40 C.F.R. § 267.197
What are the requirements for ancillary equipment?
Cite as 40 C.F.R. § 267.197 (2026)
You must provide ancillary equipment with secondary containment (for example, trench, jacketing, double-walled piping) that meets the requirements of § 267.195 (a) and (b), except for: (a) Above ground piping (exclusive of flanges, joints, valves, and other connections) that are visually inspected for leaks on a daily basis; (b) Welded flanges, welded joints, and welded connections, that are visually inspected for leaks on a daily basis; (c) Sealless or magnetic coupling pumps and sealless valves, that are visually inspected for leaks on a daily basis; and (d) Pressurized above ground piping systems with automatic shut-off devices (for example, excess flow check valves, flow metering shutdown devices, loss of pressure actuated shut-off devices) that are visually inspected for leaks on a daily basis.
- Cross-references to the CFR
- 267.195