46 C.F.R. § 159.007-5

Production inspections and tests: Application for acceptance.

Last amended: 2016Year: 2026Length: 93 wordsSubsections: 2Official source

Cite as 46 C.F.R. § 159.007-5 (2026)

(a) If the applicable subpart requires production inspections and tests by an independent laboratory, the manufacturer must select a laboratory and submit an application for acceptance that meets § 159.010-5(a) unless the laboratory— (1) Is listed in the subpart; or (2) Is accepted by the Commandant for approval inspections and tests of the equipment or material under § 159.005-7(a)(1). (b) If the manufacturer wants to follow the laboratory's procedures for production inspections and tests instead of meeting the Coast Guard procedures under this subchapter, the application must contain a description of those procedures.
Cross-references to the CFR
159.005-7159.010-5