43 C.F.R. § 3271.10

What do I need to start preparing a site and building and testing a utilization facility on Federal land leased for geothermal resources?

Last amended: 2016Year: 2026Length: 74 wordsOfficial source

Cite as 43 C.F.R. § 3271.10 (2026)

In order to use Federal land to produce geothermal power, you must obtain a site license and construction permit from BLM before you start preparing the site. Send BLM a plan that shows what you want to do, and draft a proposed site license agreement that you think is fair and reasonable. We will review your proposal and decide whether to give you a permit and license to proceed with work on the site.