40 C.F.R. Table 1 to Subpart MMMM of Part 60
Model Rule—Increments of Progress and Compliance Schedules for Existing Sewage Sludge Incineration Units
Cite as 40 C.F.R. Table 1 to Subpart MMMM of Part 60 (2026)
Comply with these increments of progress By these dates a Increment 1—Submit final control plan (Dates to be specified in state plan) Increment 2—Final compliance (Dates to be specified in state plan) b a Site-specific schedules can be used at the discretion of the state. b The date can be no later than 3 years after the effective date of state plan approval or March 21, 2016 for SSI units that commenced construction on or before October 14, 2010.