40 C.F.R. § 63.7328
How do I demonstrate initial compliance with the operation and maintenance requirements that apply to me?
Cite as 40 C.F.R. § 63.7328 (2026)
You have demonstrated initial compliance if you certify in your notification of compliance status that you have met the requirements of paragraphs (a) through (d) of this section: (a) You have prepared the operation and maintenance plans according to the requirements in § 63.7300(b) and (c); (b) You will operate each by-product coke oven battery and each capture system and control device applied to pushing emissions from a coke oven battery according to the procedures in the plans beginning no later than the compliance date that is specified in § 63.7283; (c) You have prepared a site-specific monitoring plan according to the requirements in § 63.7331(b); and (d) You submit a notification of compliance status according to the requirements in § 63.7340(e).
- Cross-references to the CFR
- 63.728363.730063.733163.7340