42 C.F.R. § 137.366

May the Secretary conduct onsite project oversight visits?

Last amended: 2015Year: 2026Length: 75 wordsOfficial source

Cite as 42 C.F.R. § 137.366 (2026)

Yes, the Secretary may conduct onsite project oversight visits semiannually or on an alternate schedule negotiated in the construction project agreement. The Secretary must provide the Self-Governance Tribe with reasonable advance written notice to assist the Self-Governance Tribe in coordinating the visit. The purpose of the visit is review the progress under the construction project agreement. At the request of the Self-Governance Tribe, the Secretary must provide the Self-Governance Tribe a written site visit report.
42 C.F.R. § 137.366: May the Secretary conduct onsite project oversight visits? | Justis AI