40 C.F.R. § 125.88
As an owner or operator of a new facility, must I keep records and report?
Cite as 40 C.F.R. § 125.88 (2026)
As an owner or operator of a new facility you are required to keep records and report information and data to the Director as follows: (a) You must keep records of all the data used to complete the permit application and show compliance with the requirements, any supplemental information developed under § 125.86, and any compliance monitoring data submitted under § 125.87, for a period of at least three (3) years from the date of permit issuance. The Director may require that these records be kept for a longer period. (b) You must provide the following to the Director in a yearly status report: (1) Biological monitoring records for each cooling water intake structure as required by § 125.87(a); (2) Velocity and head loss monitoring records for each cooling water intake structure as required by § 125.87(b); and (3) Records of visual or remote inspections as required in § 125.87(c).
- Cross-references to the CFR
- 125.86125.87