43 C.F.R. § 3137.111

When will BLM extend the primary term of all leases committed to a unit agreement or renew all leases committed to a unit agreement?

Last amended: 2016Year: 2026Length: 84 wordsOfficial source

Cite as 43 C.F.R. § 3137.111 (2026)

If the unit operator requests it, the BLM will extend the primary term of all NPR-A leases committed to a unit agreement or renew the leases committed to a unit agreement if any committed lease within the unit is extended or renewed under § 3135.1-5 or § 3135.1-6. If the BLM approves a lease renewal under § 3135.1-6(b), the BLM will require a renewal fee of $100 per acre for each lease in the unit that is renewed. [73 FR 6444, Feb. 4, 2008]
Cross-references to the CFR
3135.1-53135.1-63135.1-6.