43 C.F.R. § 404.37

How will Reclamation determine the appropriate non-Federal share of construction costs?

Last amended: 2016Year: 2026Length: 58 wordsSubsections: 2Official source

Cite as 43 C.F.R. § 404.37 (2026)

Reclamation will determine the appropriate non-Federal share of construction costs in the process of developing the feasibility report. The non-Federal cost-share will be: (a) At least 25 percent of the total construction costs; and (b) An additional amount based on your capability to pay, as appropriate, to be determined by Reclamation based on the factors in § 404.39.
Cross-references to the CFR
404.39.
43 C.F.R. § 404.37: How will Reclamation determine the appropriate non-Federal share of construction costs? | Justis AI