40 C.F.R. § 62.866

Compliance schedule.

Last amended: 2016Year: 2026Length: 65 wordsOfficial source

Cite as 40 C.F.R. § 62.866 (2026)

The Compliance Schedules were submitted on December 16, 1985, by the Governor to control total reduced Sulfur emissions from the seven kraft pulp mills identified in § 62.865(a). The schedules specify final compliance dates and enforceable increments to be as expeditiously as practicable but not more than six years from approval of the state regulations; i.e., October 12, 1990. [51 FR 40803, Nov. 10, 1986]
Cross-references to the CFR
62.865
40 C.F.R. § 62.866: Compliance schedule. | Justis AI