Medicare Claims Processing Manual (Pub. 100-04), Ch. 30 § 100.5
Questionable Indemnification Requests Procedure
100.5 - Questionable Indemnification Requests Procedure
(Rev. 1, 10-01-03)
If the contractor receives a request for indemnification that does not appear to meet the
conditions outlined in §100.2, and there is some uncertainty concerning the
indemnification claim, it undertakes development to resolve the issues. If the issues
cannot be adequately resolved, it obtains the assistance of the RO.