43 C.F.R. § 3271.13

How do I obtain approval to build pipelines and facilities connecting the well field to utilization facilities not located on Federal lands leased for geothermal resources?

Last amended: 2016Year: 2026Length: 54 wordsOfficial source

Cite as 43 C.F.R. § 3271.13 (2026)

Before constructing pipelines and well field facilities on Federal lands leased for geothermal resources, you as lessee, unit operator, or facility operator must submit to BLM a utilization plan and facility construction permit addressing any pipelines or facilities. Do not start construction of your pipelines or facilities until BLM approves your facility construction permit.
43 C.F.R. § 3271.13: How do I obtain approval to build pipelines and facilities connecting the well field to utilization facilities not located on Federal lands leased for geothermal resources? | Justis AI