43 C.F.R. § 3273.10

When do I need a site license for a utilization facility?

Last amended: 2016Year: 2026Length: 63 wordsOfficial source

Cite as 43 C.F.R. § 3273.10 (2026)

You must obtain a site license approved by BLM, unless your facility will be located on lands leased as described in § 3273.11. Do not start building or testing your utilization facility on public lands leased for geothermal resources until BLM has approved both your facility construction permit (see § 3272.14) and your site license. The facility operator must apply for the license.