40 C.F.R. § 60.2045
Who must prepare a siting analysis?
Cite as 40 C.F.R. § 60.2045 (2026)
(a) You must prepare a siting analysis if you plan to commence construction of an incinerator after December 1, 2000. (b) You must prepare a siting analysis for CISWIs that commenced construction after June 4, 2010, or that commenced reconstruction or modification after August 7, 2013. (c) You must prepare a siting analysis if you are required to submit an initial application for a construction permit under 40 CFR part 51, subpart I, or 40 CFR part 52, as applicable, for the reconstruction or modification of your CISWI.