Medicare General Information, Eligibility and Entitlement Manual (Pub. 100-01), Ch. 7 § 40.1.1
Standard Terminology Chart
40.1.1 - Standard Terminology Chart
(Rev. 105, Issued: 06-02-17, Effective: 07-03-17, Implementation: 07-03-17)
STANDARD TERMINOLOGY
DESCRIPTION
QUESTION (QCN)
Request for assistance and/or reported potential system
problem. For questions, the MACs and the STC shall
contact the SSM’s helpdesk to log their question.
PROBLEM
Confirmed system and/or documentation problem
Change Request (CR)
Any software modification made to the system as a
result of a CMS mandate or maintainer initiated action
CMS STATUS
CMS needs take action by answering a question,
finalizing an instruction, etc.
NSC (non-system change) STATUS
CMS CR does not require shared system change. May
require A/B MAC maintenance
RESEARCH STATUS
The SSM completes high level review of required
changes by analyzing them and determining the intent
of the change request
REQUIREMENTS (REQS) STATUS
The SSM finalizes the business requirements
WALKTHROUGH STATUS
The SSM presents the systems solution to the CR in a
structured walkthrough discussion with CMS and Beta
testers
WORK STATUS
The SSM completes technical design, coding and unit
testing the system change
STANDARD TERMINOLOGY
DESCRIPTION
ALPHA TESTING
Functional testing performed by the SSM, after
successful unit testing of the new or modified code;
which starts approximately ninety (90) days prior to
the implementation of the Change Request. The testing
verifies all changed components function appropriately
within the full environment at the SSM site in a
controlled environment.
BETA TESTING
This is the second phase of testing after Alpha testing.
The goal of Beta testing is to identify and resolve any
remaining defects before a product/software is released
to a production environment. Beta testing begins eight
weeks prior to the production implementation date of a
quarterly release. The Beta tester continues to test all
iterations of the code through the UAT testing phase
until the release moves to production. The Beta tester
continues to test for two weeks post production or until
they are 100% completed, whichever comes first.
User Acceptance Testing (UAT)
MACs and DME MACs perform UAT testing during
the four weeks prior to the production implementation
date of a quarterly release.
USER STATUS
The SSM returns question to user to provide more
information or examples, assess solution