40 C.F.R. § 63.5716

When must I conduct a performance test?

Last amended: 2016Year: 2026Length: 80 wordsSubsections: 1Official source

Cite as 40 C.F.R. § 63.5716 (2026)

(a) If your source is an existing source, you must complete the add-on control device performance test no later than the compliance date specified in § 63.5695. (b) If your source is a new source, you must complete the add-on control device performance test no later than 180 days after the compliance date specified in § 63.5695. (c) You must conduct a performance test every 5 years as part of renewing your 40 CFR part 70 or 71 operating permit.
Cross-references to the CFR
63.5695.