Medicare Financial Management Manual (Pub. 100-06), Ch. 8 § 150.5
Access Clause Not in Contract
150.5 – Access Clause Not in Contract
(Rev. 27, 12-19-03)
There may be situations where a provider, after applying the criteria of the regulation to a
contract, erroneously decides that the contract does not require an access clause. In such
unusual situations, if the provider demonstrates satisfactorily that the decision not to
include the clause was made in good faith with a reasonable basis(es), and the provider
and subcontractor amends its contract to include an access clause within an acceptable (to
the contractor) period of time after being advised that such amendment is required, the
contractor shall treat the contract as meeting the requirements of the regulation. An
example of a provider response demonstrating good faith with a reasonable basis is a
situation where the provider honestly concluded that the cost or value of the service
component of a goods and services contract was less than $10,000. With respect to
contracts where services or services and goods are still being provided, any such
amendment must make clear that the access clause applies to books, documents, and
records for the full term of the contract and not just for the period following the date of
amendment. If a provider demonstrates satisfactorily that the decision not to include the
clause was made in good faith with a reasonable basis, but cannot amend the contract
because the subcontractor is no longer in business, the contractor shall make a
determination as to the reasonableness of the costs of the subcontractor's services using
available information. The contractor shall take appropriate disallowance and/or
recoupment action with respect to the cost of the services of the subcontractor if either
the provider or subcontractor refuses to amend the contract, or the provider does not
demonstrate satisfactorily that the decision not to include the clause was made in good
faith with a reasonable basis.
There may also be situations in which an individual subcontractor refuses to enter into a
contract containing the required access clause, or will not agree to the addition of the
access clause to an existing contract, which becomes necessary because of a contract
modification. Providers are instructed in PRM-1, §2441 to contact the CMS Regional
Administrator in their area if they have difficulty in finding another organization that will
agree to the clause and offer the needed services at a cost at least as competitive as that of
the original organization. (A provider that does not notify the Regional Administrator but
instead, on its own initiative, contracts with a more expensive subcontractor or omits the
access clause, risks not being reimbursed for the full cost of the services furnished under
the contract.) If the Regional Administrator's efforts to persuade a subcontractor to
include the required clause are unsuccessful, and no other subcontractor is available that
will furnish the services at a competitive price and agree to the access provision, a
provider may find it necessary to contract with another organization willing to accept the
access clause, even though the cost of the services may be greater. In this situation,
providers are requested to contact their contractor before entering into a contract to assure
that the greater cost incurred will be considered during the cost report settlement process;
this is not intended to be a pre-approval requirement.