40 C.F.R. § 60.6075

When must I submit the initial performance test report?

Last amended: 2026Year: 2026Length: 39 wordsOfficial source

Cite as 40 C.F.R. § 60.6075 (2026)

As specified in § 60.8(a), submit your initial performance test report within 60 days after your municipal waste combustor reaches the maximum load level at which it will operate, but no later than 180 days after its initial startup.