46 C.F.R. § 170.095
Data submittal for a vessel equipped to lift.
Cite as 46 C.F.R. § 170.095 (2026)
The following data must be submitted with the plans required by § 170.075 if the vessel is engaged in lifting and is required to comply with subpart B of part 173 of this chapter:
(a) A graph of maximum hook load versus maximum crane radius.
(b) A table of crane radius versus the maximum distance above the main deck to which the hook load can be raised.
(c) A table showing maximum vertical and transverse moments at which the crane is to operate.
- Cross-references to the CFR
- 170.075