296 NLRB 501
Ruff Electrical Construction Co., Inc.
RUFF ELECTRICAL CONSTRUCTION
Ruff Electrical
Construction
Company, Inc.
and
International Brotherhood of Electrical Work-
ers,
Local
No.
5, AFL-CIO. Cases 6-CA-
20532 and 6-CA-20573
September 12, 1989
DECISION AND ORDER
BY CHAIRMAN STEPHENS AND MEMBERS
CRACRAFT AND DEVANEY
On March 2, 1989, Administrative Law Judge
Stephen J. Gross issued the attached decision. The
General Counsel filed exceptions and a supporting
brief.
The National Labor Relations Board has delegat-
ed its authority in this proceeding to a three-
member panel.
The Board has considered the decision and the
record in light of the exceptions and brief and has
decided to affirm the judge's rulings, findings,' and
conclusions as modified, and to adopt the recom-
mended Order.
The judge found that the preponderance of the
evidence did not establish that union activity was a
motivating factor in the layoffs of Daniel Anglum
and Charles Moss or in the discharge of Anthony
Kainz. The judge therefore concluded that the Re-
spondent did not violate Section 8(a)(3) and (1) of
the Act regarding Anglum and Moss, and did not
violate
Section 8(a)(4), (3), and (1) regarding
Kainz. In agreeing with the judge's conclusion that
the Respondent did not violate the Act, we find
that even assuming that the General Counsel estab-
lished a prima facie case, the Respondent has met
its burden of demonstrating that it would have laid
off or discharged these employees even if they had
not engaged in protected activity. Wright Line, 251
NLRB 1083 (1980), enfd. 662 F.2d 899 (1st Cir.
1981), cert. denied 455 U.S. 989 (1982); NLRB v.
Transportation
Management Corp.,
462 U.S. 393
(1983). In evaluating the Respondent's business de-
fense, we rely on facts established by the uncontro-
verted testimony at the hearing as well as those
discussed by the judge. In this regard, we find that
the evidence supports the assertion of Thomas
Ruff, the Respondent's owner, that he laid off
Anglum and Moss and discharged Kainz because
of concerns about their productivity at Clairton.
The Clairton project, which involved the com-
plete rewiring of the school's electrical system, was
' The General Counsel has excepted to some of the judge's credibility
findings The Board's established policy is not to overrule an administra-
tive law judge's credibility resolutions unless the clear preponderance of
all the relevant evidence convinces us that they are incorrect
Standard
Dry Wall Products, 91 NLRB 544 (1950), enfd. 188 F2d 362 (3d Cir
1951). We have carefully examined the record and find no basis for re-
versing the findings.
501
the largest contract ever awarded to the Respond-
ent. The Respondent's electrical work at Clairton
proceeded on schedule until approximately May
1987,2 at which time Ruff decided that Richard
Schwartz should replace Ronald Kuhn as the
project's foreman. Ruff spent little time at Clairton
in June and July, and testified that he first realized
in August that there were "serious" problems when
he started receiving complaints from the project's
architect, Victor Graves, and the other contractors
to the effect that the Respondent was not keeping
up with the other contractors and was holding
them back. On August 7, Ruff reinstated Kuhn as
the project foreman and told him that if Kuhn
could not turn the project around in 2 weeks, the
employees on the project would be replaced by
more productive labor.
Thereafter, following his return from vacation,
Ruff began to spend more time at Clairton, includ-
ing attending job meetings at which the contractors
discussed the status of the project. According to
Ronald Smith, project superintendent for Uhl Con-
struction, the general contractor, one of the sub-
jects discussed at the weekly meetings was the
delay caused by the Respondent. On August 22,
Ruff estimated, based on the number of man hours
already worked at Clairton and the percentage of
the electrical work already completed, that com-
pletion of the electrical work on the project would
require about 2100 more hours than originally
planned. Ruff described this 20-percent increase
over the projected hours on which he had based
his bid for the project as a "big problem."
It was in this context that Ruff, on August 23
and 30, laid off Moss and Anglum. Ruff testified
that, based on his observations, they were the least
experienced and least productive employees on the
job. Specifically, Ruff was concerned that the dem-
olition work they were performing would not be
completed by the end of the month. Ruffs asser-
tions that he had seen Anglum standing around
talking and that he saw Anglum and Moss carrying
small amounts of material to the dumpster, rather
than collecting it in a cart and taking a full load,
constitute objective evidence in support of his con-
cerns about their productivity. Ruff further testi-
fied that Anglum was aware that Ruff was watch-
ing him walk to the dumpster and that Anglum
then began to whistle, which Ruff interpreted as a
gesture of contempt. Significantly, Ruff's conten-
tion that these employees displayed a poor attitude
was supported by the judge's findings regarding
prevailing wage matters, and by the testimony of
Smith, who stated that beginning in the spring of
2 All dates are in 1987 unless otherwise indicated
296 NLRB No. 71
502
DECISIONS OF THE NATIONAL LABOR RELATIONS BOARD
1987 he noticed a change in the employees' atti-
tudes toward Ruff.3
Graves testified that in September he discussed
the contractors' concerns with Ruff and that Ruff,
disagreeing
with
Graves'
assessment that
more
electrical workers were needed at Clairton , charac-
terized the problem as a need to increase produc-
tivity per worker.4 According to Ruff, on Septem-
ber 11 he recalled Anglum and Moss to perform
some minor outside jobs so that none of the other
employees would have to be taken off the Clairton
project. 5
Faced
with pressure to complete the
school's gymnasium, Ruff then sent Anglum and
Moss to hang the preassembled lights. Ruff stated
that although the assignment should have been
completed in 1 day, Anglum and Moss required
more time and displayed a bad attitude . Under the
circumstances, including mounting pressure from
the other contractors and Ruff's increased familiari-
ty with the details of the project, we find that
Anglum's and Moss' performance of the lighting
assignment reinforced Ruff's belief that they were
not productive. Moreover, the fact that at least
some of the employees hired in September to finish
the electrical work had particular areas of expertise
that were known to the Respondent is further ob-
jective evidence in support of Ruff's asserted con-
cern with worker productivity. Testifying that he
hired Thurman Ingram and his crew to install the
numerous light fixtures in the school , Ruff stated,
"these guys really hustle . They go in and get a job
done and they're out." Describing the problems
presented by unclear specifications for the fire
alarm system, Ruff testified that he hired a former
employee, Gene Saus, who had the knowledge to
design and build the system as he went along. Ac-
cording to Ruff, these employees required little su-
pervision and were able to complete the work.
Following the layoffs of Anglum and Moss, and
despite the hiring of new employees, the evidence
indicates that Ruff's problems at Clairton intensi-
fied. Thus, on October 30, Smith wrote to Graves
concerning the scheduling and production prob-
lems caused by working in underlighted and un-
lighted areas and the Respondent's failure to per-
form "patchwork" where plaster needed to be re-
paired. Smith went on to question the Respondent's
productivity.
By response dated November 10,
Graves
instructed Uhl Construction to do the
a The fact that the employees' productivity may have been influenced
by the prevailing wage discussions instituted by the Union does not estab-
lish that Anglum and Moss were laid off for discriminatory reasons
4 Smith and Graves both testified that in their discussions with Ruff
about the delays, Ruff never mentioned either the Union or his employ-
eeti union activities
s In this regard , we find it unnecessary to pass on the judge's specula-
tion that Ruff recalled Anglum and Moss, rather than hire two new em-
ployees, in order to reduce the Respondent 's backpay exposure
patching work, for which the Respondent would
be charged. The following day, Graves wrote to
Ruff discussing the complaints that had been re-
ceived "for the past five or six months . . . about
delays being caused by your company ."s Graves
stated, "It is evident that you will continue to fall
further and further behind if something is not
done." Noting that the carpeting was scheduled to
be installed on December . 1, Graves warned that
noncompletion of the electrical work could result
in additional cost to the Respondent from possible
damage to the carpeting. The letter concluded,
"you are hereby notified that should any expense,
cost or liquidated damages result due to your de-
laying the project, the School District will look to
you for compensation."
Ruff testified that from the beginning of Novem-
ber, he was at Clairton at least 8 hours a day for 6
or 7 days a week for 2 months. He stated, "I was
totally
consumed with completing that project
. , , . My future was on the line . . . . I just lived
that job . . . . I had to get it finished."7
During this time of intense personal pressure be-
cause of problems on the project , Ruff, on Decem-
ber 9, discharged Kainz, whom he was supervising,
for
unsatisfactory
work,
inability
to
complete
projects on time, and a poor attitude . In early De-
cember Kainz had not completed a minor job in-
volving an emergency electrical line; there is no
evidence that Ruff was aware that Kainz had been
told that Ruff wanted him to help another employ-
ee on another assignment. Additionally, on Decem-
ber 6, Kainz had broken a piece of plaster while
drilling. In view of the fact that the Respondent's
delay in patching plaster had been a subject of
complaints from the other contractors and that
Ruff had given Kainz specific instructions on how
to drill through plaster, we agree with the judge's
finding that Ruff's reaction to the incident in ex-
ploding in anger was more the product of pressures
on him than the incident itself. We also agree that
Ruff was further provoked by Kainz who, when
confronted, stated, "Do what you have to do,"
walked away, and refused to return when Ruff
called to him. Accordingly, we conclude, as did
6 The problems included failure to perform plaster patching which de-
layed the completion of painting, tiling, and carpeting, inadequate instal-
lation of temporary light which resulted in workers using flashlights; lack
of controls and thermostats which delayed the provision of temporary
heat, lack of switches at control panels which delayed completion of the
building's heat and exhaust systems; lack of a master switch for tempo-
rary light and power which resulted in nonelectricians losing time by
having to turn individual systems on and off; and lack of permanent
wiring to light fixtures which delayed the placement of ceiling tile
7 Pursuant to the Respondent's indemnification agreement with its in-
surer, any charges incurred due to the failure to complete a project could
be recovered from the Respondent Company as well as from Ruff indi-
vidually
RUFF ELECTRICAL CONSTRUCTION
the judge, that Ruff discharged Kainz based on his
perceptions of low productivity and for reasons un-
related to Kainz' protected activity.8
For the above reasons, we find that the Re-
spondent has demonstrated that it would have laid
off Anglum and Moss and discharged Kainz, even
absent their protected activity, based on Ruff's as-
sessment that the Company had a compelling need
to replace unproductive employees at Clairton. We
therefore conclude that the Respondent did not
violate the Act as alleged.
ORDER
The recommended Order of the administrative
law judge is adopted and the complaint is dis-
missed.
a In finding that Kainz was not unlawfully discharged , we also note
that during the time that Kamz engaged in protected activity, i e , from
the time he signed an authorization card through his testimony at the
hearing on the challenged ballot , he was in fact considered by other em-
ployees to be a favorite employee of Ruff
Janice Ann Sauchin and Donald K Burns, Esqs., for the
General Counsel.
Mr. Thomas H. Ruff, of Glenshaw, Pennsylvania, for the
Respondent.
Stanford A. Segal, Esq. (Gatz, Cohen, Segal & Koerner), of
Pittsburgh, Pennsylvania, for the Charging Party.
DECISION
STATEMENT OF THE CASE
STEPHEN J. GROSS, Administrative Law Judge. The
General Counsel claims that the Respondent, Ruff Elec-
trical
Construction Company (the Company or Ruff
Electric), violated the National Labor Relations Act (the
Act) by laying off employees Dan Anglum and Charles
Moss and by firing and issuing "a poor performance
evaluation" of employee Anthony Kainz. Ruff Electric
acted against those employees, according to the General
Counsel, because they joined and supported the Interna-
tional Brotherhood of Electrical Workers, Local No. 5,
AFL-CIO (the Union or Local 5). The General Counsel
further alleges that Ruff Electric's action against Kainz
also stemmed from Kainz' testimony on the Union's
behalf at a Board hearing.'
Local 5's Organizing Efforts
As of June 1986 the Company had only two employ-
ees, brothers Ron and Russ Kuhn, both of whom had
' Local 5 filed its charge in Case 6-CA-20532 (regarding Moss and
Anglum) on December 2, 1987 The charge in Case 6-CA-20573 (regard-
ing Kamz) was filed on December 18, 1987 A consolidated complaint
issued on February 9, 1988, and was amended on February 24, 1988. Ruff
Electric admits that it is an employer engaged in commerce and admits
that Local 5 is a labor organization within the meaning of the Act But
Ruff Electric denies violating the Act in any respect
The hearing was
held in Pittsburgh on June 27 through June 29, 1988. The General Coun-
sel has filed a brief Ruff Electric. which is not represented in this pro-
ceeding by counsel , has not
503
been with Ruff Electric for many years. But earlier in
the year Ruff Electric won the contract for all the elec-
trical work involved in the refurbishment of a large
school building in Clairton, Pennsylvania. The contract
was for about $800,000. Ruff Electric had never before
undertaken anything even nearly as large. In order to
handle the Clairton work, along with the various other
projects that the Company had underway, starting that
June Ruff Electric began hiring additional employees.
Anglum was the first, then Moss (in July 1986), then
Richard Schwartz and Larry Ward. Respondent hired
Kainz and three other employees in June 1987.
Early in June 1987 Local 5 began its organizing efforts
among Ruff Electric's employees. (All the events I refer
to in this decision occurred in 1987 unless I specify oth-
erwise.) By June 4, Anglum, Kainz, Moss, Schwartz, and
Ward had signed authorization cards. On June 8 the
Union filed an election petition.
Respondent is wholly owned and run by Thomas Ruff.
(I will hereafter use the name "Ruff" to refer to Thomas
Ruff, but not to the Company.) The day the Union filed
the election petition, a representative of the Board's Re-
gional Office in Pittsburgh called Ruff Electric to advise
the Company of the petition. As Ruff testified, "it was an
emotional moment." Ever since Ruff was a child he had
thought of Local 5 as a threatening, malevolent, force.
(That stemmed from, among other things, Ruffs recol-
lections of interactions between Local 5 and his father's
company, which also was an electrical construction con-
tracting company.) Moreover Ruff saw the election peti-
tion as endangering his future and that of his family's.
The Clairton project was a gamble for Ruff. He stood to
lose virtually everything he owned, including his home,
if his Company did not complete the project successful-
ly. And the way it looked to Ruff, the unionization of
Ruff Electric would materially increase the Company's
costs of doing business and, therefore, also increase the
chances of failure.
Ruff testified that he did consider whether signing
with the Union would have advantages for his Company.
I credit that testimony. But the outcome of those consid-
erations never really was in doubt. Ruff concluded that
he wanted Ruff Electric to remain nonunion.
Ruff initially said nothing about the Union's petition to
any of the Company's employees. But once the election
date was set-July 24-Ruff sent letters to the employees
urging them to vote against union representation. On
July 22 Ruff called the employees to a meeting to again
argue against the unionization of Ruff Electric. And on
or about July 23 he met with two employees, this time at
their request where, once again, he argued that the em-
ployees would be better off without a union.2
The voting on July 24 left matters up in the air. The
Board counted five votes for the Union, four against.
There was one challenged ballot. (The challenge was by
Local 5. Months later the Board denied the challenge.
Since the challenged ballot was cast against representa-
2 One employee testified that at this meeting Ruff said that "there
would never be a union at Ruff Electric " But I do not credit that testi-
mony
504
DECISIONS OF THE NATIONAL LABOR RELATIONS BOARD
tion by Local 5-resulting in a five-to-five tie-the
Union lost.)
Ruff Electric Lays Off Anglum and Moss
During the period encompassing the last days of July
and the first days of August , Ruff Electric increased the
pay of three employees, including Anglum and Moss,
and company officials complimented Anglum and Moss
for their good work. Ruff knew by then that Anglum
and Moss supported the Union since in late June Ruff
had attended a meeting at the Board 's Pittsburgh office
in which officials of Local 5 conferred with Anglum and
Moss. And Anglum had been the Union's observer at the
election.
But shortly after that pay increase action , Ruff began
hearing about problems at Clairton. Other contractors
complained that they were being delayed by Ruff Elec-
tric's failure to stay on schedule. On August 7 Ruff re-
sponded by putting a different foreman in place at Clair-
ton (Ron Kuhn) and telling him that if "you [Kuhn]
can't turn that project around in two weeks, I'm serious-
ly thinking about replacing everybody on that project."
Ruff thereupon left on a previously scheduled 10-day va-
cation.
A few days after Ruff returned to work he asked the
Company's secretary to calculate how many hours Ruff
Electric employees had worked at Clairton . At the time
the Company had completed about 69 percent of its
work at Clairton. Ruff got his answer on August 22.
As of the close of business on August 21, Ruff Elec-
tric's employees had logged 8760 hours of work at Clair-
ton. Since Ruff Electric was only 69 percent of the way
toward completion, that 8760 figure suggested that the
Company would use a total of 12,696 hours of employee
time at Clairton by the time the job was finished there.
That, in turn, spelled disaster for Ruff, or something
close to it. In determining what to bid for the Clairton
contract, Ruff had estimated that Clairton would require
10,552 hours to complete. Thus the projected figure of
12, 696 hours was 20 percent higher than the hours upon
which Ruff had based his bid.
Ruff concluded that he had to increase the productivi-
ty of his work force at Clairton , and that he would at-
tempt to do so in two ways. First, by spending more
time at Clairton himself; and second, by, as Ruff testified,
putting "people in there that I felt could complete the
project."
Six Ruff Electric employees had spent a substantial
percentage of their time at Clairton : the two Kuhn
brothers (who had been with Ruff Electric for many
years); Anglum and Moss (who Ruff knew to be union
supporters); and Schwartz and Ward (who had signed
union authorization cards but had done nothing to signal
any prounion views to Ruff).
On Sunday night, August 23 (the day following the
employee-hours calculations for Clairton), Ruff called
Moss to say that "there was no work available" for Moss
and that Ruff Electric accordingly was laying him off
"indefinitely . . . effective immediately." One week later
Anglum got an almost identical call from Ruff.
Given Ruffs belief that low employee productivity at
Clairton was endangering the very existence of Ruff
Electric, some sort of drastic personnel action was in the
cards. The question is why Ruff focused on Anglum and
Moss.
Ruff said the reason was their lackluster performance
at the Clairton site . (Ruff testified that Anglum's and
Moss' productivity was not a problem at other locations.
"I could never understand it. When I would send people
[including Anglum and Moss] to other projects I had no
problem, productivity was just fine.
But when they
would go back to Clairton, it would just drop. There
was some kind of attitude problem. I don't know what it
was.")
As regards Moss, Ruff testified that on a number of
occasions he saw Moss
"just standing there."
Ruff
agreed that he visited Clairton only infrequently and that
he did not say anything to Moss on any of the occasions
on which he did see Moss goofing off. Moreover Ruff
also volunteered that when he expressed his views to the
foreman about Moss' slow pace , the foreman would dis-
agree. 3 Nonetheless, Ruff testified, he was convinced
that Moss was not carrying his share of the load.4
As for Anglum, Ruff testified that "I was very upset
with Dan Anglum" because of low productivity, Ang-
lum's apparent lack of concern about Ruff Electric's
need to speed its pace, and Anglum 's expressions of hos-
tility toward Ruff.
Ruff described one incident involving both Anglum
and Moss that Ruff clearly found very troubling. Both of
them had carried small amounts of material all the way
to the dumpster (a relatively long walk) rather than ag-
gregating discarded material and using a cart to take a
full load.
As for Ruff telling the two employees that they were
being laid off for lack of work rather than firing them,
Ruff gave two different explanations.
One was that Ruff Electric's workload was about to
decrease. As of August 23 (when Ruff laid off Moss),
Ruff Electric had 10 employees; on August 30 (when
Ruff laid off Anglum), the Company was down to 8 em-
ployees. The Company, said Ruff, was at that time in the
process of winding up a number of its projects and did
not need that many employees any longer . Thus, said
Ruff, Ruff Electric did need to lay off two employees.
(Another Ruff Electric official , James Loutzenhiser, tes-
tified to like effect.) Ruff selected Anglum and Moss for
layoff because "they were the least experienced, least
productive people" employed by Ruff Electric.
Ruff's other explanation for telling Anglum and Moss
that they were "laid off" is that Ruff thought that that
terminology would make things easier for both the em-
ployees and for the Company than if Ruff had told
Anglum and Moss that they were fired for cause.
Ruff Electric Recalls Anglum and Moss, Then
Fires Them
Starting in early September the other prime contrac-
tors at Clairton began putting on the record their view
a Neither party called the foreman as a witness.
4 The foreman in those instances was Ron Kuhn Previously Schwartz
had been foreman at Clairton , and he too told Ruff that the Ruff Electric
employees at Clairton were getting their jobs done
RUFF ELECTRICAL CONSTRUCTION
that Ruff Electric's slow pace was delaying the entire
project, and that that slow pace was due to insufficient
manpower.
On September 11, Ruff Electric put Anglum and Moss
back to work. (The impression I got was that Ruff chose
Anglum and Moss, rather than two new employees, in
order to reduce the Company 's
backpay exposure,
whether as the result of litigation before the Board-al-
though neither Anglum nor Moss had yet filed an unfair
labor practice charge-or before some other tribunal.)
On Thursday, September 17, the Board's Pittsburgh
office held a hearing on the ballot that had been chal-
lenged by the Union at the election conducted back in
July. Employees Moss, Kainz, and Ward testified on
behalf of Local 5. Anglum attended the hearing in com-
pany with the Union's representatives, but he did not tes-
tify.
Friday, September 18, was the last day of work at
Ruff Electric for Anglum and Moss. Sometime during
the course of that day Ruff went to check on the work
of the two employees. Ruff testified that he discovered
that they had failed to complete nearly as much as he
had expected . And both Anglum and Moss reacted with
hostility when Ruff spoke to them.
Ruff got upset. When he returned to the Company's
office he complained bitterly about Anglum and Moss: "I
don't know why the S.O.B.'s are trying to do it; I don't
know why the S.O.B.'s won't work."
On Sunday, September 20, Ruff called Anglum and
Moss to say that they were laid off. Notwithstanding
Ruff's use of the "term laid off," in fact Ruffs action
amounted to a discharge. Ruff does not claim otherwise.
Ruff Electric Fires Kainz
Ruff Electric hired additional employees soon after
Anglum and Moss left, all persons whom Ruff had previ-
ously known. But the company remained behind sched-
ule. By November 11 the project's architect was suffi-
ciently concerned about Ruff Electric 's lack of progress
to say so in a letter that ended:
[Y]ou are hereby notified that should any expense
. . . result due to your delaying the [Clairton]
project, the School District will look to you for
compensation.
One of Ruffs responses was to begin working full time
at Clairton, directly supervising the Kuhn brothers plus
Ward and Kainz.
Early in the course of Ruffs supervision of Kainz,
Kainz said something to Ruff that made Ruff think that
Kainz was insisting that Ruff Electric employees under-
take only electrical work, and that Ruff Electric should
hire pipefitters and plumbers to do work traditionally
handled by those crafts. Ruff angrily responded that Ruff
Electric had "won the election" and went on to say that
..you guys are trying to milk me down here on this job
and I'm not going to go for it."5
s Kainz testified that Ruff also said, "we'll never be union " But I do
not credit that testimony
505
Then, early in December, Ruff assigned a minor task
to Kainz-an assignment easily doable within a day. Be-
cause a fellow employee asked Kainz for help with an-
other job, Kainz did not immediately turn to the job
Ruff had assigned him. As a result, the following work-
day Kainz had to tell Ruff that he had not yet finished
that assignment. It is worth noting in this respect that at
the time Kainz was being paid more than $22 an hour as
a journeyman electrician . He had begun receiving that
rate of pay in early September. Previously the Company
had paid Kainz $12.50 an hour.
Finally, on or about December 6-2 or 3 weeks after
Ruff began working full time at Clairton-Ruff instruct-
ed Kainz in a relatively simple task that involved, among
other things, drilling through some plaster. In the course
of that drilling a large chunk of plaster "blew out."
From Kainz's viewpoint and that of a fellow employee,
"it wasn't a big deal." But given the circumstances that
Ruff Electric faced at Clairton, any mishap that required
even a few additional minutes of employee time must
have been aggravating to Ruff. Moreover the architect's
November
11 letter had specifically referred to Ruff
Electric's problems with plaster patching.
Ruff did not see the hole in the plaster until December
7, the day after it happened. But as Kainz testified, when
Ruff did, "all of a sudden Tom just started yelling at
me." As the incident ended Ruff said something like, "if
you can't do the job right, do you want me to get some-
one else to do it?" Kainz responded by saying, "do what
you have to do," and then walked away from Ruff. Ruff
called to Kainz, but Kainz kept walking.
Early in the morning on December 9 Ruff telephoned
Kainz to say that Kainz was terminated as a Ruff Elec-
tric employee "effective today." On that same day Ruff
sent a letter to Kainz that read:
To confirm my phone call to you on December
9, effective December 9, 1987, your employment
with this company is terminated due to your unsat-
isfactory work performance and your poor attitude.
Specifically you have repeatedly failed to com-
plete work assignments as directed and you have
failed to complete work assignments in a timely
manner.
Specifically you have publicly exhibited disre-
spect for your supervisor, myself.
Specifically you have performed unworkman like
work resulting in damages to finishes requiring un-
necessary repairs. .. .
The Fate of Other Prounion Employees at
Ruff Electric
The record shows that employees Anglum, Moss,
Kainz, Schwartz, and Ward signed union authorization
cards, and that Anglum, Moss, Kainz, and Ward ap-
peared at Board proceedings on behalf of the Union, or
at least in company with union representatives.
As discussed above, Ruff Electric fired Anglum, Moss,
and Kainz. Ruff Electric also fired Schwartz (in early
September), and laid off Ward (in February or March
1988). These five employees appear to be the only elec-
506
DECISIONS OF THE NATIONAL LABOR RELATIONS BOARD
tricians whom Ruff Electric either fired or laid off. Thus
of the only five employees the record shows to have
supported the Union, Ruff Electric got rid of all of them.
Yet during the same period Ruff Electric neither laid off
nor fired any other electrician . That disparity could, of
course, be mere coincidence. But those figures do raise
one's suspicions . See, in this regard, NLRB Y. Camco
Inc., 340 F.2d 803 (5th Cir. 1965).
But the General Counsel does not claim that Ruff
Electric's action in respect to either Schwartz or Ward
violated the Act. 6 Moreover Ruff Electric was not put
on notice that its discharge of Schwartz and layoff of
Ward might be used to prove that the company acted
against Anglum, Moss, and Kainz for unlawful reasons.?
Prevailing and Wage Matters
According to the evidence before me, most of Ruff
Electric's work was covered by the Pennsylvania Pre-
vailing Wage Act. In particular, the work at Clairton
was. Under that Act: (1) specified wage rates have to be
paid certain employees (including electricians) engaged
in work covered by that Act; and (2) there is a fixed re-
lationship between the number of journeymen (whose
wages are specified) who can be employed on such
projects and the number of apprentices (whose wages are
not specified.)8 Also according to the evidence before
me, the wages that Ruff Electric paid its journeymen
working at Clairton met the requirements of the Prevail-
ing Wage Act; but the Company did not abide by the
specified journeyman-apprentice ratio.
Ruff Electric deemed Anglum , Moss, and Ward to be
apprentices the entire time it employed the three, and
paid them accordingly. (Anglum never received much
more than half the journeyman's pay rate . Moss and
Ward earned less than half.) And the Company paid
Kainz at an apprentice's rate until September 1987, when
the Company began paying him journeyman 's pay.)
As discussed earlier, representatives of Local 5 started
organizing Ruff Electric's employees in June. One of the
first matters they raised with the employees was that the
Company was not complying with Prevailing Wage re-
quirements. Specifically, as at least some of the employ-
ees understood it, some of the employees being paid at
apprentices levels should have been getting journeyman's
pay.
Sometime during the course of Ruff Electric's work
on the Clairton project, Local 5 filed a complaint with
the Prevailing Wage Division of the Pennsylvania State
Department of Labor and Industry alleging that Ruff
Electric owed three of its employees a total of at least
$70,000 as a result of the Company's Prevailing Wage
violations.
These Prevailing Wage matters may have impinged on
the relationship between Ruff Electric and its employees
in at least two ways.
One is that if the employees believed that they were
being paid at unlawfully low rates, their work , or at least
their attitudes, may have been affected . And that would
tend to bolster Ruffs testimony about poor productivity
and hostile attitudes on the part of Anglum and Moss.
There is, indeed , evidence that such matters did affect
the attitudes of some employees of Ruff Electric. At the
preelection meeting that Ruff held in July, the employees
asked a number of questions pertaining to their appren-
tice status. And the project superintendent at Clairton
for another of the prime contractors testified:
[T]here seemed to be some dissatisfaction, some
conflict that surfaced between employees and the
employer . . . . In hindsight it was about the time
that organizing activities were taking place. .. .
The first time I noticed anything . . . out of the or-
dinary, a group of electricians came in and asked to
see my set of specifications and they seemed inter-
ested in the wages set up . . . . by the specification.
... There was a change in attitude , because at the
beginning of the job the employees seemed to be
relatively satisfied with their jobs. And then during
the time [that] there was some organization activity
... there seemed to be a conflict developed be-
tween [the employees and] the employer.9
The other possible effect of the prevailing wage issue
is that it may have inclined Ruff toward laying off em-
ployees being paid at apprentice rates rather than em-
ployees earning journeyman's pay. The problem with
that theory, however, is that the record does not indicate
when prevailing wage complaints were first filed against
Ruff Electric.
6 Local 5 filed an unfair labor practice charge regarding Ward 's layoff,
but the Union withdrew it at the General Counsel 's suggestion Schwartz
did not file an unfair labor practice charge because , he testified, he had
no interest in litigating his right to reinstatement at Ruff Electric
I Ruff did testify about the reasons he fired Schwartz I received that
testimony over the General Counsel 's objections.
a According to testimony in this proceeding , the journeyman -appren-
tice ratio allowed on prevailing wage jobs is as follows
Journeymen
Apprentices
1
1
2
3
4
2
5
2
6
2
7
3
Ruffs Conspiracy Theory
As far as Ruff is concerned, there is no issue about
whether Anglum, Moss, and Kainz were productive em-
ployees at the times he fired them . He claims that it is
clear that they weren't. The issue to Ruff, instead, is why
the three were unproductive . And the answer, Ruff
claims, is that it was the fault of Local 5 . Ruff contends
that Local 5 wants to destroy Ruff Electric. As Ruff
stated it, "I do not believe that their [Local 5's] actual
intent was to legally organize employees of Ruff Elec-
9 According to the witness, while there was an attitude shift on the
part of Ruff Electric's employees, "it really didn't seem to me that it af-
fected their work."
RUFF ELECTRICAL CONSTRUCTION
tric. . . . I believe their only interest was to put Ruff
Electric out of business." 10
One way the Union allegedly sought to do this was to
institute various legal actions against the Company. In
Ruff's words:
[T]he Union has gone out of its way to interfere
with Ruff Electric and have them [the Company's
management] distracted from their work and suffer
financial damages through complaints and what-
ever. . . . I don't believe that the charges [filed by
Local 5] are legitimate. . . . I think it is just another
tactic of the Union because they lost the election.
Another approach the Union used, Ruff believes, was
to offer journeyman status to Anglum and Moss even
though they did not in fact have the necessary experi-
ence and skills. As Ruff put it, in respect to the relation-
ship between Local 5 and Anglum:
the promise was there [by Local 5] that when he
[Anglum] was ready, they were ready to take him
in. And therefore while he was still under the em-
ployment of Ruff he would have the mental attitude
of, "why should I perform for Ruff Electric at 10
or 12 dollars and hour when I can go over here
with the Union at 21 or 22 dollars an hour." And
the Union, in turn [was] hoping that Ruff would lay
him off or fire him and consequently they could file
a charge against Ruff Electric.
Conclusion
All things considered, my conclusion is that the pre-
ponderance of the evidence fails to show that Anglum's,
Moss', or Kainz' support for Local 5 was a factor in Ruff
Electric's actions against them , or that the company's
discharge of Kainz was related in any way to his testi-
mony at a Board hearing.
Anglum and Moss
When Anglum and Moss were first "laid off" they
were the only employees of Ruff Electric who had pub-
licly manifested their support for Local 5. The Company
reemployed them. But a couple of days after they sup-
ported the Union at a Board hearing in September, the
Company fired both of them. Moreover the only evi-
dence that either Anglum or Moss was unproductive-
Ruff's claimed reason for selecting them for layoff and
discharge-was Ruffs testimony about their work. As
the General Counsel points out, there is no objective evi-
dence that they were any less productive than anyone
else in the Company's employ. In fact the two foremen
for
whom Anglum and Moss worked
(Kuhn and
Schwartz) said that they got their jobs done. Moreover
when Anglum and Moss were first laid off , Ruff had had
only sporadically watched them at work. And the frame-
work in which all this occurred was Ruffs fear and de-
10 Ruff was not on the witness stand when he made this statement or
the two following quoted statements . Rather, he was arguing about the
relevance of certain subpoenaed material.
507
testation of the Union and his belief that the Union was
plotting to destroy his Company.
It is a commonplace observation that any strongly
held belief shapes the way one perceives-indeed, plays
a role in determining what one perceives . Given Ruffs
belief that Local 5 was intent on destroying him and his
knowledge that Anglum and Moss supported the Union,
there obviously is a possibility that Ruff, consciously or
not, kept looking for evidence that Anglum and Moss
were part of Local 5's conspiracy to destroy Ruff Elec-
tric. In this light Ruffs comment about Anglum and
Moss-"I don't know why the S.O.B.'s are trying to do
it; I don't know why the S.O.B.'s won't work"-coupled
with Ruff's admitted belief that Local 5 wanted to put
him out of business and Ruffs knowledge that Anglum
and Moss supported the Union-comes very close to
proving that state of mind . And a boss' state of mind that
ilk spells doom for any employee, since sooner or later
some minor slackening off or mistake by the employee
will permit the boss to convince himself that his conspir-
acy theory is correct.
As I add up the record , it comes extraordinarily close
to showing that this is what happened to Anglum and
Moss-that Ruffs belief about Local 5's hostile inten-
tions produced his perception that Anglum and Moss
were not doing their jobs . Since there is no evidence that
Local 5 or any of Ruff Electric's prounion employees
really was conspiring to destroy the Company, Ruff
Electric's action against Anglum and Moss stemming
from that belief on Ruffs part would be a violation of
Section 8(a)(3) of the Act. See NLRB v. Burnup & Sims,
379 U.S. 21 (1964); Schneider's Dairy, 248 NLRB 1093,
1097 (1980), enfd. mem. 636 F.2d 1210 (3d Cir. 1980).
But there is also evidence to the effect that Ruff did
not hold the prounion employees ' stance against them.
Both Anglum and Moss got pay raises after the two pub-
licly indicated their allegiance to Local 5 . Employee
Ward, who testified on behalf of Local 5 at the Septem-
ber Board hearing, remained in the Company's employ
for 5 or 6 more months. And the General Counsel's does
not claim that the Company violated the Act in any re-
quest when it laid off Ward.
Finally, on Anglum 's and Moss' last day of work for
Ruff Electric-a time when Ruff was desperately trying
to figure out why employee productivity was so much
lower than he had forecast-they were hostile and un-
pleasant in an interaction with Ruff. And previously Ruff
had spotted Anglum and Moss engaged in what Ruff
considered a deliberate
waste of time-walking the
length of the building to dispose of paltry amounts of
trash.
Kainz
In early September Ruff thought enough of Kainz to
promote him to journeyman status . A few weeks later
Kainz testified on the Union's behalf. A few months after
that Ruff fired Kainz . And the event that Ruff claims
precipitated his action against Kainz was, as the General
Counsel accurately describes it, "a relatively insignificant
and commonplace work occurrence."11
1I Br. at I I
508
DECISIONS OF THE NATIONAL LABOR RELATIONS BOARD
It is altogether unlikely that, because of Kainz' testi-
mony, Ruff deliberately schemed to get rid of Kainz,
waiting nearly 3 months to fire Kainz in order to throw
off the scent. On the other hand, it is possible that Ruff's
reaction to Kainz' mistake might have been a product of
the emotional baggage that
Ruff carried concerning
Local 5. That is, given Ruff's knowledge that Kainz sup-
ported the Union, and given Ruff's belief that the Union
wanted to destroy his company, Ruff may have deemed
Kainz' mistake to be proof of Kainz' complicity in the
effort to destroy Ruff Electric.
But the weight of the evidence points elsewhere. Ruff
fired Kainz in early December. At the time Ruff was
under crushing pressure because of problems at Clairton.
In respect to the incident that precipitated Kainz' depar-
ture from Ruff Electric, Ruff had gone out of his way to
instruct Kainz on how to accomplish what appeared to
be a simple task. When Ruff happened by again, he was
confronted by one of the very problems that had led him
to give the instructions to Kainz-a good-sized hole in
the plaster. Ruff exploded in anger, surely more a prod-
uct of the pressures on him than the incident itself. The
record suggests that the matter would have ended there
if Kainz had responded by saying that it wouldn't
happen again, or that he apologized, or something in that
vein.
Instead
Kainz, understandably miffed by what
seemed to him to be Ruff's vast overreaction, replied
curtly to Ruff, then walked away, refusing to return or
even to respond when Ruff called to him. Given Ruffs
state of mind at the time, that behavior on Kainz' part
virtually amounted to a demand to be fired.
Under these circumstances there is no reason to think
that when, soon thereafter, Ruff fired Kainz, that action
had anything to do with Kainz' support for Local 5.12
On these findings of fact and conclusions of law and
on the entire record, I issue the following recommend-
ed"
ORDER
The complaint is dismissed.
12 The General Counsel argues that I should give meaning to Ruff
Electric's failure to call Ron Kuhn as a witness ; the Company's "shifting
defenses," the fact that neither Anglum , Moss, nor Kainz ever received
any written warnings, and that other employees had put in more hours at
Clairton than had Anglum and Moss . But in the circumstances present
here, I think such factors say nothing about Ruff's motivation.
Is If no exceptions are filed as provided by Sec . 102.46 of the Board's
Rules and Regulations,
the findings, conclusions,
and recommended
Order shall, as provided in Sec 102 48 of the Rules, be adopted by the
Board and all objections to them shall be deemed waived for all pur-
poses