Court Of Appeals Enforcing An Order Of
The National Labor Relations Board.”
Jeffrey L. Cutler and Lourdes M. Garcia, of Encino, California,
for Respondent Union.
DECISION
STATEMENT OF THE CASE
MICHAEL D. STEVENSON, Administrative Law Judge.
This case was tried before me at Los Angeles, California on
May 11 and 12, 1998,1 pursuant to a complaint issued by the
Regional Director for the National Labor Relations Board for
Region 31 on April 20, 1998, and which is based on charges
filed by California Dump Truck Owners Association (the
Charging Party or Owners Association) on November 25, 1997,
and on February 18, 1998 (first amended charge). The com-
plaint alleges that Teamsters Local Union No. 166 (Respon-
dent) has engaged in certain violations of Section 8(e) of the
National Labor Relations Act (the Act).
ISSUE
Whether Respondent violated the Act by entering into and
maintaining an agreement with the Employer, Shank/Balfour
Beatty, according to the terms of which agreement, the Em-
ployer would not do business with nor otherwise use self-
employed truck owner-operators to perform certain work, be-
cause the owner-operators are independent contractors, and not
employees, within the meaning of the Act.
All parties were given full opportunity to participate, to in-
troduce relevant evidence, to examine and to cross-examine
witnesses, to argue orally, and to file briefs. Briefs, which have
been carefully considered, were filed on behalf of the General
Counsel, the Charging Party, and the Respondent.
On the entire record of the case, and from my observation of
the witnesses and their demeanor, I make the following
FINDINGS OF FACT
THE ALLEGED UNFAIR LABOR PRACTICE
A. Facts (Stipulated)
In a stipulation executed on May 11, 1998 by all parties, it
was agreed that Shank/Balfour Beatty (Shank) is now and has
been at all times material to this case, a partnership between
two California corporations, M. L. Shank Co., Inc., and Balfour
Beatty Construction, Inc., and that Shank’s office and principal
place of business is located in Highland, California (GC Exh.
1(j), par. 3(a)). It was further agreed that within the past calen-
dar year, Shank purchased and received in California, materials
and supplies valued in excess of $50,000 either directly from
suppliers located outside the State of California or from suppli-
ers who themselves had obtained such materials and supplies
directly from outside California (par. 3(b)). Finally, it was
agreed that for all times material to this case, Shank was an
employer engaged in commerce and in a business affecting
commerce within the meaning of Section 2(6) and (7) of the
Act (par. 4).
In the same stipulation, the parties agreed that for all times
material to this case, Respondent is a labor organization within
the meaning of Section 2(5) of the Act (par. 5), and for the
same time period, that Respondent has two officials, Errol
Haynes and Robert (Bob) Wiley, who are president and busi-
ness representative respectively, and who are both agents of
Respondent within the meaning of Section 2(13) of the Act
(par. 6).
1 All dates herein refer to 1997 unless otherwise indicated.
TEAMSTERS LOCAL 166 (SHANK/BALFOUR BEATTY)
429
The stipulation recites other facts relevant and material to
this case: the Metropolitan Water District of Southern Califor-
nia (MWD), is engaged in the construction of a water distribu-
tion pipeline and water tunnel near San Bernardino, California,
called the Inland Feeder Pipeline Project (Project). Parsons
Constructors (Parsons) is the project manager for the Project.
Construction is now occurring at the City Creek Portal section
of the Project (par. 7).
The MWD has subcontracted certain work on the Project to
Shank, including certain tunneling work (par. 8).
Respondent and various other labor organizations have en-
tered into the Inland Feeder Project Labor Agreement (PLA)
(GC Exh. 4), which is effective by its terms from August 1,
1996 through the completion of the project (par. 9).2 On or
about February 7, in a letter to the MWD (GC Exh. 2), Shank
agreed to abide by the terms and conditions of the PLA, and to
require all of its subcontractors to sign a letter of assent to the
PLA (par. 1(o)) (GC Exh. 2).
On or about February 9, 1998, Shank sent a letter (GC Exh.
3) to Respondent which was received by Haynes on or about
February 10, 1998 (par. 11).
B. Facts (Nonstipulated)
1.
I will recite the February 9, 1998 letter below, but for now I
begin by noting that with perhaps one exception, all remaining
significant facts in this case are undisputed. Next, I reproduce a
map (GC Exh. 8) that was offered into evidence to assist the
reader who may not be familiar with the area of Southern Cali-
fornia in issue.
2 The record contains two PLAs: The one offered by General Coun-
sel is dated August 7, 1996 (GC Exh. 4); the other offered by Respon-
dent is dated August 1, 1996 (R. Exh. 6). Whatever differences which
exist between the two versions are not germane to this case.
Point 4 on the map designates Robertson’s Ready Mix Co.
and surrounding yard. This location is approximately 4 miles
from City Creek Portal (Point 1 on map) as indicated by the
arrows on the map over several different public streets and
highways. Other than use of these public thoroughfares, there
is no other way for trucks or other vehicles to get to one loca-
tion from the other and vice versa. However, since the trip
from Robertson’s to City Creek Portal involves navigating an
upward grade of undescribed degree, the trip down is faster,
particularly in an empty tractor-trailer which has dropped off a
load.
No one from Robertson’s testified, but Gerald Stokes, the
project manager for Shank (the general contractor on the pro-
ject in question) and General Counsel’s sole witness at hearing,
aptly described the role of Robertson’s in this case.
In order to build the (6-mile) tunnel referred to above, two
problems among others had to be solved: where to put the dirt
excavated from the tunnel, and how to shore up the tunnel
safely and efficiently. Robertson’s played a role in resolving
both matters. First, the material taken from the tunnel was
separated into topsoil and other dirt. The former was trans-
ported from City Creek Portal to the Muck Storage Site (Point 3
on map). Shank arranged for owner-operator truck drivers
(independent contractors) to pick up and deposit the topsoil. As
the crow flies, the distance from pick up to deposit was about
200 yards. Using available roads, however, the drivers covered
a distance of about 1–1½ miles. This operation began in early
1997 with three owner opreators and their trucks furnished by
Hernandez Trucking Co., an affirmative action business enter-
prise which was part of an outreach program.3 No representa-
tive of Hernandez testified, but Stokes described the business as
one which both employs truckdrivers and acts as a broker for
owner-operators. The owner-operators furnished to Shank by
Hernandez Trucking Co., for the haul to the Muck Storage Site
were not dispatched from Respondent’s hiring hall and not
covered by the PLA.
3 Hernandez Trucking is a member of the Charging Party.
DECISIONS OF THE NATIONAL LABOR RELATIONS BOARD
430
On or about July 7, Respondent became aware of the Muck
Storage Site haul and protested to Shank the use of independent
owner-operators for the work. Since Shank claimed the work
in question was not covered by the PLA, Respondent filed a
grievance on or about July 10 (GC Exh. 5) to resolve that issue.
During subsequent meetings in July undertaken to attempt to
resolve the grievance, the parties were not successful.4 How-
ever, by September 29, without a referral to arbitration, Shank
and Respondent did resolve the matter:
September 29, 1997
Meeting
In Attendance:
Jerry Stokes–Shank/Balfour Beatty
Shel Coudray–MWD
Dick Boyles–PCI
Re: Settlement effort: I.B.T. #166/S/BB Owner-Operator
Grievance
A meeting was held with Teamsters Local Union #166
President Errol Haynes, Gary Dixon and Dick Boyles late
Friday, September 26th, 1997 in an effort to offset the
pending Arbitration regarding Owner-Operators.
After lengthy discussions Errol Haynes offered to set-
tle the grievance filed by Frank Muchow, Mike Shau and
Jerry Lowder in a non-precedent setting manner for twelve
(12) days pay at the applicable rate to be divided equally
among the grievants.
If Shank/Balfour Beatty can agree to this Settlement
please sign below.
/s/ Jerry Stokes
r
c.
Jerry Stokes for
Shank/Balfour Beatty
Dick A. Boyles fo
Parsons Constructors In
/s/ Shel Coudray
/s/ Errol Haynes
t
6
Shel Coudray (witness) for
Metropolitan Water District
Errol Haynes, Presiden
Teamsters Local Union
#16
(GC Exh. 6)
This settlement resulted in the payment by Shank of about
$2000 to Respondent in accord with the stipulated terms. Re-
spondent claimed it settled for much less than was due and
owing under the terms of the PLA.
2.
The other dirt excavated from the tunnel was hauled from
City Creek Portal to Robertson’s which allowed Shank the use
of its yard without Shank having to pay the customary dumping
fee. In the course of this operation, Shank furnished a bull-
dozer to move and grade the dumped earth and a water truck to
continually spray the area to reduce dust. Both pieces of
equipment were operated by Shank employees, covered by the
PLA, the bulldozer by an Operating Engineer, and the water
truck by a Respondent member. The actual haul itself was
performed in July by a combination of nonunion employees of
Hernandez and owner-operators also furnished by Hernandez.
For this work, Respondent not only didn’t claim it, but through
4 In a letter of July 17, to Respondent, Shank claimed it did not vio-
late the PLA and gave reasons in support of its position (CP Exh. 1).
its president, Haynes, specifically disavowed any contention
that the dumping of dirt at Robertson’s yard was covered by the
PLA and/or that the owner-operators would have to be employ-
ees. On August 6, Stokes sent a letter (GC Exh. 9) to Haynes
confirming the above position which Haynes had previously
related to Stokes. Haynes did not reply.
In his testimony, as Respondent’s witness, Wiley explained
Respondent’s rationale for not claiming the work involving the
dirt haul to Robertson’s:
because it completely went off the site of work. It went out-
side the boundaries of the right-of-way on the jobsite com-
pared to the Muck disposal site that went . . . 200 yards as the
crow flies, but around the block to get it there. That was
within the right-of-way of this job.
(Tr. p. 292)
In sum, according to Wiley, the work was simply not within
Teamsters jurisdiction (Tr. p. 293).
3.
The dirt dumped into Robertson’s from City Creek Portal
was transported over a number of local streets shown on the
map (GC Exh. 8). The work in issue in this case concerns con-
crete segments to be used to shore up the tunnel transported on
the very same streets for approximately the same distance.
There were two differences, the segments were going up to City
Creek Portal compared to the dirt coming down, and Respon-
dent claimed the work of driving the tractor-trailers rather than
disavowing it.
To shore up the tunnel, Shank decided to use concrete seg-
ments, each weighing about 6000 pounds. It takes four seg-
ments to shore up 4 lineal feet of tunnel. About 40 percent of
the 4000 segments needed has been manufactured thus far. The
work is being done in the Robertson’s yard on top of the dirt
base dumped there from the excavated tunnel. The company
doing the work is Coast GEO, a minority owned company,
which apparently is unionized. No representative of Coast
testified.
The work already done has accumulated in Robertson’s yard
rather than been transported to City Creek Portal due to certain
unforeseen complications in excavating the tunnel and confu-
sion and uncertainty over the pending issue as to whether the
work driving the tractor-trailers is covered by the PLA.
Stokes made it clear in his testimony and I find that Shank’s
intention had been to solicit bids from Hernandez and others for
independent contractors to do the work. The “work” involved
driving the segments the approximate 4 miles up and driving
the empty truck back, and both at Robertson’s and at City
Creek Portal the driver has to exit the tractor to unlatch the
trailer and cause the fifth wheel to come down. The trailer is
then left at the location either with the segment on it or empty,
depending at which end this “work” is done, and a new trailer is
hooked up, again either loaded or empty. The driver’s non-
driving work at each end takes a minute or slightly more. The
work of loading and unloading the trailer and of stabilizing the
segment with timber blocks on the trailer is all done either by
Shank employees or by Coast GEO employees both unques-
tionably covered by the PLA.
Stokes testified that it would have been cheaper for Shank to
pay the owner-operators the going rate of $46–$55 per hour and
have them be responsible for the maintenance, insurance, and
other costs of running the tractors as compared to Shank acquir-
TEAMSTERS LOCAL 166 (SHANK/BALFOUR BEATTY)
431
ing a tractor and hiring one or more new employees from Re-
spondent’s hiring hall. Shank already owned one or more trail-
ers, which would carry the segments, so these would be fur-
nished to the owner-operators. Before the hearing ended,
Stokes reported that Shank could wait no longer, and had ar-
ranged to purchase a used tractor to be used in hauling the seg-
ments.
Sometime in July, Respondent became aware of Shank’s
plan to use owner-operators to transport the segments to City
Creek Portal and took the position that the work driving the
trucks was covered under the PLA. In a series of meetings
between Stokes, Wiley, and Haynes, and a representative of
Parsons named Gary Dixon, who did not testify, the parties
discussed Shank’s intention to transport the segments as de-
scribed above. These meetings, two in July and two in Sep-
tember, ostensibly were for the purpose of resolving Respon-
dent’s Muck Disposal grievance, but generally at these meet-
ings, the discussions turned to the planned segment haul from
Robertson’s yard. Dixon took a strong position at these meet-
ings in support of Respondent’s point of view that the work was
covered by the PLA. Moreover, Haynes and Wiley both stated
repeatedly at these meetings that if Shank decided to implement
its plan to use owner-operators, Respondent would file a griev-
ance under the PLA, just like the one they had filed to chal-
lenge use of owner-operators for the haul to the Muck Disposal
site.
By February, Shank had concluded that it was unwilling to
risk hiring the owner-operators it had planned to hire, having
the Respondent file its threatened grievance, and perhaps losing
the grievance in which case, it would have to pay both Respon-
dent and the owner-operators. Accordingly, on February 9,
1998, Stokes wrote a letter to Haynes, which reads as follows:
Teamsters, Local 166
18597 Valley Blvd.
Bloomington, CA 92316
Attention: Mr. Errol Haynes, President
Dear Mr. Haynes:
As
you
know,
within
the
next
few
weeks
Shank/Balfour Beatty (“S/BB”) will begin hauling seg-
ments from the Robertson’s Ready Mix casting yard, over
several miles of public roads, to the City Creek Portal on
the Arrowhead East Tunnel. This hauling will involve
some 4,000 loads.
S/BB had planned to perform this haul using reliable
and responsible, self-employed, owner operators who are
members of the California Dump Truck Owner’s Associa-
tion.
On February 4, 1998, however, you told me that the
union’s position had not changed and that all work in con-
nection with hauling the segments is jobsite work; is cov-
ered by the Inland Feeder Project Labor Agreement
(“PLA”); and that all provisions of the PLA must be ap-
plied to any self-employed owner operators performing the
work, namely that they must be dispatched by the union,
pay union fees and dues, and have trust fund payments
made for them.
Of course, this is the same position taken by Parsons
Constructors, Inc. (“PCI”) and the union in July of last
year, when PCI informed S/BB that PCI was a party to,
and had negotiated, the PLA, and that the intent of the
bargaining parties was that truck owner operators had to
be treated as employees. Moreover, since this same time,
PCI and the union have agreed and insisted that the length
of haul over public roads has nothing to do with whether
self-employed truck owner operators must be treated as
employees.
In the face of this concerted and unchanged position,
mindful of the costs and risks of defending against griev-
ance and arbitration, S/BB has no choice except to agree
with the union that the segment haul must be performed
under the PLA, and that S/BB will not use self-employed
truck owner operators without compelling them to be
treated as employees under the PLA.
If this agreement is found to be unlawful, S/BB re-
serves the right to hire self-employed truck owner opera-
tors in accordance with usual industry practice in Califor-
nia, without regard for the PLA.
Very truly yours,
/s/ G.G. Stokes
G.G. Stokes
Project Manager
(GC Exh. 3)
While Haynes did not respond, Dixon’s reply to this letter
reads as follows:
February 12, 1997
Mr. G.G. Stokes
Project Manager
Shank/Balfour Beatty
Arrowhead East Tunnel
Post Office Box 129
Highland, California 92346
Dear Mr. Stokes:
I am in receipt of a copy of your letter of February 9,
1998, to Errol Haynes, President, Teamsters Local 166.
Please be advised that you have misstated and mischarac-
terized Parsons constructors’ position.
We do not and cannot speak for Teamsters Local 166,
but with regard to Parsons’ position, the transportation of
supplies and/or materials which involves use of public
highways rather than exclusively on the construction site
(with or without the incidental use of public roads) does
not constitute covered work under the Project Labor
Agreement. How you intend to carry out the transporta-
tion of the segments between “Robertson’s Ready Mix
Casting Yard” to the “City Creek Portal” is strictly up to
you. If the Teamsters believe that such work is covered by
the Project Labor Agreement, they may, of course, inde-
pendently take whatever legal or contractual position and
action is available to them.
Sincerely
/s/ Gary
Gary D. Dixon, Sr.
(GC Exh. 7)
C. Analysis and Conclusions
1.
I begin by noting the Temporary Injunction Order and Find-
ings of Fact and Conclusions of Law entered by U.S. District
DECISIONS OF THE NATIONAL LABOR RELATIONS BOARD
432
Judge Kim McLane Wardlaw on May 18, 1998, pursuant to
Section 10(l) of the Act upon petition of the General Counsel.
Section 10(l) of the Act provides district courts with the power
to temporarily enjoin unfair labor practices that impinge on the
public interest in the free flow of commerce (i.e., strikes and
boycotts). Aguayo v. Tomco Carburetor Co., 853 F.2d 744 fn.
2 (9th Cir. 1988). The Order and Findings and Conclusions of
J. Wardlaw, attached to General Counsel’s brief, do not control
the Board’s disposition of unfair labor practices charges. Ad-
vertiser’s Mfg. Co., 280 NLRB 1185, 1186 fn. 3 (1986), and
accordingly are noted for background only.
2.
I turn next to Section 8(e) of the Act, which reads in perti-
nent part as follows:
It shall be an unfair labor practice for any labor or-
ganization and any employer to enter into any contract or
agreement, express or implied, whereby such employer
ceases or refrains or agrees to cease or refrain from han-
dling, using, selling, transporting or otherwise dealing in
any of the products of any other employer, or to cease do-
ing business with any other person, and any contract or
agreement entered into heretofore or hereafter containing
such an agreement shall be to such extent unenforceable
and void: Provided, That nothing in this subsection (e)
shall apply to an agreement between a labor organization
and an employer in the construction industry relating to
the contracting or subcontracting of work to be done at the
site of the construction, alteration, painting or repair of a
building, structure, or other work: . . .
In the recent case of Carpenters (Manufacturing Woodwork-
ers), 326 NLRB No. 31, slip op. p. 4 (Aug. 26, 1998), the
Board recited “Applicable 8(e) principles.”
Not every collective-bargaining agreement with a
“cease doing business” objective that comes literally
within the proscription of Section 8(e) is necessarily
unlawful. Thus, a union may lawfully require an employer
to cease or refrain from doing business with another em-
ployer if the union’s objective is properly found to be the
preservation of work traditionally performed by employ-
ees represented by the union.15 As the Supreme Court has
held, Section 8(e) does not prohibit agreements made and
maintained for the purpose of pressuring an employer to
preserve for its employees work which they have tradi-
tionally performed.16 Rather, the Court said that “[t]he
touchstone [of Section 8(e)] is whether the agreement or
its maintenance is addressed to the labor relations of the
contracting employer vis-a-vis his own employees” as op-
posed to being “tactically calculated to satisfy union ob-
jectives elsewhere.”17
__________________________
15 Electrical Workers IBEW Local 46 (Puget Sound NECA), 303
NLRB 48, 50 (1991), quoting from Operating Engineers Local 12
(Griffith Co.), 212 NLRB 343, 343–344 (1974), enf. denied 545 F.2d
1194 (9th Cir. 1976), cert. denied 434 US 854 (1977).
16 National Woodwork Mfrs. Assn. v. NLRB, 386 US 612, 635 (1967).
17 Id. at 645; Associated General Contractors, 280 NLRB 698, 701
(1986) (the focus of the analysis is whether the disputed clause has the
primary purchase of protecting unit work or unit standards, or the sec-
ondary purpose of promoting broader goals of the union by asserting
control over the labor relations of other employers).
In light of the above, I turn to the central question of whether
Shank and Respondent entered into an agreement within the
meaning of Section 8(e). The General Counsel addresses this
question at some length in her brief, pages 7–13, contending
that there was indeed an agreement. Respondent asserts in its
brief, page 6, “for a violation of Section 8(e) of the Act to be
found in the construction industry, parties must have entered
into an agreement that has a secondary effect on offsite work.
Shank and the Union did not enter into an agreement pursuant
to Section 8(e) of the Act.”
I find that the parties did indeed enter into an agreement and
I place reliance on Shank’s letter of February 9 to Respondent
(GC Exh. 3), recited above, particularly the final two para-
graphs. There is no issue regarding Respondent’s receipt of the
letter and its failure to disavow, clarify, or otherwise respond
constitutes an admission by silence, because if there were no
agreement, Respondent would reasonably be expected to deny
same. Coca-Cola Bottling Co., 313 NLRB 1197, 1200 (1994),
citing Jones, Evidence p. 524 (6th ed. 1972).5
The conclusion I reach above is reinforced by my credibility
findings in the Facts. Thus I find that Haynes and Wiley had
not only claimed the segment haul at various times in July and
September at meetings held to resolve a grievance regarding the
Muck Site haul, but that Respondent’s representatives had also
threatened to file a grievance in furtherance of their claim. I
specifically discredit and do not believe the testimony of
Haynes wherein he testified that he told Stokes on February 4,
1998, merely “that we claim all Teamsters work covered by the
PLA.” On cross-examination, Haynes added that he did not
“claim the segment haul from Robertson’s since it hadn’t
started yet.” This ignores the context of the entire issue includ-
ing the two other hauls described above. At page 323 of the
transcript, Haynes admitted that he told Stokes specifically that
Respondent didn’t claim the dirt haul to Robertson’s. Am I to
believe that Haynes would speak clearly on this point and
vaguely on the segment haul, leaving to Stokes to interpret his
meaning. I don’t believe it. Based on my view of his de-
meanor, Haynes was not the kind of man to speak in riddles. In
addition, Haynes’ testimony is contrary to what Stokes recited
in the letter of February 9, 1998 (GC Exh. 3), a letter which
Haynes never disputed.
So I find that Shank and Respondent entered into an agree-
ment and that the agreement constituted a secondary boycott
because rather than preserving work traditionally done by bar-
gaining unit employees, it seeks to acquire work not tradition-
ally done by those employees. Thus, the facts of the instant
case show that the hauling of dirt to Robertson’s was not done
by bargaining unit employees, but was done by independent
owner-operators and by nonunion employees of Hernandez
Trucking. The hauling of segments from Robertson’s to City
Creek Portal can look to the dirt haul and other surrounding
circumstances to establish the proposition that the agreement
between Shank and Respondent was work-acquisitive in nature.
5 I note the case of Sheet Metal Workers Local 27, 321 NLRB 540,
fn. 3 (1996), where the Board pointed out “that, as a matter of law,
solely unilateral conduct by a union, for example, a threat of picketing
or the mere filing of a grievance, to enforce an unlawful interpretation
of a facially lawful contract clause does not violate Sec. 8(e) because
such conduct does not constitute an ‘agreement.’ (Citations omitted.)
Unilateral conduct of this kind, however, may violate other provisions
of the Act.” In the present case, I find that there is a great deal more
present than solely unilateral conduct by a union.
TEAMSTERS LOCAL 166 (SHANK/BALFOUR BEATTY)
433
See Marrowbone Development Co. v. District 17, 147 F.3d
296, 300–304 (4th Cir. 1998); Retail Clerks Local 770 (Hughes
Markets), 218 NLRB 680, 682–683 (1975).
3.
The construction industry proviso is of no help to Respon-
dent. All agree that the City Creek Portal area where the seg-
ments are delivered is a construction jobsite. However, in Op-
erating Engineers Local 12 (Stief Co.), 314 NLRB 874, 877
(1994), the Board stated that:
[B]ased on the legislative history of the proviso to Section
8(e), the Board has found that the proviso does not apply to
various types of transportation work. See Joint Council of
Teamsters No. 42 (AGC of California), 248 NLRB 808
(1980), enfd. sub nom. Teamsters Joint Council No. 42 v.
NLRB (California Dump Truck Owners Assn.), 671 F.2d 305
(9th Cir. 1981), amended 702 F.2d 168 (9th Cir. 1981), cert.
denied 464 US 827 (1983).4 Thus, the Board has found that
the mixing, delivery, and pouring of ready-mix concrete,5 the
delivery of precast concrete pipe,6 the transportation of tools,
materials, and personnel to and from a construction site,7 the
delivery of sand fill,8 and the haulage of waste9 are not jobsite
work.
____________________
4 As the Board recognized in Teamsters No. 42 (AGC of California),
the legislative history of Sec. 8(e) reveals that a primary motivation for
the enactment of the proviso was the desire to “prevent potential labor
strife between union and nonunion personnel working at the same job-
site.” Id. at 815. Thus, these concerns are not implicated by the tem-
porary presence on the jobsite of delivery personnel. Id.
5 Teamsters Local 294 (Island Dock Lumber), 145 NLRB 484 (1963),
enfd. 342 F.2d 18 (2d Cir. 1965).
6 Joint Council of Teamsters No. 42 (Inland Concrete Enterprises),
225 NLRB 209 (1976).
7 Teamsters Local 282 (D. Fortunato, Inc.), 197 NLRB 673 (1972).
8 Teamsters Local 294 (Rexford Sand & Gravel), 195 NLRB 378
(1972).
9 Teamsters No. 42 (AGC of California), supra, 248 NLRB at 817.
Based on the above authorities, I find that the construction
industry proviso does not apply here because the transportation
of the segments from Robertson’s to City Creek Portal was not
jobsite work.6 See also General Truck Drivers Local 957 v.
NLRB, 934 F.2d 732, 736–738 (6th Cir. 1991), citing at page
738, Joint Council of Teamsters No. 42 v. NLRB, 702 F.2d 168
(9th Cir. 1981), cert. denied 464 US 827 (1983). In Joint
Council of Teamsters, a master labor agreement between unions
and employers in California construction industry prohibited
general contractors from hiring nonunion dump truck owner-
operators. The Board found the agreement to be an unfair labor
practice in violation of Section 8(e). The court in General
Truck Drivers agreed with the Joint Council decision that inde-
pendent truckers who spend 90 percent of their time driving are
not onsite workers.
The independent contractors who would have done the seg-
ment haul from Robertson’s would have spent the great major-
ity of their time driving between the two locations and just a
6 Jobsite work is work to be done at the site of construction such as
alteration, painting or repairs of a building, structure or other work.
District Council of Carpenters (Cardinal Industries), 136 NLRB 977
(1962), p. 988 of J.D.
few minutes at each location bringing down the 5th wheel of
the trailer and unlatching the tractor. This is not onsite work.
4.
I have considered Respondent’s authorities, Dairy Employ-
ees Local 454, 210 NLRB 483 (1974) and Local Freight Driv-
ers Local 208, 224 NLRB 1116 (1976), cited respectively at
pages 7 and 8 of the brief, and find them to be distinguishable
on their facts. Respondent’s argument at pages 10–12 of its
brief, that Shank is attempting to avoid the Union’s contractual
right to file grievances is without merit. Respondent does not
explain why a union or any other entity would have a right to
file a grievance to achieve an unlawful objective, i.e., the
awarding of offsite work to bargaining unit employees (secon-
dary objective), thereby defeating Shank’s right to award the
work to owner-operators as it had intended. In fact, filing a
grievance under certain circumstances may itself violate Sec-
tion 8(e) of the Act. See Carpenters Local 745 (SC Pacific),
312 NLRB 903 (1993); Elevator Constructors (Long Elevator),
289 NLRB 1095 (1988).7
5.
I end my analysis as I began it, by noting again that neither I
nor the Board is bound by the Order and Findings of the U.S.
District Judge in the 10(l) proceeding. Yet, the General Coun-
sel contends, brief, page 16, that “the Region has concluded
that the remedy herein should require Respondent, “to cease-
and-desist from its violation of Section 8(e) in the same manner
as that required by the District Court’s injunction.” The Gen-
eral Counsel correctly assumes in her brief that Respondent
would propose in its brief, narrower language for the Board to
adopt than that contained in the District Court’s injunction.
To be more specific, the U.S. District Judge’s cease-and-
desist order covers “the transportation of cement water tunnel-
support segments from the Robertson’s Ready Mix storage site
to any location on the Inland Pipeline Project.” Respondent
asks me and the Board to modify the Court’s cease-and-desist
order to read, “from Robertson’s Ready Mix storage site to City
Creek Portal.” In support of this proposed modification, Re-
spondent states, brief, page 13, “Any broader . . . remedy risks
encroaching upon the Union’s lawful right to claim work [and]
. . . would limit the Union’s right to pursue grievances over
work which it believes is on site.”
The General Counsel’s request is equivalent to a broad
cease-and-desist order in other types of cases. In general, enti-
tlement to a broad order must be based on a Respondent’s pro-
clivity to violate the Act, established either by the facts within a
particular case, or by prior Board decisions against the Respon-
dent at bar based upon similar unlawful conduct in the past.
Sheet Metal Workers Local 27 (CAMCON), 292 NLRB 1046
(1989) (Judge’s broad cease-and-desist order reversed on
grounds that animosity between Respondent and another union
local, and Respondent’s intent to prevent members of the other
local from working in its jurisdiction not adequate to support
broad order).
In the instant case, as in Sheet Metal Workers Local 27, the
General Counsel does not cite any prior Board decisions against
Respondent based on similar conduct. To establish proclivity
for unlawful conduct in the present case, the General Counsel
7 The General Counsel does not allege that Respondent’s threats to
file a grievance, if Shank allowed owner-operators to perform the seg-
ment haul, were unlawful, and I express no opinion on the matter.
DECISIONS OF THE NATIONAL LABOR RELATIONS BOARD
434
states, brief, page 18, that narrower language than that con-
tained in the District Court’s injunction [would be] “inadequate
because it would not remedy clearly similar, future potential
violations of 8(e) by Respondent at the Inland Feeder Pipeline
Project . . . other than those violations that specifically involve
the City Creek Portal and Strawberry Creek Portal locations.”
I reject the General Counsel’s request because there is no
showing of any proclivity to violate the Act. Compare Team-
sters Local 294 (Island Dock Lumber ), 145 NLRB 484, 493
(1963). In fact, Respondent’s failure to claim the dirt haul to
Robertson’s was an inconsistent position I used against Re-
spondent in part to find the violation. But with respect to the
Remedy, said position helps Respondent to refute any claim of
proclivity to violate the Act. Moreover, the General Counsel’s
argument asks me to rely on speculation and surmise about
what Respondent might do in the future, to impose a broad
order. The effect of such argument, if adopted, would be to
nullify the difference between a narrow and broad order. That
is, the General Counsel’s argument could be made in every case
to support a request for a broad cease-and-desist order. Finally,
it is most unlikely that future violations would occur on this
project because, assuming this decision survives appeal, Shank,
the general contractor, is likely to resist any agreement with
Respondent to cease doing business with any third party, in-
cluding owner-operators of vehicles. That is, Shank’s chances
of prevailing in any grievance over worksite issues is mani-
festly improved as a result of this decision.8
D. The Effect of the Unfair Labor Practices on Commerce
The activities of Respondent set forth in sections A–C,
above, occurring in connection with the operations of the Em-
ployer, described in section A, above, have a close, intimate,
and substantial relationship to trade, traffic, and commerce
among the several States and tend to lead to labor disputes bur-
dening and obstructing commerce and the free flow of com-
merce.
CONCLUSIONS OF LAW
1. Shank/Balfour Beatty is a partnership between two Cali-
fornia corporations, and at all times material has been an em-
ployer engaged in commerce and in business affecting com-
merce within the meaning of Section 2(2), (6), and (7) of the
Act.
2. Teamsters Local Union No. 166, International Brother-
hood of Teamsters, Chauffeurs, Warehousemen and Helpers of
America, is, and at all times material has been, a labor organi-
zation within the meaning of Section 2(5) of the Act.
3. By entering into, maintaining, reaffirming, giving effect
to, invoking, or enforcing the terms of the Inland Feeder Project
Labor Agreement or any other agreement in which Shank/Bal-
four Beatty agrees, or has agreed, to cease or refrain from doing
business with any other person, including the owner-operators
of any vehicle, with respect to the transportation of cement
water tunnel-support segments from the Robertson’s Ready
Mix storage site to the City Creek Portal location and surround-
ing areas on the Inland Feeder Pipeline Project, Respondent has
violated Section 8(e) of the Act.
4. The aforesaid unfair labor practice is an unfair labor prac-
tice affecting commerce within the meaning of Section 2(6) and
(7) of the Act.
8 Again, I express no opinion on whether the future filing of a griev-
ance by Respondent to enforce worksite issues would violate the Act.
THE REMEDY
Having found that Respondent has engaged in unfair labor
practices within the meaning of Section 8(e) of the Act, it will
be recommended that it cease and desist therefrom, and take
certain affirmative action designed to effectuate the policies of
the Act. It will also be recommended that Respondent rescind
and render null and void and of no effect the agreement of on or
about February 10, 1998, by which Shank/Balfour Beatty
agrees, or has agreed to cease and desist or refrain from doing
business with any other person, including the owner-operator of
any vehicle, with respect to the transportation of cement water
tunnel support segments from the Robertson’s Ready Mix stor-
age site to the City Creek Portal location on the Inland Feeder
Pipeline Project.
On the basis of the foregoing findings of fact and conclu-
sions of law, and on the entire record, and pursuant to Section
10(c) of the Act, I make the following recommended9
ORDER
The Respondent, Teamsters Local Union No. 166, Interna-
tional Brotherhood of Teamsters, Chauffeurs, Warehousemen
and Helpers of America, their respective officers, agents, and
representatives, shall
1. Cease and desist from
(a) Entering into, maintaining, reaffirming, giving effect to,
invoking, or enforcing the terms of the Inland Feeder Project
Labor Agreement or any other agreement in which Shank/Bal-
four Beatty agrees, or has agreed, to cease or refrain from doing
business with any other person, including the owner-operators
of any vehicle, with respect to the transportation of cement
water tunnel-support segments from the Robertson’s Ready
Mix storage site to the City Creek Portal location and surround-
ing areas on the Inland Feeder Pipeline Project.
2. Take the following affirmative action which it is found
will effectuate the policies of the Act.
(a) Rescind and render null and void and of no effect any
agreement in which Shank/Balfour Beatty agrees or has agreed,
to cease or refrain from doing business with any other person,
including the owner-operators of any vehicle, with respect to
the transportation of cement water tunnel-support segments
from the Robertson’s Ready Mix storage site to the City Creek
Portal location and surrounding areas on the Inland Feeder
Pipeline Project.
(b) Within 14 days after service by the Region, post at its un-
ion office and other places where it customarily posts notices to
members in California, copies of the attached notice marked
“Appendix.”10 Copies of the notice, on forms provided by the
Regional Director for Region 31, after being signed by the Re-
spondent’s authorized representative, shall be posted by the
Respondent and maintained for 60 consecutive days in con-
spicuous places including all places where notices to members
are customarily posted. Reasonable steps shall be taken by the
9 If no exceptions are filed as provided by Sec. 102.46 of the Board’s
Rules and Regulations, the findings, conclusions, and recommended
Order shall, as provided in Sec. 102.48 of the Rules, be adopted by the
Board and all objections to them shall be deemed waived for all pur-
poses.
10 If this Order is enforced by a Judgment of a United States Court of
Appeals, the words in the notice reading “Posted by Order of the Na-
tional Labor Relations Board” shall read “Posted Pursuant to a Judg-
ment of the United States Court of Appeals Enforcing an Order of the
National Labor Relations Board.”
TEAMSTERS LOCAL 166 (SHANK/BALFOUR BEATTY)
435
Respondent to ensure that the notices are not altered, defaced,
or covered by any other material. In the event that, during the
pendency of these proceedings, the Respondent has gone out of
business or closed the facility involved in these proceedings,
the Respondent shall duplicate and mail, at its own expense, a
copy of the notice to all current employees and former employ-
ees employed by the Respondent at any time since November
25, 1997.
(c) Within 21 days after service by the Region, file with the
Regional Director a sworn certification of a responsible official
on a form provided by the Region attesting to the steps that the
Respondent has taken to comply.
APPENDIX
NOTICE TO MEMBERS
POSTED BY ORDER OF THE
NATIONAL LABOR RELATIONS BOARD
An Agency of the United States Government
The National Labor Relations Board has found that we violated the
National Labor Relations Act and has ordered us to post and abide
by this notice.
WE WILL not enter into, maintain, reaffirm, give effect to,
invoke, or enforce the terms of the Inland Feeder Project labor
Agreement, or any other agreement in which Shank/Balfour
Beatty agrees or has agreed, to cease or refrain from doing
business with any other persons, including the owner-operators
of any vehicle, with respect to the transportation of cement
water tunnel-support segments from the Robertson’s Ready
Mix storage site to the City Creek Portal location and surround-
ing areas on the Inland Feeder Pipeline Project.
WE WILL rescind and render null and void and of no effect
any agreement by which Shank/Balfour Beatty agrees or has
agreed, to cease or refrain from doing business with any other
persons, includidng the owner-operastors of any vehicle, with
respect to the transportation of cement water tunnel-suport
segments from the Robertson’s Ready Mix storage site to the
City Creek Portal location and surrounding areas on the Inland
Feeder Pipeline Project.
TEAMSTERS
LOCAL
UNION
NO.
166,
INTERNATIONAL
BROTHERHOOD
OF
TEAMSTERS,
CHAUFFEURS,
WARE-
HOUSEMEN AND HELPERS OF AMERICA