342 NLRB 954
Operating Engineers Local 150 (Nickelson Industrial)
DECISIONS OF THE NATIONAL LABOR RELATIONS BOARD
342 NLRB No. 95
954
International Union of Operating Engineers, Local
150, AFL–CIO and Nickelson Industrial Service,
Inc. and Laborers’ International Union of North
America, Local 4, AFL–CIO. Case 13–CD–709–1
August 31, 2004
DECISION AND DETERMINATION OF DISPUTE
BY MEMBERS LIEBMAN, SCHAUMBER, AND MEISBURG
This is a jurisdictional dispute proceeding under Sec-
tion 10(k) of the National Labor Relations Act. The
charge in this proceeding was filed February 10, 2004,1
by Nickelson Industrial Service, Inc. (the Employer),
alleging that the Respondent, International Union of Op-
erating Engineers, Local 150, AFL–CIO (the Operating
Engineers or Local 150), violated Section 8(b)(4)(D) of
the Act by engaging in proscribed activity with an object
of forcing the Employer to assign certain work to em-
ployees it represents rather than to employees repre-
sented by Laborers’ International Union of North Amer-
ica, Local 4, AFL–CIO (the Laborers or Local 4). The
hearing was held on March 1, before Hearing Officer
Denise Jackson-Riley.
The National Labor Relations Board has delegated its
authority in this proceeding to a three-member panel.
The Board affirms the hearing officer’s rulings, find-
ing them free from prejudicial error. On the entire re-
cord, the Board makes the following findings.
I. JURISDICTION
The parties stipulated that the Employer is an Illinois
corporation that provides services in excess of $50,000 to
companies outside the State of Illinois. The parties stipu-
late, and we find, that the Employer is an employer en-
gaged in commerce within the meaning of Section 2(6)
and (7) of the Act and that the Operating Engineers and
the Laborers are labor organizations within the meaning
of Section 2(5) of the Act.
II. THE DISPUTE
A. Background and Facts of Dispute
The Employer is engaged in the business of disman-
tling industrial machinery. In January 2004, the Em-
ployer was hired by Era Valdivia Contractors, Inc.
(EVC), the general contractor responsible for work at the
Field Museum annex project in Chicago, to perform inte-
rior demolition work at the site. Specifically, EVC hired
the Employer to dismantle and remove beams and pipe
that had been installed as a temporary measure to support
the new annex building while concrete was poured into
the structure. In order to remove the beams and pipe, the
1 All dates are in 2004, unless otherwise indicated.
Employer had to cut them into small pieces and then
move the pieces by forklift to an area where they could
be lifted out of the structure by a crane. The Employer
had a collective-bargaining agreement with the Laborers
and had always used Laborers-represented employees to
perform its forklift work.
Before the Employer could begin work on the project,
its forklifts needed to be lowered into the structure by
crane. The Employer hired Imperial Crane to move the
forklifts. On February 2, Imperial Crane lowered the
forklifts into the structure and, once the forklifts were in
place, employees represented by Local 4 began perform-
ing the forklift work.
That same day, Local 150 business agents Dabney
McCain and Kevin Burke went to the jobsite after learn-
ing that forklifts were being put in place. At the work
site, McCain and Burke spoke with Tony Kavouris, sen-
ior project manager for EVC, and a foreman2 for the Em-
ployer. McCain stated that the forklift work belonged to
Local 150. Kavouris told McCain to get in touch with
the Laborers’ business agent and resolve the issue.
McCain called Local 4 business agent William Hosty
and informed him that he would be sending three operat-
ing engineers from Local 150 to operate the forklifts at
the Field Museum site. Hosty told him that he did not
think that was a good idea and that he would send two
Local 4 representatives out to discuss the matter with
him. Shortly thereafter, Local 4 representatives James
Leatherman and John Lally arrived at the site. The as-
sembled union representatives discussed the matter but
did not reach agreement.
In order to prevent any work disruption, the Employer
arranged to have Industrial Crane provide three of its
employees represented by Local 150 to operate the fork-
lifts. Employees represented by Local 150 began per-
forming the forklift work on February 3.
On or about February 10, Local 4 Business Agent
Hosty called the Employer’s president, Jeffrey Lev, to
tell him that the forklift work belonged to the Laborers
and that he needed to put employees represented by the
Laborers on the work immediately. On February 10,
four Local 4 laborers were dispatched to the worksite to
replace the Local 150 operating engineers who had been
operating the forklifts.
That same day, Local 150 Agent McCain called Lev
and stated that the forklift work belonged to the Operat-
ing Engineers. Lev suggested that McCain call Local 4
agent Hosty and that the two parties should settle the
matter. Local 150 agent Dan Regan also called Lev stat-
2 There is conflicting testimony regarding the name of this em-
ployee, but ultimately his true identity is not relevant to the determina-
tion of the issues presented.
OPERATING ENGINEERS LOCAL 150, AFL-CIO (NICHELSON INDUSTRIAL SERVICE)
955
ing that the forklift work belonged to Local 150. As he
had with McCain, Lev told Regan to call Hosty to
“straighten it out,” and stated that the Employer would
abide by the unions’ decision. Lev further testified that
Regan “got a little upset with me and told me to use la-
borers for everything” because “he was going to pull his
people off.”3
The next day, February 11, the Operating Engineers
picketed the Field Museum site and shut down work for
2 days.4 On February 12, EVC reclaimed the forklift
work from the Employer and, thereafter, employees rep-
resented by Local 150 performed the forklift work. EVC
has indicated that it will return the work to the Employer
if the Board awards the disputed work to the Laborers.
B. Work in Dispute
The work in dispute is the operation of forklift trucks
for the purpose of interior demolition work, involving the
dismantling and removal of support beams and pipe in-
side a building being constructed at the site of the Field
Museum in Chicago, Illinois.5
C. Contentions of the Parties
The Employer contends that there is reasonable cause
to believe that the Operating Engineers violated Section
8(b)(4)(D) by picketing the Field Museum site with the
object of forcing the Employer to reassign the disputed
work to employees represented by them. The Employer
also contends that there is no voluntary method for re-
solving the dispute. Finally, the Employer asserts that
the disputed work should be assigned to employees rep-
resented by Local 4 because the 10(k) factors weigh in
favor of that assignment, including that the Employer is
contractually bound to assign the work to Local 4.
The Laborers contend that there is reasonable cause to
believe that Section 8(b)(4)(D) has been violated and that
the parties do not have an agreed-upon method for re-
solving their dispute. Like the Employer, the Laborers
assert that the 10(k) factors favor awarding the work to
employees represented by Local 4.
The Operating Engineers contend that the Board
should quash the notice of hearing because the Employer
no longer controls the work in question, there is no rea-
sonable cause to believe Section 8(b)(4)(D) has been
violated, and the parties have an agreed-upon method to
voluntarily adjust the dispute. In addition, the Operating
3 Regan testified that he “never called Jeff Lev and threatened
[him].”
4 The record does not reveal the language used on the picket signs,
other than that Nickelson was named.
5 The Operating Engineers believe that the work in dispute should be
characterized as “renovation” or “restoration” work instead of “demoli-
tion” work. This assertion is not supported by the record.
Engineers contend that, should the Board undertake a
Section 10(k) analysis, the relevant factors indicate that
the work should be awarded to employees represented by
Local 150.
D. Applicability of the Statute
Before the Board may proceed with a determination of
dispute pursuant to Section 10(k) of the Act, it must be
established that there are competing claims for the work,
that reasonable cause exists to believe that Section
8(b)(4)(D) has been violated, and that the parties have no
agreed-upon method for voluntary adjustment of the dis-
pute.
To begin, Local 150 contends that because Local 150
and the Laborers are required to submit jurisdictional
disputes to the Cook County Building Trades Joint
Grievance Board, and because the Employer has a collec-
tive-bargaining agreement with Local 4, the parties are
required to present any jurisdictional disputes to that tri-
bunal. As we have recognized, however, in order for an
agreement to constitute an agreed-upon method for vol-
untary adjustment, all parties to the dispute must be
bound to that agreement. See Laborers International
Union (E & B Paving), 340 NLRB No. 150 (2003).
Therefore, because the Employer is not a party to the
Cook County Building Trades agreement, and its collec-
tive-bargaining agreement with the Laborers does not
incorporate that agreement, we find that the Employer is
not bound by the agreement and, therefore, that the
agreement does not constitute an agreed-upon method for
voluntary adjustment within the meaning of Section
10(k).
We also find that there are competing claims for the
work in dispute. Local 4 has at all times claimed the
work for the employees it represents, and these employ-
ees have been performing the work. Also, Local 150
representative Regan warned the Employer that it would
pull all operating engineers off the site if the Employer
did not agree to use employees represented by Local 150.
This evidence establishes its rival claim for the work.
In addition, we find that reasonable cause exists to find
that a violation of Section 8(b)(4)(D) has occurred. Even
assuming, as Operating Engineers argues, that an object
of the picketing was to protest the Employer’s wage
rates, the evidence reasonably establishes that at least
another object of the picketing was to force the Employer
to assign the disputed work to employees represented by
Local 150. In making this finding, we rely upon state-
ments made by Local 150 representative Regan warning
the Employer that he would pull all the Operating Engi-
neers off the Field Museum site if the Employer did not
agree to use employees represented by Local 150 to per-
DECISIONS OF THE NATIONAL LABOR RELATIONS BOARD
956
form the disputed work.6 Because “[o]ne proscribed
object is sufficient to bring a union’s conduct within the
ambit of Section 8(b)(4)(D),” we find that the dispute is
properly before the Board for determination under Sec-
tion 10(k) of the Act. Longshoremen ILA Local 3033
(“Coastal Cargo Co.”), 323 NLRB 570, 572 (1997)
(quoting Cement Masons Local 577 (Rocky Mountain
Prestress), 233 NLRB 923, 924 (1977)).
Local 150’s remaining contention, that a 10(k) deter-
mination is not warranted because the Employer no
longer controls the ability to assign the disputed work, is
without merit. We have repeatedly held that 10(k) de-
terminations are proper where the original employer has
lost the work in question as a result of the jurisdictional
dispute. See, e.g., Electrical Workers Local 98 (Total
Cabling Specialists), 337 NLRB 1275 (2002); Dock
Builders, Local 1456 (Vibroflotation), 199 NLRB 453
(1972).
E. Merits of the Dispute
Section 10(k) requires the Board to make an affirma-
tive award of disputed work after considering various
factors. NLRB v. Radio & Television Broadcast Engi-
neers, IBEW Local 1212 (Columbia Broadcasting), 364
U.S. 573 (1961). The Board has held that its determina-
tion in a jurisdictional dispute is an act of judgment
based on common sense and experience, reached by bal-
ancing the factors involved in a particular case. Machin-
ists Lodge 1743 (J.A. Jones Construction), 135 NLRB
1402 (1962).
The following factors are relevant in making the de-
termination of this dispute.
1. Certifications and collective-bargaining agreements
None of the labor organizations involved herein has
been certified by the Board nor is there evidence indicat-
ing that a Board certification covered the disputed work.
The Employer is party to a collective-bargaining
agreement with the Laborers that covers all “interior
wrecking” work such as the work in dispute here. It has
no collective-bargaining agreement with the Operating
Engineers. This factor favors an award of the disputed
work to employees represented by Local 4.
2. Employer preference and past practice
The Employer’s preference, as clearly indicated by the
testimony of Employer President Lev, is that the work in
dispute be performed by employees represented by Local
6 Although, in his testimony, Regan denied making the threat, “it is
well settled that a conflict in testimony does not prevent the Board from
proceeding under Section 10(k),” because we need only find that “rea-
sonable cause” exists for finding an 8(b)(4)(D) violation. Bricklayers
Local 15 (Fusco Corp.), 278 NLRB 967, 968 (1986).
4. In the past, the Employer has assigned all forklift
work for interior demolition purposes to Laborers-
represented employees. This factor favors awarding the
disputed work to employees represented by Local 4.
3. Area and industry practice
The weight of the evidence indicates that the industry
practice in the Chicago area is to use Laborers to perform
the disputed work. The evidence establishes that all em-
ployer-members of the Chicago Demolition Contractors
Association use employees represented by the Laborers
to operate forklifts in interior demolition work. This
factor favors awarding the work to employees repre-
sented by Local 4.
4. Relative skills and experience
Employees represented by Local 4 and Local 150 all
receive extensive training in forklift operation and both
Locals required their forklift operators to have the appro-
priate certifications. This factor does not favor awarding
the work in dispute to either group of employees.
5. Economy and efficiency of operations
The Employer’s president testified that, in his experi-
ence, employees represented by the Laborers can per-
form the disputed work more efficiently because they
perform a wide range of tasks associated with interior
demolition work, including torch cutting and saw cutting,
as compared with the Operating Engineers, who only
operate the forklifts. Therefore, this factor favors award-
ing the disputed work to employees represented by Local
4.
6. The interunion agreement
The Operating Engineers contend that a 1991 memo-
randum of understanding between Local 150 and the
Laborers District Council (the Interunion Agreement)
favors assignment of the disputed work to employees
represented by Local 150. The Interunion Agreement,
however, does not cover the work at issue. On its face,
the Interunion Agreement covers only “the use of brick
forklifts by mason contractors and small skid steer load-
ers . . . by cement and concrete contractors.” Because the
work in dispute does not fall within either of these cate-
gories of work, the Interunion Agreement is not relevant
to the instant 10(k) determination.
In any event, even if we were to adopt Local 150’s in-
terpretation of the Interunion Agreement as covering the
work at issue, we would not give this factor significant
weight in determining the assignment of the work at is-
sue, because the Employer is not a party to the Interunion
Agreement. See Local Union No. 379, Ironworkers
(Owren Kirklin & Sons), 261 NLRB 843, 845 (1982);
OPERATING ENGINEERS LOCAL 150, AFL-CIO (NICHELSON INDUSTRIAL SERVICE)
957
District Council of Painters No. 8 (Quad C Corp.), 259
NLRB 905, 907 (1982).
CONCLUSION
After considering all the relevant factors, we conclude
that employees represented by Local 4 are entitled to
perform the work in dispute. We reach this conclusion
relying on the collective-bargaining agreement between
the Employer and the Laborers, employer preference and
past practice, area and industry practice, and economy
and efficiency of operations.
In making this determination, we are awarding the
work to employees represented by the Laborers’ Interna-
tional Union of North America, Local 4, AFL–CIO, not
to that union or its members. The determination is lim-
ited to the controversy that gave rise to this proceeding.
DETERMINATION OF DISPUTE
The National Labor Relations Board makes the follow-
ing determination of dispute.
1. Employees of Nickelson Industrial Service, Inc.,
represented by Laborers’ International Union of North
America, Local 4, AFL–CIO are entitled to operate fork-
lift trucks for the purpose of interior demolition work
involving the dismantling and removal of support beams
and pipe inside a building being constructed at the site of
the Field Museum in Chicago, Illinois.
2. International Union of Operating Engineers, Local
150, AFL–CIO is not entitled by means proscribed by
Section 8(b)(4)(D) of the Act to force Nickelson Indus-
trial Service, Inc. to assign the disputed work to employ-
ees represented by it.
3. Within 14 days from this date, International Union
of Operating Engineers, Local 150, AFL–CIO shall no-
tify the Regional Director for Region 13 in writing
whether it will refrain from forcing the Employer, by
means proscribed by Section 8(b)(4)(D), to assign the
disputed work in a manner inconsistent with this deter-
mination.