42 C.F.R. § 495.340

As-needed HIT PAPD update and as-needed HIT IAPD update requirements.

Last amended: 2017Year: 2026Length: 108 wordsSubsections: 5Official source

Cite as 42 C.F.R. § 495.340 (2026)

Each State must submit a HIT PAPD update or a HIT IAPD no later than 60 days after the occurrence of project changes including but not limited to any of the following: (a) A projected cost increase of $100,000 or more. (b) A schedule extension of more than 60 days for major milestones. (c) A significant change in planning approach or implementation approach, or scope of activities beyond that approved in the HIT planning advance planning document or the HIT implementation advance planning document. (d) A change in implementation concept or a change to the scope of the project. (e) A change to the approved cost allocation methodology.