40 C.F.R. § 60.2190

What must I submit prior to commencing construction?

Last amended: 2016Year: 2026Length: 71 wordsOfficial source

Cite as 40 C.F.R. § 60.2190 (2026)

You must submit a notification prior to commencing construction that includes the five items listed in paragraphs (a) through (e) of this section: (a) A statement of intent to construct; (b) The anticipated date of commencement of construction; (c) All documentation produced as a result of the siting requirements of § 60.2050; (d) The waste management plan as specified in §§ 60.2055 through 60.2065; and (e) Anticipated date of initial startup.
Cross-references to the CFR
60.205060.2055
40 C.F.R. § 60.2190: What must I submit prior to commencing construction? | Justis AI