40 C.F.R. § 60.5215

By what date must I conduct annual air pollution control device inspections and make any necessary repairs?

Last amended: 2016Year: 2026Length: 79 wordsSubsections: 1Official source

Cite as 40 C.F.R. § 60.5215 (2026)

(a) You must conduct an annual inspection of each air pollution control device used to comply with the emission limits, according to § 60.5220(c), no later than 12 months following the previous annual air pollution control device inspection. (b) Within 10 operating days following an air pollution control device inspection, all necessary repairs must be completed unless you obtain written approval from the Administrator establishing a date whereby all necessary repairs of the affected SSI unit must be completed.
Cross-references to the CFR
60.5220