40 C.F.R. § 62.15045
When must I complete each increment of progress?
Cite as 40 C.F.R. § 62.15045 (2026)
(a) You must complete each increment of progress according to the compliance schedule in table 1 of this subpart for Class I and II units. If your Class I or Class II unit is listed in table 9 of this subpart, then you must complete each increment of progress according to the schedule in table 9 of this subpart. ( See § 62.15410 for definitions of classes.) (b) For Class I units ( see definition in § 62.15410) that must meet the five increments of progress, you must submit dioxins/furans stack test results for at least one test conducted during or after 1990. The stack tests must have been conducted according to the procedures specified under § 62.15245 and you must submit the stack test results when the final control plan is due for your Class I MWC unit according to the schedule in table 1 or table 9 of this subpart.
- Cross-references to the CFR
- 62.1524562.15410