40 C.F.R. § 60.5790

Who must submit a siting analysis?

Last amended: 2026Year: 2026Length: 65 wordsSubsections: 1Official source

Cite as 40 C.F.R. § 60.5790 (2026)

(a) You must prepare a siting analysis if you commence construction of a large municipal waste combustor after January 23, 2024. (b) You must prepare a siting analysis if you are required to submit an initial application for a construction permit, under 40 CFR part 51, subpart I, or 40 CFR part 52, as applicable, for the reconstruction or modification of your municipal waste combustor.
40 C.F.R. § 60.5790: Who must submit a siting analysis? | Justis AI