Medicare General Information, Eligibility and Entitlement Manual (Pub. 100-01), Ch. 7 § 40.3.6
Testing Requirements Applicable to all CWF Data Centers (Hosts)
40.3.6 - Testing Requirements Applicable to all CWF Data Centers (Hosts)
(Rev. 97, Issued: 01-15-16, Effective: 09-21-15, Implementation: 09-21-15)
Each CWF data center or CWF sector host shall:
•
Forward all satellite software and documentation to the satellites (contractors) to which
they serve as the primary production host;
•
Install the CWF quarterly release software in a designated test region;
•
Make the designated test region available their satellites (users) for testing;
•
Coordinate test data, such as beneficiary data, with the user testers;
•
Process all satellite files submitted by the users and return all corresponding reply files
generated for users;
•
Report release problems to the CWF Maintainer and CMS;
•
Verify with CMS that each of its satellites submitted at least one test file during user
testing; and
•
The CWF Host shall support future date testing by the MACs.
•
The CWF Host shall review date simulation schedule submitted by the FISS FWG, MCS
FWG, and DMOP TAG.