Medicare Claims Processing Manual (Pub. 100-04), Ch. 4 § 10.11.3
Selection of the CCR to be Used
10.11.3 - Selection of the CCR to be Used
(Rev. 1657, Issued: 12-31-08, Effective: 01-01-09, Implementation: 01-05-09)
Contractors will use the CCR calculated for the most recent period of time, whether
based on a tentatively settled cost report or a final settled cost report. For example, if the
CCR being used is the tentatively settled CCR for FY 2008, and a tentatively settled CCR
for FY 2009 is determined before the final settled CCR for FY 2008, then the contractor
uses the CCR based on the tentatively settled 2009 cost report.